Ocean Star at Rashid Yachts & Marina Construction Updates
The Verified Build Record on the Mina Rashid Waterfront
Ocean Star reached 30.46% construction at its 11 August 2026 RERA inspection, with foundations closed out and both marina buildings rising toward a July 2028 handover.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Ocean Star at Rashid Yachts & Marina at a Glance
Ocean Star is Emaar Properties' 154 apartment waterfront release inside Rashid Yachts & Marina, registered as DLD project 3010 on 29 March 2024 and on site since 06 July 2024. Its first published inspection reading, 30.46% on 11 August 2026, belongs to a project built low rather than tall: two buildings of four and six storeys standing on one shared basement and ground level, the first floor given over to the entertainment area and common facilities. That form is why this record moves in wide steps instead of the floor by floor climb a tower produces, and why several work packages already run in parallel this early in the build. The figures below are the DLD registered anchors behind the record.
3010
Active
06 July 2024
154 Units
17,103.62 sq m
July 2028
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Ocean Star at Rashid Yachts & Marina Construction Update Timeline
This record opens with one published reading: 30.46%, certified at the RERA inspection of 11 August 2026, set against the register's previous reading of 20.16%. The 10.30 points between those two figures were added while enabling and foundation works on plot 495 closed out and four separate packages opened together across both buildings. Every inspection recorded from here is added to the track and the table below, newest first, with the full dated update behind each row.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| August 2026 | 30.46% | 11 August 2026 | View the August 2026 update |
Pace Analysis
How Fast Ocean Star at Rashid Yachts & Marina Has Been Built
With one certified reading published, pace at Ocean Star is read two ways: the average across the whole build so far, and the step recorded between the register's two readings.
- Jul 2024 to Aug 2026: site start to first published reading, 0% to 30.46%About 1.2 points per month
- Register's previous reading to 11 Aug 2026: 20.16% to 30.46%10.30 points added
An average of 1.2 points per month across 25 months reads slowly, and the reason is visible in what those months bought. Enabling works and foundations on plot 495 consume time without moving a percentage far, and the register's 20.16% is essentially the cost of that ground. What changed by 11 August 2026 is how many packages run at once: structure, MEP, external envelope and internal finishes all progressing inside the same inspection is the signature of a four and six storey frame, where fit out never has to wait for a fiftieth floor to be poured. From 30.46% to certified completion, 69.54 points remain against roughly 23 months to the July 2028 handover, or about 3.0 points per month. For an end user that number is the one to check each cycle; for an investor it is the test of whether those parallel packages hold their pace or thin out as the finishes deepen.
Get the Next Inspection Figure First
Tell me you are tracking Ocean Star at Rashid Yachts & Marina and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Ocean Star at Rashid Yachts & Marina at Mina Rashid
A percentage only carries meaning against what is being delivered. The project guide covers the homes behind every reading on this page:

Ocean Star at Rashid Yachts & Marina, Facing the Canal Pool
Ocean Star at Rashid Yachts & Marina is an Emaar address of 154 apartments across two buildings around the Canal Pool.
View the Ocean Star at Rashid Yachts & Marina Project GuideConsidering an Entry Mid Build?
Availability at Ocean Star shifts between inspection cycles as Emaar sells through the stock it still holds. If the record on this page is what brought you here, ask for current availability before the next reading publishes.
Ask About Remaining Availability on WhatsAppStage Record
Ocean Star at Rashid Yachts & Marina Build Stages, Mapped to the Inspections
Each stage below is tied to the window it actually occupied in Ocean Star's own register entries, so the 30.46% recorded on 11 August 2026 can be read in sequence rather than against a generic construction timeline.
Registration and Site Handover
Project 3010 was entered on the DLD register on 29 March 2024, and the contractor took plot 495 at Madinat Dubai Almelaheyah on 06 July 2024.
Enabling Works and Foundations
The ground stage that the register's 20.16% reading represents: excavation, enabling works and the foundations beneath both buildings, certified complete by the August 2026 inspection.
Structure, MEP and External Envelope
The 11 August 2026 inspection recorded structure, MEP, external envelope and internal finish works all progressing across Building 1 and Building 2 at 30.46%.
Frame Closed and Fit Out Deepens
The developer's schedule of record attaches 40%, 60% and 80% construction completion to the December 2026, May 2027 and October 2027 instalments, the band this project enters next.
Completion and Handover
The remaining 69.54 points from the August 2026 reading, closing at 100% construction completion and the final instalment at the July 2028 handover.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Ocean Star at Rashid Yachts & Marina's own record.
Buyer Position
Tracking Your Position at Ocean Star at Rashid Yachts & Marina
This page is one of four project resources that together cover a Ocean Star at Rashid Yachts & Marina purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Ocean Star at Rashid Yachts & Marina Construction Updates
This page: the certified inspection record for Ocean Star, from site start to July 2028 handover.

Ocean Star at Rashid Yachts & Marina Golden Visa: Two of Three
At Ocean Star at Rashid Yachts & Marina, Emaar's 154 apartments, the one bedroom tier stays below the minimum.
Read the Ocean Star at Rashid Yachts & Marina Golden Visa Guide
Ocean Star at Rashid Yachts & Marina Escrow: Mina Rashid on Record
First Abu Dhabi Bank holds Ocean Star at Rashid Yachts & Marina escrow, DLD project 3010, 30.46% certified August 2026.
Verify the Ocean Star at Rashid Yachts & Marina Escrow AccountApproaching Handover
Between 30.46% and Handover: What Ocean Star at Rashid Yachts & Marina Buyers Should Do Now
At the 30.46% recorded on 11 August 2026, the work that decides a July 2028 handover is happening now, in four packages running at once, and the next register entry is the only place it appears as a number. The instalments on this plan fall due on fixed calendar dates rather than on notice, so the three checks below belong in this cycle rather than the one after it.
First, confirm where your remaining payments sit against the schedule of record and route every one of them through the trust account listed on the Ocean Star escrow account page.
Second, if residency is part of the plan, settle eligibility now through the Ocean Star Golden Visa guide, since the qualifying tier is decided by the layout you hold rather than by the completion percentage.
Third, follow the record itself: the Ocean Star August 2026 construction update carries the inspection detail behind the 30.46% figure, and each later reading is added here as it is certified.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Mina Rashid Structure
A build record is only half the picture; the other half is what is rising around it. These three pages place Ocean Star's progress inside its market, its district and its developer's delivery history:

Mina Rashid Properties for Sale
Browse waterfront apartments for sale at Rashid Yachts & Marina, with projects, prices and payment plans.
See Mina Rashid Properties for Sale
Mina Rashid Community Overview
Read the Rashid Yachts & Marina guide: Emaar's transformation of historic Port Rashid into a marina lifestyle community.
Explore the Mina Rashid Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Ocean Star at Rashid Yachts & Marina Construction Updates Frequently Asked Questions
The record is updated each time a RERA inspection for project 3010 is entered in the DLD register, which for an off plan project of this size usually falls once or twice a year rather than monthly. The series opens with the inspection of 11 August 2026 at 30.46%, and every later reading is added to the inspection timeline above with its own dated update page.
Ocean Star is an active DLD registered project, number 3010, in its structural stage, recorded at 30.46% at the inspection of 11 August 2026 with the progress status noted as main contract progressing. Enabling and foundation works were certified complete at that inspection, with structure, MEP, external envelope and internal finish works progressing across both buildings.
Yes. The DLD register carries a previous reading of 20.16% for project 3010, and the 11 August 2026 inspection recorded 30.46%, a gain of 10.30 points. That earlier reading is published as a percentage without a paired inspection date, so the dated series on this page begins with August 2026; the detail behind it sits in the August 2026 inspection update for Ocean Star.
Construction started on 06 July 2024, so the 30.46% recorded on 11 August 2026 represents an average of about 1.2 percentage points per month across roughly 25 months, most of it spent on enabling works and foundations. The full breakdown, including what the remaining 69.54 points imply per month, is in the pace analysis above.
Ocean Star is two buildings, one topping out at four storeys and the other at six, sharing a single basement and ground level, with the communal facilities and entertainment area placed on the first floor. A frame that low tops out far earlier than a tower, which is why the 11 August 2026 inspection already records external envelope and internal finish works progressing alongside structure at 30.46% rather than queued years behind it.
Handover is scheduled for July 2028. From the 30.46% certified on 11 August 2026 that leaves 69.54 percentage points and roughly 23 months of recorded progress to run, and each inspection published between now and then is added to this record as it is certified.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Ocean Star at Rashid Yachts & Marina construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.