Emaar · Dubai Hills Estate
Palm Hills at Dubai Hills Estate Construction Updates
The Closed Build Record for 74 Villas Inside Dubai Hills Estate
The DLD register records Palm Hills at 100% construction for the 09 April 2025 inspection, and the RERA report for that same visit gives a Progress Status of Completed.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Palm Hills at Dubai Hills Estate at a Glance
Palm Hills is a gated cluster of 74 five-bedroom villas inside Dubai Hills Estate, built on plot 4380 at Hadaeq Sheikh Mohammed Bin Rashid and registered with the Dubai Land Department as project 2263. Construction started on 15 August 2021, and the register now reads Finished with 100% recorded at the inspection of 09 April 2025. What makes this record unusual is its shape: an entire horizontal build of 74 villas sits behind a single dated inspection, which is why the registration anchors below carry more of the story here than the percentage does.
2263
Finished
15 August 2021
74 villas
18,126.06 sq m
31 October 2024 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Palm Hills at Dubai Hills Estate Construction Update Timeline
One dated inspection stands for this whole build. On 09 April 2025 the register moved Palm Hills to 100% from a previous reading of 93.3%, a step of 6.7 percentage points, and the RERA report for that same visit entered the Progress Status as Completed. No inspection date is recorded against the 93.3% figure anywhere in the register, so the track below places it by percentage alone and the table carries only the reading that can be dated.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| April 2025 | 100% | 09 April 2025 | View the April 2025 update |
Reading the dates: project 2263 carries a registered completion date of 31 October 2024, while the inspection that recorded 100% and a Completed progress status is dated 09 April 2025. The register prints the two as separate entries with nothing on the record connecting them, and handover itself is now recorded as Ready rather than as a future quarter. Ask for the current handover status on WhatsApp .
Pace Analysis
How Fast Palm Hills at Dubai Hills Estate Has Been Built
Pace on Palm Hills cannot be read the way it is read on a project with several dated inspections. Exactly one inspection date exists, so the only honest arithmetic runs across the full named span:
- 15 Aug 2021 construction start to the 09 Apr 2025 inspection: zero to 100%About 2.3 points per month
- Previous reading of 93.3% to the 100% recorded on 09 Apr 20256.7 points, no dated span
The 2.3 figure is stated as arithmetic and nothing more: it divides the full 100 points by the 43.8 months between the 15 August 2021 start and the 09 April 2025 inspection, and it does not claim to describe how the villas actually rose month by month. The one interior data point in this record, the undated 93.3% reading, makes the limit plain rather than fixing it, because a step of 6.7 points with no date attached can never be converted into a rate. Read the number as a delivery benchmark for a 74-villa horizontal build inside Dubai Hills Estate, and read it as history: with the programme entered as Completed there is no remaining span left to forecast.
Get the Next Inspection Figure First
Tell me you are tracking Palm Hills at Dubai Hills Estate and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Palm Hills at Dubai Hills Estate
A closed percentage only matters once you know what was delivered against it. The full project guide covers the villas this record was tracking:

Palm Hills at Dubai Hills Estate: Gated Villas with Elie Saab Interiors
Palm Hills at Dubai Hills Estate gathers 74 five bedroom Emaar villas behind a gate, each built ground plus two.
View the Palm Hills at Dubai Hills Estate Project GuideConsidering a Villa in a Completed Cluster?
Buying after the record closes removes construction risk from the decision entirely: the villas are standing and the register reads Finished. What is left is which of them is still available, and that shifts between listings without notice.
Ask About Remaining Availability on WhatsAppStage Record
Palm Hills at Dubai Hills Estate Build Stages, Mapped to the Inspections
Palm Hills was a horizontal build, so its stages ran outward across a street grid instead of upward through a facade, and the register dates only two points along that run. Each stage below is placed against what the Palm Hills record can actually evidence, with the undated stretches named rather than filled in.
Site Start on Plot 4380
Construction began on 15 August 2021 at Hadaeq Sheikh Mohammed Bin Rashid, just over nine weeks after project 2263 was registered on 08 June 2021.
Concrete Structure and Block Work
The monitoring report describes Palm Hills as a concrete structure and block build across ground plus two villas. No inspection percentage is dated inside this stretch.
Internal and External Finishes
The same report lists internal and external finishes as part of the scope. The 93.3% figure on the register sits somewhere in here, carrying no date at all.
Streets, Verges and Entrances
The four RERA site photographs taken on 09 April 2025 show finished asphalt between the plots, landscaped verges, covered entrance canopies and glazed villa frontages.
Closed Record and Handover
The 09 April 2025 inspection recorded 100% and entered the Progress Status as Completed. Handover is Ready, and Emaar's note at that visit still listed snags, minor items and repairs at building level.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Palm Hills at Dubai Hills Estate's own record.
Buyer Position
Tracking Your Position at Palm Hills at Dubai Hills Estate
This page is one of four project resources that together cover a Palm Hills at Dubai Hills Estate purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Palm Hills at Dubai Hills Estate Construction Updates
This page: the closed Palm Hills inspection record, from the 2021 start to 100% in 2025.

Palm Hills at Dubai Hills Estate Golden Visa on a Title Deed
Palm Hills at Dubai Hills Estate, a 74 villa Emaar enclave, has one 5 bedroom typology, roughly nine times the minimum.
Read the Palm Hills at Dubai Hills Estate Golden Visa Guide
Palm Hills at Dubai Hills Estate: A Small Emirates Islamic Escrow
Palm Hills at Dubai Hills Estate is a 27-unit Emaar release, DLD project 2263, whose buyers paid into Emirates Islamic escrow.
Verify the Palm Hills at Dubai Hills Estate Escrow Account
Palm Hills at Dubai Hills Estate Snagging: Flora and Bloom Villas
Palm Hills at Dubai Hills Estate is an Emaar cluster of 74 five bedroom villas, with interiors designed by Elie Saab.
Book Palm Hills at Dubai Hills Estate SnaggingApproaching Handover
Between 100% and Handover: What Palm Hills at Dubai Hills Estate Buyers Should Do Now
With the register at 100% and the progress status entered as Completed, nothing further will move on the construction side of a Palm Hills purchase. Everything left sits on the handover side, and it runs in sequence: once you sign acceptance for a villa, any defect you did not document first becomes yours to chase, which is why the three steps below belong before the key collection appointment rather than after it.
First, arrange independent snagging while the handover process is still open; the Palm Hills snagging inspection page sets out what gets documented, and a Completed status at project level says nothing about the finish inside one villa.
Second, check any remaining balance against the DLD registered escrow account for project 2263 before it moves; the Palm Hills escrow account page carries the Emirates Islamic Bank registration and how to verify it yourself.
Third, if the purchase is meant to support residency, settle eligibility through the Palm Hills Golden Visa guide before the title deed is issued, since the deed timing sets the application path.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Dubai Hills Estate Structure
A closed build record is only half the picture; the other half is the district the villas stand in and the developer that handed them over. These three pages put the Palm Hills record in context:

Dubai Hills Estate Properties for Sale
Compare the Emaar projects for sale in this community, with current prices, payment plans and handover dates.
See Dubai Hills Estate Properties for Sale
Dubai Hills Estate Community Overview
Read the Dubai Hills Estate guide: 2,700 acres of parks, an 18-hole championship golf course and Dubai Hills Mall.
Explore the Dubai Hills Estate Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Palm Hills at Dubai Hills Estate Construction Updates Frequently Asked Questions
Palm Hills is recorded as Finished on the Dubai Land Department register for project 2263, with construction progress at 100% as of the inspection dated 09 April 2025 and a RERA Progress Status of Completed for that same visit. Handover is recorded as Ready. The dated entries behind that status are set out in the inspection record above.
The inspection of 09 April 2025 put Palm Hills at 100%, 6.7 percentage points above a previous reading of 93.3%. That previous figure carries no inspection date anywhere in the register, so the movement is a step between two readings and cannot be expressed as monthly progress. The full entry is published in the April 2025 Palm Hills inspection update.
Construction ran from 15 August 2021 to the 09 April 2025 inspection, a span of roughly 43.8 months, or close to three years and eight months. Spreading the full 100 points across that named span gives about 2.3 percentage points per month. That figure is plain arithmetic over the whole build and not a monthly observed rate, and with the programme recorded Completed it is not a forecast of anything. The working is shown in the pace analysis above.
The register holds a completion date of 31 October 2024 against project 2263, and the inspection that recorded 100% with a Completed status is dated 09 April 2025. The two entries are printed separately with nothing on the record linking them, and handover for Palm Hills is now recorded as Ready rather than as a future quarter.
Palm Hills is a gated cluster of 74 five-bedroom villas in a ground plus two configuration, delivered across the Flora and Bloom collections with interiors designed by Elie Saab. Layouts, sizes and the full investment case sit in the Palm Hills at Dubai Hills Estate project guide.
Because the register carries only one dated inspection for project 2263. Progress before 09 April 2025 survives on the record as a single undated figure of 93.3%, which cannot be published as a month, and the 09 April 2025 reading is the one that closed the monitoring programme at Completed. That single reading is documented in the April 2025 Palm Hills construction update.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Palm Hills at Dubai Hills Estate construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.