OMNIYAT · Palm Jumeirah
ORLA Dorchester Collection Construction Updates
The Dated Build Record of ORLA's Three Linked Towers on the Palm Jumeirah Crescent
ORLA recorded 70.01% at its 21 August 2026 RERA inspection, leaving 29.99 points across its three linked towers on the Palm Jumeirah crescent to close before handover.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
ORLA Dorchester Collection at a Glance
ORLA is OMNIYAT's 90-residence Dorchester Collection building on the western side of the Palm Jumeirah crescent, entered in the DLD register as project 2455 on 17 November 2022. Between its 31 January 2023 construction start and the 70.01% recorded on 21 August 2026, one percentage has tracked three staggered towers joined into a single frame over two basement levels, so every reading below describes the whole linked structure, not one tower at a time. The six cards are the register anchors behind that record.
2455
Active
31 January 2023
90 ultra-luxury residences
67,242.11 sq m
31 December 2026 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
ORLA Dorchester Collection Construction Update Timeline
ORLA's register holds three readings: an undated 48% carried as the previous figure before May 2026, 60.02% on 18 May 2026, and 70.01% on 21 August 2026. Only the two 2026 readings carry dates, 95 days apart, so they form the one pair on this record that yields a monthly rate. The track shows all three; each dated row in the table links its full monthly update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| August 2026 | 70.01% | 21 August 2026 | View the August 2026 update |
| May 2026 | 60.02% | 18 May 2026 | View the May 2026 update |
Pace Analysis
How Fast ORLA Dorchester Collection Has Been Built
ORLA's record supports one measured pace and one derived whole-build average, plus an earlier gain that has no dates to divide by. Set side by side, they read like this:
- Jan 2023 to Aug 2026: derived whole-build average, construction start to 70.01% over about 42.6 monthsAbout 1.6 points per month
- Undated earlier inspection to 18 May 2026: 48% to 60.02%12.02 points, interval undated
- 18 May 2026 to 21 Aug 2026: structure reaching an advanced stage, 60.02% to 70.01%About 3.15 points per month
The two rates describe different spans. The whole-build average divides 70.01 points across the roughly 42.6 months since 31 January 2023, a period that absorbs the enabling works, the foundations and both basement levels, all logged as complete by the 18 May 2026 inspection. The May to August 2026 quarter ran at about 3.15 points per month over 95 days, nearly twice that average, while the inspector moved structure works to an advanced stage and kept envelope, MEP and finishes open alongside them. The 12.02 point step from 48% to 60.02% shows movement but, without a start date, no speed. For an end user, the recent quarter is the more telling figure: the three linked towers added measurable progress faster than across the build as a whole. For an investor, the facts that sit beside it matter as much: 29.99 points remained on 21 August 2026, and the register still dates completion to 31 December 2026, 132 days later. Neither rate is a forecast; the next dated inspection is what shows whether the quarter's pace held.
Get the Next Inspection Figure First
Tell me you are tracking ORLA Dorchester Collection and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About ORLA Dorchester Collection at Palm Jumeirah Dubai
The 70.01% recorded on 21 August 2026 is progress toward a specific product: 90 residences under Dorchester Collection management on a 29,000 square metre beachfront plot. The project guide covers what that product is:

ORLA Dorchester Collection: Foster + Partners Towers on the Crescent
ORLA Dorchester Collection is OMNIYAT's beachfront address on the Palm Jumeirah crescent, 90 residences in three staggered, interconnected towers.
View the ORLA Dorchester Collection Project GuideConsidering an Entry Before Handover?
Availability at ORLA narrows as the build moves toward its registered completion, and the launch payment plan was written for a longer runway than a purchase made now would have. If the record on this page is what brought you here, ask me what is currently available and on what terms before remaining inventory narrows further.
Ask About Remaining Availability on WhatsAppStage Record
ORLA Dorchester Collection Build Stages, Mapped to the Inspections
ORLA's two dated inspection reports list the same eight work packages, and the one change between them places the building on the stages below: enabling and foundation works closed in both, structure works moved from progressing on 18 May 2026 to an advanced stage on 21 August 2026, and the remaining packages open together at different stages.
Site Activation and Enabling Works
Construction started on 31 January 2023, 75 days after DLD registration on 17 November 2022; enabling works stand as completed in both the May and August 2026 reports.
Foundations and Two Basement Levels
Foundation works under the two registered basement levels were logged complete at the 18 May 2026 inspection, which also carried the undated earlier reading of 48%.
Linked Tower Structure
The ground-plus-13-floor frame joining three staggered towers moved to an advanced stage between 60.02% on 18 May 2026 and 70.01% on 21 August 2026.
Envelope, MEP, and Interior Finishes
External envelope, MEP, internal works and internal finishes were recorded progressing at different stages on 18 May and 21 August 2026, running alongside the structure.
External Works, Completion, and Handover
External works remain open in the 21 August 2026 notes, with 29.99 points between that 70.01% reading and 100%; no completion step appears in the record yet.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on ORLA Dorchester Collection's own record.
Buyer Position
Tracking Your Position at ORLA Dorchester Collection
This page is one of four project resources that together cover a ORLA Dorchester Collection purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

ORLA Dorchester Collection Construction Updates
This page: every recorded ORLA inspection from the January 2023 start toward the Q4 2026 handover.

ORLA Dorchester Collection Golden Visa From a Single Beachfront Residence
OMNIYAT's ORLA Dorchester Collection, 90 residences on the Palm Jumeirah crescent, qualifies at every tier to the Luna Sky Palace.
Read the ORLA Dorchester Collection Golden Visa Guide
ORLA Dorchester Collection Escrow: OMNIYAT's Palm Account at Mashreq
OMNIYAT's ORLA Dorchester Collection on Palm Jumeirah, DLD project 2455, holds 90 units at Mashreq, 70.01% certified August 2026.
Verify the ORLA Dorchester Collection Escrow Account
ORLA Dorchester Collection Snagging: Three Staggered, Linked Towers
ORLA Dorchester Collection is OMNIYAT's beachfront building on the crescent of Palm Jumeirah, drawn by Foster + Partners, with 90 residences.
Book ORLA Dorchester Collection SnaggingApproaching Handover
Between 70.01% and Handover: What ORLA Dorchester Collection Buyers Should Do Now
At 70.01% on 21 August 2026, ORLA still had its structure at an advanced stage and its envelope, MEP and finishing packages open, with 29.99 points to record before 100%. On the launch plan, half of the price falls due on the completion date, which makes the months before the registered 31 December 2026 the time to prepare rather than react. Handover notices typically leave buyers a short window to complete their appointment, so the three steps below belong before the notice arrives, not after it.
First, line up independent snagging so defects in terraces, private pools, double-height glazing and home automation are documented before you accept the residence; the ORLA snagging inspection page covers timing and scope.
Second, check the remaining launch-plan payments, including the 50% on completion, against the ORLA escrow account page, so the largest transfer goes only to the Mashreq Bank PSC account registered for project 2455.
Third, since every ORLA tier clears the Golden Visa value threshold, settle whether to apply on the off-plan registration or wait for the title deed through the ORLA Golden Visa guide.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Palm Jumeirah Dubai Structure
A build record is only half the picture; the other half is what already stands around it. These three pages put ORLA's progress on the crescent in its market, community, and developer context:

Palm Jumeirah Dubai Properties for Sale
Browse beachfront apartments, penthouses, sky mansions and signature villas for sale across Palm Jumeirah.
See Palm Jumeirah Dubai Properties for Sale
Palm Jumeirah Dubai Community Overview
Read the Palm Jumeirah guide: Nakheel's island of signature villas, branded residences, private beaches and five-star resorts.
Explore the Palm Jumeirah Dubai Community
Omniyat: Ultra-Luxury Architectural Icons From Palm Jumeirah to Business Bay
Omniyat designs ultra-luxury waterfront residences and commercial landmarks, and held the largest share of the UAE's ultra-luxury segment in 2024.
View the OMNIYAT Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
ORLA Dorchester Collection Construction Updates Frequently Asked Questions
ORLA, Dorchester Collection is an Active DLD-registered project, number 2455, recorded at 70.01% at the RERA inspection of 21 August 2026 with the progress status Main Contract - Progressing. That report logs enabling and foundation works as complete and structure works at an advanced stage, with envelope, MEP, internal finishes and external works still progressing. The full record is in the inspection timeline above.
The 21 August 2026 inspection recorded 70.01% construction progress at ORLA, up 9.99 points from the 60.02% reading of 18 May 2026, 95 days earlier. The inspection notes and the full reading are in the ORLA August 2026 construction update.
The DLD register dates completion of project 2455 to 31 December 2026, and ORLA's handover is expected in Q4 2026. At the 21 August 2026 inspection the building stood at 70.01%, 132 days before that date, with 29.99 points still to record. The registered date can be revised in the register between inspections, so this page reports it as filed rather than forecasting it, and the record here is updated as each inspection is filed.
The DLD record for ORLA, project 2455, lists 90 units and 67,242.11 sq m of total built area. Those 90 ultra-luxury residences run from 2 bedroom homes of about 2,799 sq ft (260 sq m) to the Luna Sky Palace at about 58,476 sq ft (5,433 sq m), spread over 2 basements, ground, 13 floors and a roof.
Across the whole build, ORLA averaged about 1.6 points per month, a derived figure that spreads the 70.01% of 21 August 2026 over roughly 42.6 months from the 31 January 2023 start. The only dated pair of inspections, 60.02% on 18 May 2026 and 70.01% on 21 August 2026, shows about 3.15 points per month over 95 days. Both measure past progress and neither is a projection; the breakdown is in the pace analysis above.
Construction started on 31 January 2023, 75 days after ORLA was registered with the DLD on 17 November 2022. The first dated reading on the record is 60.02% at the 18 May 2026 inspection, covered in the ORLA May 2026 construction update; an earlier 48% reading sits in the register without a date.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the ORLA Dorchester Collection construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.