Select Group · Dubai Maritime City · Construction Update
Nautica One Construction Update - December 2025
December 2025 Inspection Confirms Nautica One Reaches 46.73% Construction Progress in Dubai Maritime City
Superstructure continues to rise as facade installation and MEP systems accelerate across Nautica One, verified at 46.73 percent in the 4 December 2025 RERA inspection cycle.
Direct advisor access. Every message answered personally, never by a call center.
Verified DLD Inspection Data
Nautica One Construction Snapshot
A 14.38 point rise since the August 2025 inspection carries Nautica One past the halfway mark of construction and into the envelope and MEP stage, where certified readings matter most for the milestone payments still ahead in the plan.
Nautica One by Select Group
2781
Active
46.73%
4 December 2025
19 October 2023
328 residential units
22,983.78 sq m
Q4 2026
Data source: RERA inspection conducted on 4 December 2025, tracked against DLD inspection records. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: July 2026.
Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else.
This Inspection Cycle
Nautica One Construction Progress Summary
Between the August and December 2025 inspections, Nautica One advanced from 32.35% to 46.73%, a 14.38 point gain driven by continuing superstructure, facade close-in on the waterfront elevations, and MEP installation. Past the mid point now, the site is shifting from raising the tower to enclosing and servicing it.
- Enabling, foundation, and substructure works across plot 392
- Podium levels and the lower structural core
- Superstructure cast through the lower and middle typical floors
- Superstructure continuing through the upper typical floors
- Facade and external envelope on the sea facing elevations
- MEP installation advancing behind the rising structure
- Internal blockwork and first fix across the 328 units
- Remaining superstructure to topping out
- Full facade close-in and interior fit out
- Further RERA inspection cycles toward 100%
- Completion certificate and handover in Q4 2026
Payment Linked Progress
What 46.73% Progress Means for Nautica One Buyers
Most Dubai off plan payment plans tie installments to certified construction milestones, so at 46.73% a larger share of the plan has been triggered and the installments still ahead come into sharper focus. Past the mid point of construction, four actions matter most for Nautica One buyers.
Verify the escrow account
Any milestone payment still ahead should go only to the DLD regulated escrow account registered for project 2781. Nautica One escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.
Reread your SPA milestone schedule
With more of the plan now triggered by certified progress, check how your sale and purchase agreement links each installment to a milestone. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the certified milestones.
Track each certified reading
Past the mid point, each RERA cycle now unlocks a larger share of the 40/60 plan. The Nautica One construction updates hub keeps every reading in one place through to handover.
Understand the snagging window
At 46.73% the pre handover inspection is still ahead, but knowing the process now means the booking is ready when Nautica One nears completion. The Nautica One snagging inspection guide covers the window before acceptance.
General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.
Buying at 46.73%?
Entering past the mid point of construction shortens the remaining wait while keeping the largest installment for completion, and the two bedroom tier from AED 2.10M clears the AED 2M Golden Visa property threshold. Every payment goes to the DLD-registered escrow account for project 2781, released against certified construction progress.
- Certified through foundation, podium, and the middle floors
- Roughly ten to twelve months to the Q4 2026 handover window
- About 60% of the 40/60 plan still due at completion
- Construction risk carried from excavation onward
- Two to four years of waiting is the usual delivery horizon
- Full installment runway, priced at launch levels
Unit availability at Nautica One shifts between inspection cycles; confirm the current list before you commit.
About the Development
Nautica One Project Details

With foundation, podium, and the middle typical floors complete and the superstructure continuing upward, Nautica One is a mid construction development of 328 one and two bedroom waterfront apartments in Dubai Maritime City. Starting prices: AED 1.40M ≈ USD 381K.
For buyers entering at this stage, the trade off is a shorter remaining wait and fewer cycles to track than at launch, set against an earlier position in the payment plan, with handover expected in Q4 2026 per the current project record.
Nautica One by Select Group Project GuideSite Context This Cycle
Explore Nautica One Location on Dubai Map
Nautica One occupies plot 392 on the Dubai Maritime City peninsula between Port Rashid and Dubai Drydocks World, its tower turned toward the marina and open water; that waterfront orientation puts facade close-in and external works on the sea facing elevations among the most visible packages in this envelope stage.
Because Dubai Maritime City already carries completed roads, peninsula utilities, and direct access to Sheikh Zayed Road, Nautica One is enclosing into a connected district rather than an emerging one, which matters for buyers weighing the Q4 2026 handover against their occupancy or rental plans. See the project's position on the interactive Dubai real estate map.

Buyer Resources for This Project
Investing in Nautica One During Envelope and MEP Construction
The envelope and MEP band is where payment protection, residency eligibility, and handover preparation begin to converge. Each resource below is matched to where Nautica One stands right now.

Nautica One Construction Updates
This page: the verified December 2025 inspection record for Nautica One, from foundation through mid construction.
Nautica One Golden Visa
Check whether a two bedroom Nautica One purchase clears the AED 2M Golden Visa residency threshold.
Read Nautica One Golden Visa Guide
Nautica One Escrow Account
Confirm the DLD-registered escrow account for project 2781 before releasing your next milestone installment.
Verify Nautica One Escrow Account
Nautica One Snagging Inspection
Learn the pre handover snagging process now, well before Nautica One reaches its inspection window.
Read Nautica One Snagging GuideUpdate Timeline
Other Nautica One Construction Updates
Follow Nautica One across the August 2025, December 2025, and April 2026 inspection cycles as construction advances toward the expected Q4 2026 handover.
Where This Update Fits
Explore Nautica One Structure
This December reading is one node in the wider record: the peninsula around the site, the developer behind it, and the listings it competes with.

Dubai Maritime City Properties for Sale
Compare available Dubai Maritime City listings as Nautica One passes the mid point of construction.
Dubai Maritime City Properties for Sale
About Dubai Maritime City
See how Dubai Maritime City's peninsula masterplan, marina, and roads frame Nautica One's waterfront position.
Dubai Maritime City Community Guide
Select Group Developer Profile
Review Select Group's delivery record across Dubai and international towers before your remaining payment decisions.
Select Group Developer ProfileFAQs
Nautica One Construction Progress in December 2025: Frequently Asked Questions
As of the RERA inspection conducted on 4 December 2025, Nautica One stands at 46.73% construction progress in the DLD project register.
Nautica One moved from 32.35% in August 2025 to 46.73% on 4 December 2025, a gain of 14.38 points. The increase reflects continuing superstructure, facade close-in on the waterfront elevations, and MEP installation across the Dubai Maritime City tower.
The December 2025 record shows the project past the mid point of construction at 46.73%, with 53.27 percentage points still to complete before certification. Handover is expected in Q4 2026 on the current project record; how the remaining inspection cycles progress toward completion is tracked on the Nautica One construction updates hub.
Yes. Expected completion dates can be revised between inspection cycles as construction progresses. The Q4 2026 window reflects the record as of December 2025; any revision would appear in a later update on this cluster.
With foundation, podium, and the lower and middle floors complete as of the 4 December 2025 inspection, site activity centers on the superstructure through the upper typical floors, the external envelope on the sea facing elevations, MEP installation, and internal blockwork and first fix across the 328 units.
At 46.73% the project is past the mid point but still ahead of handover, so buyers weighing a resale or assignment before completion should first confirm whether Select Group permits assignment at this stage and on what terms. The assignment conditions, any developer transfer fee, and the minimum paid percentage are set in your SPA and the developer transfer policy, not by the inspection reading itself.
A Question the FAQ Can Not Answer?

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is helping you read the December 2025 inspection record for Nautica One correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.