Nice 2 at DAMAC Lagoons by DAMAC Construction Update - August 2026

August 2026 DLD Register Reading Puts Nice 2 at DAMAC Lagoons at 83.88% Construction Progress

Internal works, the external envelope, MEP, finishes, external works and infrastructure were progressing at advanced stages when RERA inspected Nice 2 on 17 August 2026.

Direct advisor access. Every message answered personally, never by a call center.

83.88%DLD Register Progress
17 August 2026Inspection Date
Q2 2027Expected Completion
2336DLD Project Number

DLD Register and RERA Report Data

Nice 2 at DAMAC Lagoons Construction Snapshot

An 11.14 point rise from the previous register reading of 72.74% brings Nice 2 to 83.88% and into the finishing band, where the record begins to shape snagging, completion-payment and handover planning for its 434 villas and townhouses.

Project Name

Nice 2 at DAMAC Lagoons by DAMAC

Project Number

2336

Project Status

Active

Construction Progress

83.88%

Inspection Date

17 August 2026

Construction Start

28 February 2022

Total Units

434 villas and townhouses

Total Built Area

71,172.86 sq m

Expected Completion

29 July 2025

Data source: the DLD project register (Dubai REST) for project 2336, inspection report dated 17 August 2026, read with the RERA progress monitoring report of the same date. The RERA report prints no percentage, so 83.88% is the DLD register reading; the register shows the previous 72.74% reading without a date. Expected completion is DAMAC's estimate of Q2 2027, while the registered completion date is the date the DLD register holds. The hero image is a DAMAC project rendering, not a photograph of the site. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: October 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Nice 2 at DAMAC Lagoons Construction Progress Summary

The RERA progress report of 17 August 2026 describes the structural phases of Nice 2 as substantially completed and gives the project the status Main Contract, Progressing. What remains is spread across finishing packages inside and around the villas and townhouses, each recorded at an advanced stage rather than at a starting point.

Completed
  • Enabling works, substantially completed per the RERA report
  • Foundations and substructure for the 434 homes
  • Superstructure, substantially completed per the same report
In Progress at 83.88%
  • Internal works and internal finishes at advanced stages
  • External envelope works across the villa and townhouse rows
  • MEP systems: mechanical, electrical, and plumbing
  • External works and infrastructure, with mobilization listed as ongoing
Ahead of Handover
  • Further register readings toward 100%
  • Completion notice and the 50% completion payment under the SPA
  • Handover within DAMAC's Q2 2027 estimate
Next inspectionPosted in the DLD project register after the next RERA site visit; this page records the 17 August 2026 reading only.
Completion targetQ2 2027 per DAMAC's current estimate, roughly ten months after the 17 August 2026 reading.
Remaining distance16.12 percentage points separate the August 2026 reading from 100% on the register.

Payment Linked Progress

What 83.88% Progress Means for Nice 2 Buyers

DAMAC's published 50/50 launch plan for Nice 2 counts its instalments from the sale date rather than from construction milestones, so the 83.88% reading matters most for the 50% due on completion and for the checks that come before it. At this stage of Nice 2, four actions matter most.

Before Remaining Instalments

Verify the escrow account

Any payment still ahead of handover should go only to the DLD regulated escrow account registered for project 2336, held with Emirates NBD. Nice 2 escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before the Handover Notice

Reread your SPA completion terms

Check how your sale and purchase agreement sets the 50% completion payment and the handover notice period, and map those clauses against DAMAC's Q2 2027 estimate. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

Window Open Now

Book the snagging window

At 83.88% on the register, Nice 2 is past the roughly 70% point at which the standard booking window for a pre handover inspection opens. Nice 2 snagging inspection guide covers roof, facade and garden checks for villas and townhouses before acceptance.

Every Cycle

Track the remaining cycles

16.12 register points remain between the August 2026 reading and 100%. The Nice 2 construction updates hub collects each posted reading in one place.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 83.88%?

Entering Nice 2 at this stage trades instalment runway for visibility: the superstructure is recorded as substantially completed, the open work sits in finishing packages, and the remaining choice is between the homes still offered. Every payment goes to the DLD-registered escrow account for project 2336, released against construction progress recorded on the DLD register.

Entering Now at 83.88%
  • Recorded structure: the RERA report of 17 August 2026 is the risk picture
  • Roughly ten months from the reading to DAMAC's Q2 2027 estimate
  • 50% of the 50/50 plan due on completion, with your schedule set in the SPA
Typical Launch Entry
  • Construction risk carried from enabling works to handover
  • Two to four years of waiting is the usual delivery horizon
  • Longer instalment runway, priced at launch levels
AED 1.70M ≈ USD 463KStarting Price
50/50 Payment Plan50% Due on Completion
Q2 2027 (Estimated)Expected Handover
Ask What Is Available at Nice 2

Limited Units Available per the Nice 2 project page as of this update; availability shifts between cycles. The 50/50 figures are DAMAC's published launch plan, and the terms for a purchase today are confirmed in the SPA.

About the Development

Nice 2 at DAMAC Lagoons Project Details

Nice 2 by DAMAC in DAMAC Lagoons project rendering of a contemporary two-storey villa with a garden, swimming pool and shaded terrace in Dubai - Presented by Tohid Fetrat
DAMAC Lagoons · DAMAC

With its superstructure recorded as substantially completed, Nice 2 is a finishing stage cluster of 434 villas and townhouses, described in the RERA report as G+1 and G+2 homes, offered as 4 and 5 Bedroom Townhouses and 6 Bedroom Villas. Starting prices: AED 1.70M ≈ USD 463K.

For buyers entering at this stage, the trade off is a shorter wait against a shorter instalment runway before the 50% completion payment, with handover estimated by DAMAC for Q2 2027.

Nice 2 at DAMAC Lagoons Project Guide

Site Context This Cycle

Explore Nice 2 at DAMAC Lagoons Location on Dubai Map

Nice 2 is one of the destination-themed clusters of DAMAC Lagoons, the community DAMAC positions along Hessa Street opposite DAMAC Hills, and DAMAC's cluster plan sets its homes in townhouse rows and detached villas along internal streets, which is why the August 2026 report lists external works and infrastructure beside the finishing packages at each home.

DAMAC describes the community as within minutes of Mohammed Bin Zayed Road, Emirates Road and Al Khail Road, yet its clusters are being delivered in stages, so buyers planning occupancy or rental from the Q2 2027 estimate should weigh which shared amenities will be operating by then. See the cluster's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Nice 2 at DAMAC Lagoons on Dubai Map

Buyer Resources for This Project

Investing in Nice 2 at DAMAC Lagoons During Final Construction Progress

At 83.88%, Nice 2 sits where escrow checks, residency planning, and pre handover inspection begin to overlap. Each resource below is matched to where the cluster stood in August 2026.

Nice 2 by DAMAC in DAMAC Lagoons construction updates cover image featuring a project rendering of villa facades, roadside parked cars and flowering landscaping in Dubai - Presented by Tohid Fetrat
You Are Here

Nice 2 Construction Updates

This page: the 17 August 2026 register reading and RERA report notes for Nice 2.

Nice 2 by DAMAC in DAMAC Lagoons Golden Visa concept graphic showing a gold card over rendered villa facades, roadside cars and flowering planting in Dubai - Presented by Tohid Fetrat

Nice 2 at DAMAC Lagoons Golden Visa Through the 5 Bedroom Townhouse

Nice 2 at DAMAC Lagoons, a 434-home DAMAC cluster, qualifies individually at its 5 bedroom townhouse and 6 bedroom villa only.

Read Nice 2 Golden Visa Guide
Nice 2 by DAMAC in DAMAC Lagoons escrow account concept graphic showing a shield and padlock over a rendered villa exterior with a garden in Dubai - Presented by Tohid Fetrat

Nice 2 at DAMAC Lagoons: The Second Nice Release's Escrow

Nice 2 at DAMAC Lagoons holds 434 units in Emirates NBD escrow as DLD project 2336, 83.88% certified in August 2026.

Verify Nice 2 Escrow Account
Nice 2 by DAMAC in DAMAC Lagoons snagging inspection concept graphic showing an inspection icon over a furnished room with shelving, desks and easels in Dubai - Presented by Tohid Fetrat

Nice 2 at DAMAC Lagoons Snagging for 6 Bedroom Villas and Townhouses

Nice 2 at DAMAC Lagoons holds 434 DAMAC townhouses and villas, with a design theme drawn from the French Riviera.

Book Nice 2 Snagging Inspection

Update Timeline

Other Nice 2 at DAMAC Lagoons Construction Updates

August 2026 is the first monthly record for Nice 2 on this site; each newer register reading joins the hub as it is posted.

All Nice 2 at DAMAC Lagoons Construction Updates

FAQs

Nice 2 at DAMAC Lagoons Construction Progress in August 2026: Frequently Asked Questions

The DLD project register shows Nice 2 at DAMAC Lagoons, project 2336, at 83.88% construction progress on the inspection report dated 17 August 2026. The previous reading shown on the same register screen is 72.74%, which the app displays without a date. The RERA progress report of 17 August 2026 prints no percentage of its own, so 83.88% is the register figure, not a number taken from the report.

Q2 2027 is DAMAC's estimated handover for Nice 2 as of this update, and the 17 August 2026 reading leaves 16.12 register points to reach 100%. The registered completion date held on the DLD register is earlier than that estimate and has not been revised there as of the August 2026 record, so buyers should confirm the current handover date with DAMAC in writing and check the register for any revision before relying on either date. How the register date and the estimate are tracked across the project is covered on the Nice 2 construction updates hub.

The report records enabling works, foundations, substructure and superstructure as substantially completed, and internal works, the external envelope, MEP, internal finishes, external works and infrastructure as progressing at advanced stages, with mobilization still listed as ongoing. It also includes inspection photographs; these are record documents and are not reproduced on this page.

It is the progress status the RERA report of 17 August 2026 gives Nice 2, indicating that work was continuing under the main construction contract and had not reached a completed status. It is a stage label rather than a measurement, so it is read together with the 83.88% register figure, not in place of it.

In the Dubai REST app the project is listed under its register name, Damac Lagoons - Nice 2, with project number 2336. Its project details screen shows the inspection report dated 17 August 2026 with the current and previous readings, and the report itself can be downloaded from the same screen. The register name differs from the marketing name, so searching by the project number is the more reliable route.

No. The image at the top of this page is a DAMAC project rendering of the planned villa facades and garden, and it is not evidence of completed or ongoing construction. Site progress for August 2026 is documented by the DLD register reading and the RERA report of 17 August 2026, whose inspection photographs are not published here.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the August 2026 inspection record for Nice 2 at DAMAC Lagoons correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts