Emaar · Dubai Hills Estate
Palace Residences Hillside at Dubai Hills Estate Construction Updates
Foundation-Stage Progress Tracked Inside a Finished Dubai Hills Community
Palace Residences Hillside recorded 7.87% construction at its 05 May 2026 RERA inspection, an early reading that establishes the foundation pace behind a June 2029 handover.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Palace Residences Hillside at Dubai Hills Estate at a Glance
Palace Residences Hillside is Emaar's 359-residence branded development inside Dubai Hills Estate, entered on the Dubai Land Department register as project 4015 on 07 August 2025. Seven months separate its 30 September 2025 construction start from the 7.87% recorded at the May 2026 inspection, so this record begins at the very bottom of the curve rather than partway up it. What makes the position unusual is the ground around it: plot 5410 sits inside a master community whose golf course, park, mall and schools were finished years before this foundation was poured, so the only thing still under construction here is the building itself.
4015
Active
30 September 2025
359 residential units
34,920.15 sq m
30 June 2029 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Palace Residences Hillside at Dubai Hills Estate Construction Update Timeline
This record opens with one dated cycle: 7.87% certified at the inspection of 05 May 2026, against a previous certified reading of 5.77% that the DLD register carries without a date. The 2.10 points between the two were earned in enabling and foundation activity on plot 5410, which is why the track below still sits close to its starting cap. Each future cycle is added as a dated row here, and the table links the full site report for every reading.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| May 2026 | 7.87% | 05 May 2026 | View the May 2026 update |
The 5.77% previous reading is plotted on the track above but has no published inspection date in the DLD record, so it is not given a dated row. Registered completion for project 4015 stands at 30 June 2029 and has not lapsed.
Pace Analysis
How Fast Palace Residences Hillside at Dubai Hills Estate Has Been Built
With one dated inspection on the record, pace at Palace Residences Hillside is measured two ways: against the construction start date, and against the previous certified reading.
- 30 Sep 2025 to 05 May 2026: mobilization, enabling works and foundations, 0% to 7.87%About 1.1 points per month
- Previous certified reading to 05 May 2026: 5.77% to 7.87%, interval undated in the register2.10 points added
A curve this short cannot yet show acceleration or taper, but it can be tested against the distance left to cover. Seven months of below-grade work bought 7.87%, and that is normal arithmetic for excavation and foundations: certified value climbs slowly while the crew is working under the ground line, then jumps once floor plates start repeating. From 7.87% on 05 May 2026 to the registered completion date of 30 June 2029, the project has 92.13 points and about 37 months left, which averages roughly 2.5 points per month. That is the number to hold against every future reading on this page. For an end user, it sets the honest expectation that the next few cycles will move in single points; for an investor, the payment plan does the same work from the other side, since the instalments dated October 2026 and March 2027 fall due before the 50 percent construction trigger scheduled for September 2027.
Get the Next Inspection Figure First
Tell me you are tracking Palace Residences Hillside at Dubai Hills Estate and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Palace Residences Hillside at Dubai Hills Estate
A foundation-stage percentage only means something next to what those foundations are going to carry. The project guide covers the 359 residences, the resort amenity programme and the pricing behind this record:

Palace Residences Hillside Project Guide
Layouts across 359 branded residences from one bedroom apartments to three bedroom townhouses, the resort amenity deck, the position inside the Dubai Hills Estate masterplan, and pricing from AED 1.71M ≈ USD 466K.
View the Palace Residences Hillside at Dubai Hills Estate Project GuideConsidering an Early-Stage Entry?
Availability at Palace Residences Hillside shifts as the build advances and the dated instalments already fallen due are added to a later entry. If the record on this page is what brought you here, ask me what is still released before the next cycle publishes.
Ask About Remaining Availability on WhatsAppStage Record
Palace Residences Hillside at Dubai Hills Estate Build Stages, Mapped to the Inspections
One inspection has been certified so far, so the stages below split into what the record already proves and what the developer payment plan schedules next. Every window is taken from the project 4015 register or from the plan's own construction triggers, never from a generic build sequence.
Registration and Site Handover
Project 4015 was registered with the Dubai Land Department on 07 August 2025 and construction on plot 5410 was recorded as started on 30 September 2025.
Enabling Works and Foundations
The 05 May 2026 inspection found mobilization ongoing with enabling and foundation works progressing, moving the certified figure from 5.77% to 7.87%.
Basement, Podium and Twenty Floors
The structural stage this record has not reached: the basement, ground floor, podium level and twenty residential floors registered for this building, plus the mechanical level and roof.
Facade, Fit-Out and Amenity Deck
Enclosure and interior fit-out, together with the resort pool deck, padel court and nursery facility registered among the project amenities.
Finishing, Commissioning and Handover
Final finishing and systems commissioning ahead of the 30 June 2029 registered completion date, when the closing 20 percent instalment falls due.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Palace Residences Hillside at Dubai Hills Estate's own record.
Buyer Position
Tracking Your Position at Palace Residences Hillside at Dubai Hills Estate
This page is one of four project resources that together cover a Palace Residences Hillside at Dubai Hills Estate purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Palace Residences Hillside at Dubai Hills Estate Construction Updates
This page: the certified inspection record for Palace Residences Hillside, from 7.87% foundations to handover.

Palace Residences Hillside at Dubai Hills Estate Golden Visa
Check whether a qualifying Palace Residences Hillside purchase supports ten year UAE Golden Visa residency eligibility.
Read the Palace Residences Hillside at Dubai Hills Estate Golden Visa Guide
Palace Residences Hillside at Dubai Hills Estate Escrow Account
See how each dated instalment at Palace Residences Hillside tracks the project 4015 escrow account.
Verify the Palace Residences Hillside at Dubai Hills Estate Escrow AccountApproaching Handover
Between 7.87% and Handover: What Palace Residences Hillside at Dubai Hills Estate Buyers Should Do Now
At foundation stage the distance to handover is covered by paperwork and payments long before it is covered by visible building, which makes this the quietest and most useful window in the whole purchase. The instalments dated October 2026 and March 2027 fall due on calendar dates rather than on progress, so the three steps below belong in the next few weeks, not in the month a payment request arrives.
First, match every dated instalment in your plan against the certified milestones on the Palace Residences Hillside escrow account page, so you know which payments are calendar-driven and which follow the 50, 70 and 90 percent construction triggers.
Second, follow the record cycle by cycle rather than year by year; the May 2026 inspection report for Palace Residences Hillside is the baseline every later reading on this page is measured against.
Third, if residency is part of why you bought, settle eligibility now through the Palace Residences Hillside Golden Visa guide, because the application path differs before and after the title deed is issued at handover.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Dubai Hills Estate Structure
A build record reads differently depending on what surrounds the site. These three pages set the 7.87% reading against the community already trading around it, the developer delivering it, and the homes selling there today:

Dubai Hills Estate Properties for Sale
Compare the Emaar projects for sale in this community, with current prices, payment plans and handover dates.
See Dubai Hills Estate Properties for Sale
Dubai Hills Estate Community Overview
Read the Dubai Hills Estate guide: 2,700 acres of parks, an 18-hole championship golf course and Dubai Hills Mall.
Explore the Dubai Hills Estate Community
Emaar Properties Developer Profile
Explore Emaar the developer behind Burj Khalifa, Downtown Dubai and more than twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Palace Residences Hillside at Dubai Hills Estate Construction Updates Frequently Asked Questions
Palace Residences Hillside is an active DLD-registered project (number 4015, registered as Palace Residences Hillside A) in its enabling and foundation phase, recorded at 7.87% at the inspection of 05 May 2026. The full record is in the inspection timeline above.
The 05 May 2026 inspection recorded 7.87% construction progress, up 2.10 points from the previous certified reading of 5.77%. The inspection notes for that visit list mobilization ongoing with enabling and foundation works progressing, and the full report is in the Palace Residences Hillside May 2026 construction update.
Measured from the 30 September 2025 construction start, the 7.87% certified on 05 May 2026 averages about 1.1 percentage points per month. Reaching 100% by the registered date of 30 June 2029 means covering the remaining 92.13 points at roughly 2.5 points per month, the step up that arrives with structural work above ground. The phase breakdown is in the pace analysis above.
The DLD-registered completion date for project 4015 is 30 June 2029, matching the June 2029 handover in the developer payment plan, where the final 20 percent instalment falls due at 100 percent construction completion. With 7.87% recorded on 05 May 2026 the project sits early in that runway, and this page is updated each time an inspection is recorded.
The project comprises 359 residential units across one, two and three bedroom apartments plus three bedroom townhouses. The DLD register describes the building as a single basement, ground floor, one podium level, twenty residential floors, a mechanical level and roof, with a children nursery among the facilities. Layouts and sizes are set out in the Palace Residences Hillside project overview.
Construction officially started on 30 September 2025, under eight weeks after the project was registered with the Dubai Land Department on 07 August 2025. The first cycle published on this page, inspected on 05 May 2026, recorded 7.87%.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Palace Residences Hillside at Dubai Hills Estate construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.