Ocean Star by Emaar Properties in Rashid Yachts & Marina project rendering used for the August 2026 construction update showing a private terrace, landscaped courtyard and apartment buildings in Dubai - Presented by Tohid Fetrat

Emaar Properties · Rashid Yachts & Marina · Construction Update

Ocean Star at Rashid Yachts & Marina Construction Update - August 2026

August 2026 Inspection Confirms Ocean Star Reaches 30.46% Construction Progress at Rashid Yachts & Marina

Structure, MEP, external envelope and internal finishes are all progressing at Ocean Star, with foundations complete and 30.46 percent certified in the August 2026 RERA inspection.

Direct advisor access. Every message answered personally, never by a call center.

30.46%Construction Progress
11 August 2026Inspection Date
July 2028Expected Completion
3010DLD Project Number

Verified DLD Inspection Data

Ocean Star Construction Snapshot

A 10.30 point rise to 30.46% puts Ocean Star in the superstructure band, the stage where a payment plan stops being a schedule on paper and starts tracking what an inspector can certify on site.

Project Name

Ocean Star at Rashid Yachts & Marina

Project Number

3010

Project Status

Active

Construction Progress

30.46%

Inspection Date

11 August 2026

Construction Start

06 July 2024

Total Units

154 Units

Total Built Area

17,103.62 sq m

Expected Completion

July 2028

Data source: RERA inspection conducted on 11 August 2026, tracked against DLD inspection records. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: September 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Ocean Star Construction Progress Summary

Between the previous inspection and the 11 August 2026 reading, Ocean Star moved from 20.16% to 30.46%, a 10.30 point gain recorded while enabling and foundation works closed out and four separate work packages opened in parallel across both buildings. The site has stopped preparing ground and started building.

Completed
  • Enabling works across plot 495 at Madinat Dubai Almelaheyah
  • Foundation works beneath both residential buildings
In Progress at 30.46%
  • Structural works on Building 1 and Building 2
  • MEP: mechanical, electrical and plumbing installation
  • External envelope across both buildings
  • Internal finishes toward the 154 apartments
Ahead of Handover
  • The remaining 69.54 points of certified progress toward 100%
  • Building completion certificate procedures
  • Handover scheduled for July 2028
Next inspectionPublished in the DLD project register after the next RERA site visit; this page updates with each cycle.
Handover targetJuly 2028, roughly twenty three months beyond this inspection date.
Remaining distance69.54 percentage points separate the August 2026 reading from handover readiness.

Payment Linked Progress

What 30.46% Progress Means for Ocean Star Buyers

Most Dubai off plan payment plans tie instalments to construction milestones or to handover itself, so a certified reading of 30.46% is not just a status update: it tells you which of the four remaining Ocean Star payments are already in view. Four actions matter at this point in the build.

Before Any Remaining Instalment

Verify the escrow account

Every payment still ahead of handover should go only to the DLD regulated escrow account registered for project 3010. Ocean Star escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before the December 2026 Instalment

Map your SPA against the certified reading

Your sale and purchase agreement, not this page, defines how construction completion is certified for payment purposes and what notice you receive. Not sure how your instalments map to the 30.46% reading? Send me your SPA schedule and I will map it against the certified milestones.

This Cycle

Locate yourself in the milestone ladder

The developer's schedule of record ties the June 2026 payment to 20% construction completion and the December 2026 payment to 40%. The August 2026 certified reading of 30.46% sits between those two markers, which is the practical meaning of this cycle for a buyer already on the plan.

Every Cycle

Track the cycles to 2028

Roughly 69.54 points and several inspection cycles separate this reading from completion. Ocean Star construction updates hub collects each new reading as it is published.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 30.46%?

Entering mid build trades a shorter wait for a shorter instalment runway: the ground risk is already behind the project, four of the ten payments remain, and the choice narrows to what Emaar still holds. Every payment goes to the DLD-registered escrow account for project 3010, released against certified construction progress.

Entering Now at 30.46%
  • Enabling and foundation works already certified complete
  • Four of the ten 10% payments remain, the last in July 2028
  • Under two years from this reading to the July 2028 handover
Typical Launch Entry
  • Ground risk still ahead, from excavation through to topping out
  • A four year wait between booking and keys is common
  • The full instalment ladder, carried from launch pricing onward
AED 1.70M ≈ USD 463KStarting Price
Ten 10% InstalmentsPayment Plan of Record
From July 2028Expected Handover
Ask What Is Available at Ocean Star

Limited units available on the project page as of this update; availability shifts between cycles.

About the Development

Ocean Star Project Details

Ocean Star at Rashid Yachts & Marina by Emaar apartment balconies with evening lighting overlooking landscaped pool and waterfront community in Dubai - Presented by Tohid Fetrat
Rashid Yachts & Marina · Emaar Properties

With foundations complete and the frame rising on both buildings, Ocean Star is a superstructure stage development of 154 one, two and three bedroom apartments arranged around the Canal Pool. Starting prices: AED 1.70M ≈ USD 463K.

Entering at 30.46% trades the certainty of a finished building for a longer payment runway: four of the ten 10% instalments remain, the last falling due at handover in July 2028.

Ocean Star at Rashid Yachts & Marina Project Guide

Site Context This Cycle

Explore Ocean Star Location on Dubai Map

Ocean Star occupies plot 495 at Madinat Dubai Almelaheyah, on the Rashid Yachts & Marina waterfront, and it is built low: two buildings rising to four and six storeys over a shared basement and ground level, with the entertainment area and common facilities set at first floor. That scale is why the August 2026 cycle reads the way it does. A low rise frame tops out far sooner than a tower, which is how external envelope and internal finish works are already running alongside structure rather than queueing years behind it.

Mina Rashid is an operating port district rather than an emerging one: the marina already holds 430 wet berths for yachts up to 100m, the promenade carries its dining and retail, and the Green Line serves the area at Al Ghubaiba, which my Dubai Metro network guide puts in context for rental demand. For a buyer carrying instalments through to 2028, that maturity is the difference between waiting for a building and waiting for a neighbourhood. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Ocean Star on Dubai Map

Buyer Resources for This Project

Investing in Ocean Star Through the Superstructure Phase

The superstructure band is where residency planning and payment protection get decided, well before the remaining instalments fall due. Each resource below is matched to where Ocean Star stands right now.

Ocean Star by Emaar Properties in Rashid Yachts & Marina construction updates cover image featuring a project rendering of landscaped swimming pools and mid-rise residential buildings in Dubai - Presented by Tohid Fetrat
You Are Here

Ocean Star Construction Updates

This page: the certified 30.46% inspection reading for Ocean Star recorded on 11 August 2026.

Ocean Star by Emaar Properties in Rashid Yachts & Marina Golden Visa graphic with a gold visa card above landscaped lawns and modern apartment buildings in Dubai - Presented by Tohid Fetrat

Ocean Star at Rashid Yachts & Marina Golden Visa: Two of Three

At Ocean Star at Rashid Yachts & Marina, Emaar's 154 apartments, the one bedroom tier stays below the minimum.

Read Ocean Star Golden Visa Guide
Ocean Star by Emaar Properties in Rashid Yachts & Marina escrow account graphic with shield and padlock icons above landscaped swimming pools and apartment buildings in Dubai - Presented by Tohid Fetrat

Ocean Star at Rashid Yachts & Marina Escrow: Mina Rashid on Record

First Abu Dhabi Bank holds Ocean Star at Rashid Yachts & Marina escrow, DLD project 3010, 30.46% certified August 2026.

Verify Ocean Star Escrow Account

Update Timeline

Other Ocean Star Construction Updates

August 2026 opens the published inspection record for Ocean Star in this series. Every reading that follows is added to the same timeline, so the construction history stays in one place rather than scattered across announcements.

All Ocean Star Construction Updates

FAQs

Ocean Star at Rashid Yachts & Marina Construction Progress in August 2026: Frequently Asked Questions

As of the RERA inspection conducted on 11 August 2026, Ocean Star stands at 30.46% construction progress in the DLD project register for project 3010, with the progress status recorded as main contract progressing.

Ocean Star moved from 20.16% at the previous inspection to 30.46% on 11 August 2026, a gain of 10.30 points recorded while enabling and foundation works were completed and structure, MEP, external envelope and internal finish works opened across both buildings.

The 11 August 2026 report records enabling and foundation works as completed, with structure, MEP, external envelope and internal finish works progressing on site. The scope under inspection covers two buildings rising to four and six storeys over a shared basement and ground level, with the entertainment area and common facilities at first floor.

The certified reading on 11 August 2026 is 30.46%, which sits above the 20% construction completion marker attached to the June 2026 instalment and below the 40% marker attached to the December 2026 instalment. How certification is applied to your own payments is governed by your sale and purchase agreement rather than by the published percentage.

The August 2026 record shows the main contract progressing with no revision noted, leaving 69.54 percentage points between the 11 August 2026 reading and full certification, and roughly twenty three months to the July 2028 handover. How inspection cycles accumulate toward completion is covered on the Ocean Star construction updates hub.

Yes. Expected completion and handover dates can be revised between inspection cycles as a project advances. The date shown here reflects the position as of the August 2026 cycle; any revision would appear in a later update in this series.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the August 2026 inspection record for Ocean Star at Rashid Yachts & Marina correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts