Emaar · Dubai Hills Estate · Construction Update
Palace Residences Hillside Construction Update - May 2026
May 2026 Inspection Records Palace Residences Hillside at 7.87% Construction Progress in Dubai Hills Estate
Mobilization, enabling works, and early foundations dominate site activity at Palace Residences Hillside, verified at 7.87 percent in the May 2026 RERA inspection cycle.
Direct advisor access. Every message answered personally, never by a call center.
Verified DLD Inspection Data
Palace Residences Hillside Construction Snapshot
A 2.10 point rise since the previous recorded inspection keeps Palace Residences Hillside in the enabling and foundations band, the stage where the payment schedule and escrow discipline matter far more than anything visible on site.
Palace Residences Hillside A
4015
Active
7.87%
05 May 2026
30 September 2025
359 residential units
34,920.15 sq m
30 June 2029
Data source: RERA inspection conducted on 05 May 2026, tracked against DLD inspection records for project 4015, registered as Palace Residences Hillside A. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: September 2026.
Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp
This Inspection Cycle
Palace Residences Hillside Construction Progress Summary
Between the previous recorded reading and the 05 May 2026 inspection, Palace Residences Hillside moved from 5.77% to 7.87%, a 2.10 point gain earned entirely in mobilization, enabling and foundation activity on plot 5410. Seven months after the 30 September 2025 construction start, the certified work is still below the lowest slab.
- Project registration with the DLD recorded on 07 August 2025
- Construction start recorded on 30 September 2025
- Main contract in place and recorded as progressing at inspection
- Contractor mobilization, still ongoing at the 05 May 2026 visit
- Enabling works across the plot
- Foundation works for the single basement level
- Superstructure for the ground floor, podium and twenty residential levels
- Facade, MEP and interior fit out across the 359 residences
- Remaining RERA inspection cycles toward 100%
- Building completion certificate and handover from June 2029
Payment Linked Progress
What 7.87% Progress Means for Palace Residences Hillside Buyers
Most Dubai off plan payment plans tie instalments to construction milestones or to calendar dates, so a verified reading of 7.87% is not just a status update: it tells you which obligations and protections apply while the building is still below ground. At this stage of Palace Residences Hillside, four actions matter most.
Verify the escrow account
Every instalment ahead of handover should go only to the DLD regulated escrow account registered for project 4015, whose trust account is recorded with First Abu Dhabi Bank in the 05 May 2026 inspection report. Palace Residences Hillside escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.
Map your SPA against the payment dates
The published schedule runs on calendar dates until the construction linked instalments begin at 50% completion in September 2027, so confirm which form your own sale and purchase agreement uses. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the certified milestones.
Confirm your Oqood registration
At this stage the interim registration of an off plan sale is what puts your name against project 4015 in the DLD record. Ask for the registration confirmation and check the unit number, area and price on it against your sale and purchase agreement.
Track each inspection reading
Just over three years of inspection cycles separate the May 2026 reading from the completion date on record. Palace Residences Hillside construction updates hub keeps every certified reading in one place.
General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.
Buying at 7.87%?
Entering at the foundation stage buys the longest instalment runway the project will ever offer and the earliest position on its price list, in exchange for carrying the build from the ground up. Every payment goes to the DLD-registered escrow account for project 4015, released against certified construction progress.
- Certified inspection readings already on record, the latest 7.87% on 05 May 2026
- Construction start certified 30 September 2025, not a paper start date
- The full instalment runway to the 30 June 2029 completion date
- Committed before any inspection reading exists to check
- Contractor mobilization still unproven on the ground
- The same payment structure with less evidence behind it
18 units listed available on the project page as of this update; availability shifts between cycles.
About the Development
Palace Residences Hillside Project Details

With foundation works underway, Palace Residences Hillside is an early stage development of 359 homes, from 1 bedroom apartments to 3 bedroom townhouses, rising over a single basement and podium level. Starting prices: AED 1.71M ≈ USD 466K.
For buyers entering at this stage, the trade off is the full construction wait against the longest instalment runway the plan offers, with handover expected from June 2029 per the current DLD record.
Palace Residences Hillside Project GuideSite Context This Cycle
Explore Palace Residences Hillside Location on Dubai Map
Palace Residences Hillside occupies plot 5410 in Hadaeq Sheikh Mohammed Bin Rashid, the district name the DLD register uses for Dubai Hills Estate, and at 7.87% every item certified this cycle sits below ground: the enabling works and the foundations for the single basement that will carry the ground floor, the podium and twenty residential levels above it.
Because the surrounding community is already built out, with the golf course, the mall, the parks and the schools all in service, this project is being built into a finished neighborhood rather than an emerging one, which is the practical counterweight to a completion date three years out. See the project’s position on the interactive Dubai real estate map.

Buyer Resources for This Project
Investing in Palace Residences Hillside During Early Construction Progress
The foundation band is where registration, payment protection, and residency planning are set up correctly. Each resource below is matched to where Palace Residences Hillside stands right now.

Palace Residences Hillside Construction Updates
This page: the verified May 2026 inspection record for Palace Residences Hillside at 7.87 percent.

Palace Residences Hillside at Dubai Hills Estate Golden Visa: Three of Four
Three of four typologies at Palace Residences Hillside at Dubai Hills Estate qualify individually; 1 bedroom tier needs a second property.
Read Palace Residences Hillside Golden Visa Guide
Palace Residences Hillside at Dubai Hills Estate: One Registered Escrow
Palace Residences Hillside at Dubai Hills Estate is DLD project 4015, 360 units, buyer money held by First Abu Dhabi Bank.
Verify Palace Residences Hillside Escrow AccountUpdate Timeline
Other Palace Residences Hillside Construction Updates
This May 2026 reading is the first published inspection record for Palace Residences Hillside; the hub collects every cycle that follows it, from foundations through to handover.
Where This Update Fits
Explore Palace Residences Hillside Structure
This monthly report is one node in the wider record: the community that surrounds the site, the developer delivering it, and the listings competing with it.

Dubai Hills Estate Properties for Sale
Compare the Emaar projects for sale in this community, with current prices, payment plans and handover dates.
See Dubai Hills Estate Properties for Sale
Dubai Hills Estate Community Overview
Read the Dubai Hills Estate guide: 2,700 acres of parks, an 18-hole championship golf course and Dubai Hills Mall.
Explore the Dubai Hills Estate Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileFAQs
Palace Residences Hillside Construction Progress in May 2026: Frequently Asked Questions
As of the RERA inspection conducted on 05 May 2026, Palace Residences Hillside stands at 7.87% construction progress in the DLD project register, where it is recorded as Palace Residences Hillside A under project number 4015. The inspection report describes contractor mobilization as ongoing, with enabling and foundation works progressing.
The DLD record moved from a previous inspection reading of 5.77% to 7.87% on 05 May 2026, a gain of 2.10 points. Those points were earned below ground on the substructure works, so almost nothing of the gain is visible from the road at this stage of the project.
Yes. Expected completion dates in the DLD project register can be revised between inspection cycles. The date shown here reflects the record as it stood at the 05 May 2026 inspection of project 4015, and any revision would appear in a later update on this cluster.
The 05 May 2026 inspection report records mobilization ongoing and enabling and foundation works progressing on plot 5410. The registered building description is a single basement, ground floor, one podium level, twenty residential floors, a mechanical level and roof, so the works certified in this cycle sit at and below the lowest of those levels.
The developer payment schedule places the second instalment of 10% in May 2026, the same month as this inspection. It is a calendar dated instalment rather than a construction linked one; the first construction linked instalment on the published plan is tied to 50% completion in September 2027. Your own sale and purchase agreement governs and should be read directly.
The DLD register still showed 30 June 2029 as expected completion at the 05 May 2026 inspection, with 92.13 percentage points and just over three years separating the two. Construction start was recorded on 30 September 2025, so the project reached 7.87% in roughly seven months of certified work. How inspection cycles run through to completion certification is covered on the Palace Residences Hillside construction updates hub.
A Question the FAQ Can Not Answer?

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is helping you read the May 2026 inspection record for Palace Residences Hillside at Dubai Hills Estate correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.