Ocean Point at Rashid Yachts & Marina Construction Updates
The Register Record for Two Mid-Rise Buildings and a Townhouse Cluster in Mina Rashid
Ocean Point reached 26.95% on the DLD register reading of 21 April 2026, a climb that carried its two mid-rise buildings and townhouses past foundations into structure.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Ocean Point at Rashid Yachts & Marina at a Glance
Ocean Point is Emaar's 217-residence plot on the inland, garden-side corner of Rashid Yachts & Marina, registered with the Dubai Land Department as project 2975 on 28 February 2024. Works started on 06 July 2024, and the register reading of 21 April 2026, taken 654 days into the build, placed the project at 26.95%. One project number covers two formats here, two buildings of ground plus eight floors and a cluster of two-level townhouses, so each register reading is a single blended figure for apartment frames and townhouse works rather than a score for each building.
2975
Active
06 July 2024
217 Residential
23,551.02 sq m
Q2 2028 (developer handover)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Ocean Point at Rashid Yachts & Marina Construction Update Timeline
Ocean Point's record holds one dated reading so far: 26.95% on 21 April 2026, the inspection documented in the April 2026 monthly update. The register also lists a previous inspection at 15.46% but shows no date for it, so the 11.49 point gap between the two figures cannot be placed on a calendar. That earlier reading appears on the track as an undated dot and stays out of the table, which carries dated readings only.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| April 2026 | 26.95% | 21 April 2026 | View the April 2026 update |
Pace Analysis
How Fast Ocean Point at Rashid Yachts & Marina Has Been Built
A pace figure needs two dated readings, and Ocean Point's record so far holds one. Until the next reading posts, the record supports arithmetic between its fixed dates and figures, not a velocity:
- 28 Feb 2024 to 06 Jul 2024: DLD registration to construction start129 days
- 06 Jul 2024 to 21 Apr 2026: construction start to the 26.95% reading654 days
- Previous inspection, date not shown: 15.46% to 26.95%No dated span, no pace
- 21 Apr 2026 to handover: 26.95% to 100%73.05 points remaining
What the arithmetic does show is where Ocean Point's 654 days went. The RERA report from the 21 April 2026 visit closes out enabling, piling and foundation works and lists structure, internal works and MEP works as progressing, so the record caught the build just past its below-ground phase and early in the stretch where the frames of two ground plus eight buildings and the townhouses carry the percentage forward. The 73.05 points left at that date are a distance, not a forecast, and no rate is attached to them here: the first measured pace for Ocean Point arrives when a second dated reading posts to the register. For an end user planning a Q2 2028 move, or an investor spreading the 80% construction share, that first measured interval is the number worth waiting for, not a figure drawn back to the start date.
Get the Next Inspection Figure First
Tell me you are tracking Ocean Point at Rashid Yachts & Marina and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Ocean Point at Rashid Yachts & Marina at Mina Rashid
A register percentage only means something next to what is being delivered. The Ocean Point project guide covers the residences this record is tracking toward:

Ocean Point at Rashid Yachts & Marina: The Southern, Inland End
Ocean Point at Rashid Yachts & Marina is an Emaar project of 217 residences, two apartment buildings plus two-level townhouses.
View the Ocean Point at Rashid Yachts & Marina Project GuideConsidering a Mid-Construction Entry?
Ocean Point is listed with Limited Units Available, and what remains across its apartment and townhouse tiers shifts as construction moves on. If this record is what brought you here, ask me what is open now before you rely on any published range.
Ask About Remaining Availability on WhatsAppStage Record
Ocean Point at Rashid Yachts & Marina Build Stages, Mapped to the Inspections
Each stage below is pinned to the dates in Ocean Point's own record rather than to a generic construction sequence, so the current phase sits exactly where the 21 April 2026 inspection placed the two buildings and the townhouse cluster.
Registration and Mobilisation
Registered as DLD project 2975 on 28 February 2024, with construction starting 129 days later, on 06 July 2024, across the apartment and townhouse plot.
Enabling, Piling and Foundations
Logged as completed at the 21 April 2026 inspection, closing the below-ground phase beneath both ground plus eight buildings and the townhouse cluster.
Structure, Internal and MEP Works
Underway when the register recorded 26.95% on 21 April 2026, with the RERA report setting progress status at Main Contract, Progressing.
Envelope, Finishes and Landscape
Facades, apartment and townhouse finishes, and the pool, plaza and landscaped grounds sit beyond the works named in the 21 April 2026 inspection notes.
Completion and Handover
Building completion, commissioning and handover of the 217 residences, scheduled for Q2 2028, with 73.05 points still to be recorded after 21 April 2026.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Ocean Point at Rashid Yachts & Marina's own record.
Buyer Position
Tracking Your Position at Ocean Point at Rashid Yachts & Marina
This page is one of four project resources that together cover a Ocean Point at Rashid Yachts & Marina purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Ocean Point at Rashid Yachts & Marina Construction Updates
This page: Ocean Point's DLD register record for project 2975, from July 2024 start to handover.

Ocean Point at Rashid Yachts & Marina Golden Visa From 2 Bedrooms
Ocean Point at Rashid Yachts & Marina, Emaar's 217 residences, qualifies at three of four tiers from the 2 bedroom.
Read the Ocean Point at Rashid Yachts & Marina Golden Visa Guide
Ocean Point at Rashid Yachts & Marina Escrow: Emirates Islamic on Record
Ocean Point at Rashid Yachts & Marina, DLD project 2975, holds 217 units with Emirates Islamic, 26.95% certified in April 2026.
Verify the Ocean Point at Rashid Yachts & Marina Escrow AccountApproaching Handover
Between 26.95% and Handover: What Ocean Point at Rashid Yachts & Marina Buyers Should Do Now
At the 21 April 2026 reading Ocean Point still had 73.05 points ahead of it, and most of its 80% construction share falls due while those points are recorded. That makes this the stretch where each instalment leaving your account before Q2 2028 should be matched to the record rather than to a payment reminder. The three checks below take minutes, and they are easiest to set up before the next instalment notice arrives, not after it.
First, before any construction instalment, confirm the payee against the Ocean Point escrow account details, so funds reach the registered account for project 2975 and nowhere else.
Second, if you hold or are choosing a 2 bedroom apartment or larger, map your residency timing in the Ocean Point Golden Visa eligibility guide, since eligibility is assessed on the property value recorded with the DLD at application.
Third, revisit the Ocean Point prices and payment plan whenever a new register reading posts, so your view of the 10/80/10 schedule and the remaining tiers stays current.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Mina Rashid Structure
Ocean Point's 26.95% at 21 April 2026 reads differently beside what surrounds it: the listings it will sit among at handover, the master plan around its plot, and the developer building it. These three pages set the record in that context:

Mina Rashid Properties for Sale
Browse waterfront apartments for sale at Rashid Yachts & Marina, with projects, prices and payment plans.
See Mina Rashid Properties for Sale
Mina Rashid Community Overview
Read the Rashid Yachts & Marina guide: Emaar's transformation of historic Port Rashid into a marina lifestyle community.
Explore the Mina Rashid Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Ocean Point at Rashid Yachts & Marina Construction Updates Frequently Asked Questions
Ocean Point, DLD project 2975, was in its structure stage at the latest reading in the supplied record: 26.95% on 21 April 2026, with the RERA report from that date setting progress status at Main Contract, Progressing. Its below-ground works were finished by then, while the frames, interiors and building services were under way. The dated record sits in the Ocean Point inspection timeline above.
The Ocean Point timeline rests on two DLD register figures: 26.95% on 21 April 2026, which forms the only dated table row, and a previous inspection of 15.46% that the register lists without a date. The dated reading is covered in full in the Ocean Point April 2026 construction update, and further rows join the table as new dated readings post.
Ocean Point's percentages come from the Dubai Land Department project register for project 2975, and its stage descriptions come from the RERA Independent Progress Monitoring Report, which for the 21 April 2026 visit lists works by status but prints no percentage. Each dated register reading becomes one timeline row with its own monthly update page; the general method is set out on the Dubai Construction Updates methodology hub.
Ocean Point's handover is scheduled for Q2 2028, and that quarter is the completion timing used across this page. The DLD register extract supplied for project 2975 shows registration on 28 February 2024 and a construction start on 06 July 2024 but no registered completion date, so none is quoted here; the full register entry on Dubai REST is where to confirm whether one is held.
At the 21 April 2026 reading of 26.95%, Ocean Point had 73.05 percentage points left to reach 100%, a simple subtraction rather than a forecast. That distance spans the rest of the structure, internal and MEP works plus facades, finishes, landscaping and handover procedures across the 217 residences, ahead of the scheduled Q2 2028 handover.
Not yet for Ocean Point: a pace needs two dated readings, and the record holds one, 26.95% on 21 April 2026, because the earlier 15.46% figure carries no date in the register. The 654 days from the 06 July 2024 start to that reading appear in the Ocean Point pace section as a span only, and a first measured rate becomes possible once the next dated reading posts.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Ocean Point at Rashid Yachts & Marina construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.