Emaar · The Oasis
Palace Villas Ostra Construction Updates
The Verified Build Record for Emaar's Palace-Branded Villa Enclave
Palace Villas Ostra recorded 6.54% construction progress at its 20 July 2026 RERA inspection, the earliest dated reading in a villa build running toward Q3 2029.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Palace Villas Ostra at a Glance
Palace Villas Ostra is Emaar's Palace-branded enclave of 526 stand-alone villas on plot 2307 in Me'Aisem Second, inside The Oasis. Eleven and a half months separate the 05 August 2025 construction start from the 6.54% logged at the July 2026 inspection, and every card below is a registered value drawn from the same DLD file behind that reading. Because the collection is 526 separate houses rather than one structure, the percentage on this page aggregates rows sitting at different stages on the same day, which is why an early figure here behaves differently from an early figure on a tower.
3581
Active
05 August 2025
526 stand-alone villas
30 September 2029 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Palace Villas Ostra Construction Update Timeline
One dated inspection anchors this record so far: 6.54% verified on 20 July 2026, eleven and a half months after work started on the plot. A second figure of 3.11% sits in the register as a prior reading with no date beside it, so it is described here in words and deliberately kept off the track and out of the table, both of which only accept entries carrying their own date. Each new cycle is added as it publishes, with the full site report linked from its row.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| July 2026 | 6.54% | 20 July 2026 | View the July 2026 update |
Pace Analysis
How Fast Palace Villas Ostra Has Been Built
With a single dated reading in the register, no velocity between two inspections can be measured on this project yet. What the record does support is arithmetic against the fixed dates around that reading:
- 05 Aug 2025 start to 20 Jul 2026 inspection: 0% to 6.54%, derived averageAbout 0.6 points per month
- Undated prior reading to 20 Jul 2026: 3.11% to 6.54%, interval unpublished3.43 points gained
- 20 Jul 2026 to 30 Sep 2029 registered completion: 93.46 points to closeAbout 2.4 points per month implied
The gap between those two rates is the honest headline. A derived 0.6 points per month across the first eleven and a half months is normal for a villa program in its enabling and foundations band, where excavation, services, and plot-by-plot mobilization consume calendar without moving a percentage that only rewards completed work. Reaching 30 September 2029 asks for roughly four times that rate, which is exactly what a 526-plot site is built to deliver once superstructure runs in parallel across rows instead of sequentially. The figure to watch is not this reading but the next two: whether the curve turns upward as rows multiply is the first real evidence of whether the Q3 2029 date holds, and neither number above is a measured inter-inspection velocity until a second dated reading exists.
Get the Next Inspection Figure First
Tell me you are tracking Palace Villas Ostra and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Palace Villas Ostra at The Oasis Emaar
A percentage is only meaningful once you know what it is building. The project guide sets out what the 6.54% recorded here is working toward:

Palace Villas Ostra, Palace-Branded Lagoon Villas at The Oasis
Palace Villas Ostra is Emaar's Palace-branded enclave of 526 stand-alone villas around a swimmable lagoon, urban canals and a clubhouse.
View the Palace Villas Ostra Project GuideConsidering an Early-Stage Entry?
Limited villas are listed as available at Palace Villas Ostra, and plot position, bedroom count, and elevation style are all still selectable at this band. Tell me the row and the size you want and I will confirm what is left against the current release.
Ask About Remaining Availability on WhatsAppStage Record
Palace Villas Ostra Build Stages, Mapped to the Inspections
Each stage below is pinned to the window it actually occupied on this site rather than to a textbook sequence, which is what makes the position of the 20 July 2026 reading legible against the four stages still ahead of it.
Registration and Site Handover
Project 3581 entered the DLD register on 06 March 2025, with the escrow trust account opened at First Abu Dhabi Bank before plot 2307 was released to the contractor.
Mobilization, Enabling and Foundations
From the 05 August 2025 start: excavation, services, and foundations opening across the villa rows, with the earliest rows already carrying substructure at the 20 July 2026 inspection.
Superstructure Across the Rows
The 526 villas rise to their B+G+2 format in parallel clusters. This is the stage that carries the reading from 6.54% through the 20% instalment trigger, 13.46 points above it.
Envelope, MEP and Internal Finishing
Roofing, glazing, services, and internal packages per villa, running alongside the lagoon, canal, and clubhouse works that share the same project registration.
Landscaping, Commissioning and Handover
Plot landscaping, private pools, community amenity delivery, and final approvals close the remaining 93.46 points toward the registered completion date.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Palace Villas Ostra's own record.
Buyer Position
Tracking Your Position at Palace Villas Ostra
This page is one of four project resources that together cover a Palace Villas Ostra purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Palace Villas Ostra Construction Updates
The dated inspection record for Palace Villas Ostra, tracked from 6.54% through to Q3 2029.

Palace Villas Ostra Golden Visa, Cleared Many Times Over
Palace Villas Ostra, Emaar's 526-villa community in The Oasis, clears the threshold at every tier, the lowest more than six times.
Read the Palace Villas Ostra Golden Visa Guide
Palace Villas Ostra Escrow: Emaar's Branded Villas at The Oasis
Palace Villas Ostra escrows 526 units with First Abu Dhabi Bank under DLD project 3581, certified 6.54% in July 2026.
Verify the Palace Villas Ostra Escrow AccountApproaching Handover
Between 6.54% and Handover: What Palace Villas Ostra Buyers Should Do Now
The Emaar schedule for this project turns construction-linked from the fourth instalment onward, at 20, 40, 60, 80, and 100 percent completion. At 6.54% the first of those triggers is 13.46 points away, which puts a buyer here in the administrative window rather than the paying-heavily one. That window is short in practice, because once the reading crosses a trigger the demand follows quickly, so the three steps below belong to this band rather than the next one.
First, confirm where your money lands: every instalment on this project belongs in the DLD-regulated escrow account held with First Abu Dhabi Bank, and the Palace Villas Ostra escrow account page shows how each release is tied to certified progress.
Second, read your own sale and purchase agreement against the milestone ladder rather than the marketing schedule, then follow the inspection record cycle by cycle so the 20% call arrives expected rather than announced.
Third, if residency is part of why you bought, settle eligibility early through the Palace Villas Ostra Golden Visa guide, since the route differs between the off-plan registration stage and the title deed issued after handover.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore The Oasis Emaar Structure
An inspection percentage is only as useful as the context around it: the clusters being delivered alongside Ostra, the masterplan absorbing all of them, and the developer carrying the schedule. These three pages hold that context:

The Oasis Emaar Properties for Sale
Browse waterfront villas and mansions for sale across The Oasis clusters, with prices, layouts and payment plans.
See The Oasis Emaar Properties for Sale
The Oasis by Emaar: Lagoon Villas and Mansions in Dubailand
The Oasis holds about 3,100 villas and mansions in Dubailand, with more than 40 percent of its land given to lagoons.
Explore the The Oasis Emaar Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Palace Villas Ostra Construction Updates Frequently Asked Questions
Palace Villas Ostra is an active DLD-registered project (number 3581) in its enabling and foundations band, recorded at 6.54% at the inspection of 20 July 2026. Every dated reading held on this project sits in the inspection timeline above.
The 20 July 2026 inspection recorded 6.54% construction progress, 3.43 points above the 3.11% that sits beside it in the register as a prior reading. That prior reading carries no date, which is why this page treats the 3.43 points as a gain of unknown duration rather than a rate. The site report for the cycle is in the July 2026 construction update.
One dated reading cannot produce a measured velocity between two inspections, so both figures on this page are derived. Across the 11.5 months from the 05 August 2025 construction start to 20 July 2026, the derived average works out at roughly 0.6 percentage points per month; the 93.46 points outstanding against a 30 September 2029 registered completion imply about 2.4 points per month from here. The working is set out in the pace analysis above.
The DLD-registered completion date for project 3581 is 30 September 2029, placing handover in Q3 2029, and the inspection of 20 July 2026 recorded 6.54% against that target. Registered completion dates can be revised between inspection cycles on a project with this much build window remaining, and this page's record is updated when each new inspection is recorded.
DLD registration records 526 units for project 3581: detached villas offered in three sizes, four, five and six bedrooms, every one of them built to the B+G+2 format carried in the inspection file for plot 2307 in Me'Aisem Second. Layouts, sizes, and the wider investment case are covered in the Palace Villas Ostra by Emaar project guide.
Project 3581 was registered with the Dubai Land Department on 06 March 2025, and construction officially started on 05 August 2025. The first dated inspection in the register arrived 11.5 months later, on 20 July 2026, at 6.54%.
The 20 July 2026 inspection logged mobilization still under way and ground-level packages spread unevenly across the plot: some villa rows at enabling stage, others at foundation or substructure, and the earliest rows at first superstructure, with infrastructure works running in parallel. At 6.54% nothing above ground is finished, and the figure reflects work distributed across 526 separate plots rather than one rising building.
Plot 2307 in Me'Aisem Second holds the Palace-branded enclave inside Emaar's Oasis masterplan, arranged around a swimmable lagoon with canals running between the villa clusters off Yalayis Street. That enclave infrastructure falls inside the same registered project, so lagoon and canal works form part of the scope behind the 6.54% recorded on 20 July 2026.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Palace Villas Ostra construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.