Ocean Point by Emaar in Rashid Yachts & Marina project rendering used for the April 2026 construction update showing the planned furnished balcony, landscaped courtyard and residential buildings in Dubai - Presented by Tohid Fetrat

Emaar · Rashid Yachts & Marina · Construction Update

Ocean Point Construction Update - April 2026

DLD Register Shows Ocean Point at 26.95% After the 21 April 2026 Inspection in Rashid Yachts & Marina

Structure, internal works and MEP works were progressing at Ocean Point when RERA inspected on 21 April 2026, with enabling, piling and foundations recorded complete.

Direct advisor access. Every message answered personally, never by a call center.

26.95%DLD Register Reading
21 April 2026Inspection Date
Q2 2028Expected Completion
2975DLD Project Number

DLD Register Inspection Data

Ocean Point Construction Snapshot

An 11.49 point rise over the previous DLD register reading of 15.46%, which the register shows without a date, puts Ocean Point at 26.95% on 21 April 2026 and inside the superstructure band, the stage where construction-linked instalments and the evidence that supports them start to matter most.

Project Name

Ocean Point at Rashid Yachts & Marina by Emaar

Project Number

2975

Project Status

Active

Construction Progress

26.95%

Inspection Date

21 April 2026

Construction Start

06 July 2024

Total Units

217 Residential

Total Built Area

23,551.02 sq m

Expected Completion

Q2 2028

Data source: DLD project register reading dated 21 April 2026 and the RERA Independent Progress Monitoring Report from the inspection on the same date; the earlier 15.46% reading appears in the register without a date. This page records the April 2026 cycle; the hero image is a developer rendering, not a site photograph. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: April 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Ocean Point Construction Progress Summary

Read 654 days after construction started on 06 July 2024, the April 2026 record shows Ocean Point past its below-ground phase, with the RERA report setting progress status at Main Contract, Progressing. At that visit the effort had moved to the frames of two apartment buildings of ground plus eight floors and a cluster of two-level townhouses, with internal and MEP packages running alongside.

Completed
  • Enabling works on the Ocean Point plot
  • Piling works
  • Foundation works
In Progress at 26.95%
  • Structural works, recorded as progressing at project level
  • Internal works inside the buildings
  • MEP works: mechanical, electrical and plumbing
Ahead of Handover
  • Completing the structure of both apartment buildings and the two-level townhouses
  • Facades, finishes and MEP completion across the 217 residences
  • Building completion and handover procedures toward Q2 2028
Next inspectionPosted to the DLD project register for project 2975 after the next RERA site visit; this page records the 21 April 2026 cycle.
Completion targetHandover expected in Q2 2028; confirm the completion date held on the DLD record for project 2975.
Remaining distance73.05 percentage points separated the 21 April 2026 reading from 100%.

Payment Linked Progress

What 26.95% Progress Means for Ocean Point Buyers

Ocean Point's plan is structured as 10% on booking, 80% during construction and 10% on handover, so the construction share is where most of the money moves while the frames rise. A reading of 26.95% does not tell you what you owe; your SPA does. At this stage of Ocean Point, four actions matter most.

Before Each Construction Instalment

Verify the escrow account

Every construction instalment should go only to the DLD regulated escrow account registered for project 2975 with Emirates Islamic Bank. Ocean Point escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before Your Next Instalment

Map your SPA against the 80% share

Check how your sale and purchase agreement splits the 80% construction share, whether instalments fall on calendar dates or on progress triggers, and what evidence releases each one. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

After SPA Signing

Confirm your Oqood registration

An off plan purchase at Ocean Point is registered in the Dubai Land Department Oqood system against project 2975. Check that your Oqood record shows the correct unit and buyer names while the frames are still rising, since a later resale or mortgage relies on it.

Every Cycle

Track the next readings

With 73.05 points still to be recorded after 21 April 2026, several register readings remain before the Q2 2028 handover. Ocean Point construction updates hub collects each cycle as it is published.

General framework, not legal advice: instalment triggers, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 26.95%?

Entering during the structure stage trades part of the launch runway for evidence: foundations are recorded complete, the frames are rising, and the developer's current terms decide which construction instalments fall due at signing. Every payment goes to the DLD-registered escrow account for project 2975, released against recorded construction progress.

Entering Now at 26.95%
  • Enabling, piling and foundations recorded complete on 21 April 2026
  • Handover expected in Q2 2028
  • 10/80/10 plan: 80% during construction, 10% on handover
Typical Launch Entry
  • Ground and foundation risk carried from the first day of works
  • The longest wait, often three to four years to handover
  • Full instalment runway, priced at launch levels
AED 1.66M ≈ USD 452KStarting Price
10/80/10 Plan80% During Construction
Q2 2028Expected Handover
Ask What Is Available at Ocean Point

Limited Units Available, per the Ocean Point project page as of this update; availability shifts between cycles.

About the Development

Ocean Point Project Details

Ocean Point by Emaar in Rashid Yachts & Marina project rendering of waterfront-style residential buildings and landscaped swimming pool seen from a balcony with a person standing by the railing in Dubai - Presented by Tohid Fetrat
Rashid Yachts & Marina · Emaar

With foundations recorded complete and its structure progressing, Ocean Point is a superstructure stage development of 217 residences: 1, 2 and 3 bedroom apartments in two buildings of ground plus eight floors, plus 3 bedroom two-level townhouses. Starting prices: AED 1.66M ≈ USD 452K.

For buyers entering at this stage, the trade off is a shorter wait than at launch against less construction runway left to spread the 80% share across, with handover expected in Q2 2028.

Ocean Point at Rashid Yachts & Marina Project Guide

Site Context This Cycle

Explore Ocean Point Location on Dubai Map

Ocean Point holds the southern, inland corner of the Rashid Yachts & Marina master plan, beside the Burj View axis and the Canal Pool and set back from the marina and Seagate on the northern edge. That garden-side position means the April 2026 works are mid-rise frames and a low townhouse cluster rising among neighbouring plots of the same master community, not an exposed waterfront tower.

Rashid Yachts & Marina is planned around its marina, which the community brochure describes with 430 wet berths for yachts up to 100 m, alongside a Marina Promenade and a High Street of local shops and cafes, with Port Rashid's heritage quarter and the Dubai World Trade Centre nearby. For a buyer reading a 26.95% record, the useful question is how much of that setting will be operating by the Q2 2028 handover, which shapes occupancy and rental plans. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Ocean Point on Dubai Map

Buyer Resources for This Project

Investing in Ocean Point During Structural Construction

The structure band is where payment protection and residency planning deserve attention, well before handover preparation begins. Each resource below is matched to where Ocean Point stood at the April 2026 reading.

Ocean Point by Emaar in Rashid Yachts & Marina construction updates cover image featuring a project rendering of apartment buildings around a swimming pool, sun loungers and landscaped terraces in Dubai - Presented by Tohid Fetrat
You Are Here

Ocean Point Construction Updates

This page: the 21 April 2026 inspection record for Ocean Point, read at 26.95% progress.

Ocean Point by Emaar in Rashid Yachts & Marina Golden Visa concept graphic with a gold card above rendered apartment buildings and a landscaped garden plaza in Dubai - Presented by Tohid Fetrat

Ocean Point at Rashid Yachts & Marina Golden Visa From 2 Bedrooms

Ocean Point at Rashid Yachts & Marina, Emaar's 217 residences, qualifies at three of four tiers from the 2 bedroom.

Read Ocean Point Golden Visa Guide
Ocean Point by Emaar in Rashid Yachts & Marina escrow account concept graphic featuring a shield and padlock above a rendered landscaped lawn, pavilion and residential building in Dubai - Presented by Tohid Fetrat

Ocean Point at Rashid Yachts & Marina Escrow: Emirates Islamic on Record

Ocean Point at Rashid Yachts & Marina, DLD project 2975, holds 217 units with Emirates Islamic, 26.95% certified in April 2026.

Verify Ocean Point Escrow Account

Update Timeline

Other Ocean Point Construction Updates

April 2026 opens the monthly series for Ocean Point; the hub gathers every reading as later inspection cycles are added.

All Ocean Point Construction Updates

FAQs

Ocean Point Construction Progress in April 2026: Frequently Asked Questions

The Dubai Land Department project register records 26.95% for Ocean Point, project 2975, on the inspection report dated 21 April 2026. That is the reading this April 2026 record is built on; later readings post to the same register after each RERA site visit, so the live figure for project 2975 on Dubai REST should be checked before the April number is relied on.

15.46% is the figure the DLD register shows as Ocean Point's previous inspection, the reading that came before the 21 April 2026 report. The register does not display the date of that earlier visit, so no time span, monthly pace or trend line can be calculated from the two figures, and none is given on this page.

No revised date appears in the 21 April 2026 inspection material: the RERA report sets the progress status at Main Contract, Progressing and does not itself state a completion date. Handover remains expected in Q2 2028, and the dates that bind an individual buyer are the ones in the DLD record for project 2975 and in that buyer's SPA.

The Independent Progress Monitoring Report from the 21 April 2026 visit records enabling, piling and foundation works as completed, which closes out the groundwork phase as of that date. It lists structure, internal works and MEP works as progressing, and it does not state how many floors had been reached on either apartment building.

Enabling works, piling and foundations carry a modest share of a project's total weighting; the larger shares sit in structure, MEP, facades and finishing, most of which were still progressing or yet to come at the 21 April 2026 visit. A reading in the mid twenties with foundations finished fits a project whose frame is rising but still has most of its build ahead. How readings are weighted across stages is covered on the Ocean Point construction updates hub.

The DLD register records Ocean Point as registered on 28 February 2024 and construction as started on 06 July 2024, 129 days later. From that start to the 21 April 2026 inspection is 654 days; that span is arithmetic only, not a measure of pace and not a forecast of the remaining build.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the April 2026 inspection record for Ocean Point at Rashid Yachts & Marina correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts