DAMAC · DAMAC Lagoons
Nice at DAMAC Lagoons Construction Updates
The DLD Register Record of a Riviera-Themed Townhouse and Villa Cluster
Nice at DAMAC Lagoons reached 93.71% at its 10 August 2026 inspection, leaving finishing work across its townhouse and villa streets before a Q4 2026 handover.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Nice at DAMAC Lagoons at a Glance
Nice at DAMAC Lagoons by DAMAC is a 509-home cluster of 4 and 5 bedroom townhouses and 6 bedroom villas inside DAMAC Lagoons, registered with the Dubai Land Department as project 2335 on 13 December 2021. Construction started on 28 February 2022, and the register read 93.71% on 10 August 2026, 1,624 days into the build. Because the cluster is low-rise and spread along streets of homes rather than stacked in a single building, the work still open at that reading sits in finishes, envelopes, building services and the shared roads and infrastructure between the plots.
2335
Active
28 February 2022
509 villas and townhouses
83,375.88 sq m
29 July 2025
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Nice at DAMAC Lagoons Construction Update Timeline
The Nice at DAMAC Lagoons record opens with registration on 13 December 2021 and a construction start 77 days later, on 28 February 2022. Its one dated reading so far is 93.71% on 10 August 2026; the register lists 92.78% as the previous inspection but gives it no date, so that figure sits on the track below as an unlabelled dot rather than a table row. The August 2026 row links the full monthly update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| August 2026 | 93.71% | 10 August 2026 | View the August 2026 update |
Reading the dates: the DLD register lists 29 July 2025 as the registered completion date for project 2335, and the register reading of 10 August 2026 recorded 93.71%. That registered date is the completion date entered on the project record, not a handover notice, and the register entry can be updated; handover for Nice at DAMAC Lagoons is estimated for Q4 2026. Confirm the date that applies to your home with DAMAC and on Dubai REST.
Pace Analysis
How Fast Nice at DAMAC Lagoons Has Been Built
With one dated reading on record, pace at Nice at DAMAC Lagoons can only be read as arithmetic across the whole build, set against the distance left to the stated handover quarter:
- Feb 2022 to Aug 2026: structure through finishing, start to 93.71% on 10 August 2026, whole-build averageAbout 1.73 points per month
- Aug 2026 to Q4 2026: finishing and commissioning, the remaining 6.29 points to 100% by 31 December 2026, arithmetic, not a forecastAbout 1.32 points per month
Both figures are arithmetic, not a forecast. The first spreads 93.71 points over the 1,624 days between the 28 February 2022 start and the 10 August 2026 reading, counted in 30-day months; the second spreads the 6.29 points still open over the 143 days to the end of Q4 2026. The record cannot show a curve yet: the 92.78% previous reading carries no date, so the 0.93-point gap between it and the August figure is a difference, not a rate. What the two numbers do show is the kind of work left. With the RERA report of 10 August 2026 recording enabling, foundation and structural works as substantially completed, the open items are internal finishes, envelopes, MEP and the external works and infrastructure running between the homes, packages that usually move a register percentage in small steps. For an end user that points to handover preparation now; for an investor it points to the next register reading rather than to any rate read into this one, and neither figure is a promise of a handover date.
Get the Next Inspection Figure First
Tell me you are tracking Nice at DAMAC Lagoons and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Nice at DAMAC Lagoons
A register percentage only means something next to what it measures. The project guide covers the 509 homes this record is tracking toward handover:

Nice at DAMAC Lagoons: French Riviera Townhouses and Villas
Nice at DAMAC Lagoons is a DAMAC cluster of 509 townhouses and villas, Mediterranean outside with vintage and contemporary interiors.
View the Nice at DAMAC Lagoons Project GuideConsidering a Near-Handover Entry?
Limited units remain available at Nice at DAMAC Lagoons, and the choice of home types narrows as the cluster approaches its Q4 2026 handover. If this construction record is your starting point, ask me which homes are still offered before you weigh them against resale homes nearby.
Ask About Remaining Availability on WhatsAppStage Record
Nice at DAMAC Lagoons Build Stages, Mapped to the Inspections
Each stage below is pinned to the dates in project 2335's own register and to the RERA report of 10 August 2026, so you can see where Nice at DAMAC Lagoons stood at each point instead of reading a generic sequence.
Registration and Site Activation
Project 2335 was registered with the DLD on 13 December 2021, and construction started 77 days later, on 28 February 2022, opening the record this page tracks.
Enabling Works and Foundations
Enabling and foundation works across the cluster's plots, both recorded as substantially completed in the RERA report of 10 August 2026.
Structural Works on the Homes
Structural works on the 509 villas and townhouses, likewise reported as substantially completed at the 10 August 2026 inspection.
Envelope, MEP, and External Works
External envelope, MEP systems, external works and infrastructure, each placed at an advanced stage in the 10 August 2026 report.
Finishing and Handover Preparation
Internal works and internal finishes at advanced stages, with the register at 93.71% on 10 August 2026 and handover estimated for Q4 2026.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Nice at DAMAC Lagoons's own record.
Buyer Position
Tracking Your Position at Nice at DAMAC Lagoons
This page is one of four project resources that together cover a Nice at DAMAC Lagoons purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Nice at DAMAC Lagoons Construction Updates
This page: the full register record for Nice at DAMAC Lagoons, from 2022 start to handover.

Nice at DAMAC Lagoons Golden Visa: Two of Three Home Types
Nice at DAMAC Lagoons, 509 DAMAC villas and townhouses, qualifies at 5 bedroom townhouse and 6 bedroom villa, not 4 bedroom.
Read the Nice at DAMAC Lagoons Golden Visa Guide
Nice at DAMAC Lagoons Escrow: 93% Certified at Emirates NBD
Nice at DAMAC Lagoons, DLD project 2335, keeps 509 units' payments at Emirates NBD, 93.71% certified August 2026.
Verify the Nice at DAMAC Lagoons Escrow Account
Nice at DAMAC Lagoons Snagging for Riviera-Inspired Homes
Nice at DAMAC Lagoons is a DAMAC Properties cluster of 509 homes, 4 and 5 bedroom townhouses and 6 bedroom villas.
Book Nice at DAMAC Lagoons SnaggingApproaching Handover
Between 93.71% and Handover: What Nice at DAMAC Lagoons Buyers Should Do Now
The 6.29 points left after the 10 August 2026 reading are finishes, envelopes, MEP and external works across the cluster's streets rather than new structure, so preparation on the buyer's side now carries more weight than anything visible on site. Your SPA sets how long you have, once a completion notice is issued, to pay the completion balance and attend handover, and that period can be short, so the three steps below belong before Q4 2026, not after the notice arrives.
First, book an independent inspection of your townhouse or villa so finishes, joinery, garden areas and building services are documented before you accept the keys; the Nice at DAMAC Lagoons snagging guide sets out the timing around handover.
Second, make sure every remaining instalment, and the 50% completion payment under the developer's 50/50 Payment Plan above all, goes into the Emirates NBD trust account registered for project 2335, as explained on the escrow account page for Nice at DAMAC Lagoons.
Third, if your home is one of the types priced at or above the Golden Visa threshold, read the Nice at DAMAC Lagoons Golden Visa guide before handover, because the move from Oqood registration to title deed affects when and how an application can be made.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore DAMAC Lagoons Structure
A cluster record reads differently once you see what surrounds it. These three pages place the Nice at DAMAC Lagoons build inside its resale market, its community and its developer's wider portfolio:

DAMAC Lagoons: Mediterranean-Themed Villas, Townhouses, Apartments and Offices
DAMAC Lagoons sits opposite DAMAC Hills in Dubailand, with 11 themed clusters and 3 projects of villas, townhouses, apartments and offices.
See DAMAC Lagoons Properties for Sale
DAMAC Lagoons Community Overview
Read the DAMAC Lagoons guide: Mediterranean-themed clusters and crystal lagoons across a 45 million sq ft waterfront masterplan.
Explore the DAMAC Lagoons Community
DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations
Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.
View the DAMAC Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Nice at DAMAC Lagoons Construction Updates Frequently Asked Questions
At the DLD register reading of 10 August 2026, Nice at DAMAC Lagoons stood at 93.71%, leaving 6.29 percentage points before 100%. The RERA report of the same date lists internal works, the external envelope, MEP, external works, internal finishes and infrastructure as being at advanced stages, with handover estimated for Q4 2026. Where each of those packages sits in the build is set out in the stage record above.
The RERA report of 10 August 2026 for Nice at DAMAC Lagoons describes the work by stage and gives a progress status rather than printing a figure, so the percentage on this page comes from the Dubai Land Department project register. That register shows 93.71% on 10 August 2026, 0.93 points above the previous inspection reading of 92.78%, which it lists without a date. The reading and the report are covered in the August 2026 construction update for Nice at DAMAC Lagoons.
Progress at Nice at DAMAC Lagoons is tracked through two official records for project 2335: the percentage posted in the Dubai Land Department project register, read on Dubai REST, and the RERA progress report that describes each stage of work. This page adds every dated register reading as a timeline row; with the 10 August 2026 reading of 93.71% the record holds one dated row, and the undated 92.78% previous reading appears on the track only. The rows are in the inspection timeline above.
The DLD register lists 29 July 2025 as the registered completion date for Nice at DAMAC Lagoons, while handover is estimated for Q4 2026 and the register read 93.71% on 10 August 2026. The registered date is the completion date entered on the project record; it is not a handover notice, and the register can be updated. Buyers confirm the date that applies to their home with DAMAC in writing and check project 2335 on Dubai REST, and this page's record is updated when the next reading is posted.
Nice at DAMAC Lagoons was registered with the Dubai Land Department on 13 December 2021 as project 2335, and construction started 77 days later, on 28 February 2022. The register lists 29 July 2025 as the registered completion date, and the reading of 10 August 2026 recorded 93.71%, 1,624 days after the start, with handover estimated for Q4 2026.
Averaged over the whole build, Nice at DAMAC Lagoons gained about 1.73 percentage points per month between the 28 February 2022 start and the 93.71% reading of 10 August 2026. Reaching 100% by the end of Q4 2026 would take about 1.32 points per month over the remaining 143 days, which is below that average. Both figures are arithmetic using 30-day months, not a forecast and not a promise of a handover date; the working is in the pace analysis above.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Nice at DAMAC Lagoons construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.