Emaar · Dubai Hills Estate
Park Gate 2 at Dubai Hills Estate Construction Updates
The Verified Build Record for Seventeen Villas at the Dubai Hills Estate Entrance
Park Gate 2 reached 55.15% construction at its 8 June 2026 RERA inspection, with structure complete across all seventeen villas and envelope, MEP, and finishing works underway.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Park Gate 2 at Dubai Hills Estate at a Glance
Park Gate 2 is Emaar's seventeen-villa release on plot 5713, at the entrance of Dubai Hills Estate. Construction started on 17 June 2025 and the 8 June 2026 inspection recorded 55.15%, so more than half the build was audited inside the first twelve months. Seventeen homes make an unusually short register for a Dubai project, which is why a single cycle here moves the percentage in steps a thousand-unit tower never produces. The figures below are the DLD-registered anchors behind that record.
3641
Active
17 June 2025
17 villas (13 four bedroom, 4 five bedroom)
8,218.38 sq m
28 February 2027 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Park Gate 2 at Dubai Hills Estate Construction Update Timeline
This record opens with one published reading. The register carries 55.15% for project 3641 at the inspection of 8 June 2026, against 47.69% at the cycle before it, a step of 7.46 points. That earlier figure is held in the register without a published date, so the track below plots it as the previous cycle rather than against a month it cannot be pinned to. Each table row links the full report for its period.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| June 2026 | 55.15% | 8 June 2026 | View the June 2026 update |
Pace Analysis
How Fast Park Gate 2 at Dubai Hills Estate Has Been Built
With one dated reading in the register, pace at Park Gate 2 is read two ways: the average earned since the site opened, and the step between the last two audited cycles.
- 17 Jun 2025 start to 8 Jun 2026: enabling, foundations, structure, early envelope, 0% to 55.15%About 4.7 points per month
- Previous audited cycle to 8 Jun 2026: 47.69% to 55.15%, cycle interval not publishedPlus 7.46 points
The first twelve months carried the heavy load. Enabling, piling, foundations, and the full ground-plus-two frame of every villa were all signed off as complete at the June 2026 visit, and that is the work behind an average of 4.7 points a month. What comes next behaves differently. The same report leaves six packages open at once, from the external envelope and MEP through internal works and finishes to the external and infrastructure scope, and on a seventeen-plot enclave those trades run side by side across the site instead of stacking floor by floor up a tower, so the register tends to move in broader steps with longer gaps rather than a smooth climb. Reaching 100% by the registered date of 28 February 2027 asks for roughly 5.2 points a month across the remaining 44.85, modestly above the pace recorded so far. For an owner, that number is the one to check against the next cycle. For an investor weighing the Q1 2027 window, a project whose structure is already closed out and whose remaining scope is fit-out and infrastructure carries a different risk profile from one still pouring concrete at the halfway mark.
Get the Next Inspection Figure First
Tell me you are tracking Park Gate 2 at Dubai Hills Estate and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Park Gate 2 at Dubai Hills Estate
A build percentage only means something next to what is being delivered. The full project guide covers what the 55.15% is measured against:

Park Gate 2 Project Guide
Four and five bedroom villas from AED 14.12M ≈ USD 3.84M, built-up areas of 5,146 and 5,392 sq ft, rooftop garden terraces, the instalment schedule that ends at 100% construction completion, and where this enclave sits inside the Dubai Hills Estate masterplan.
View the Park Gate 2 at Dubai Hills Estate Project GuideConsidering an Entry Before Handover?
Park Gate 2 is quoted as having limited units available, and on a release this small availability shifts between cycles as the build moves toward completion. If the 55.15% reading is what brought you here, ask me which villas are still unsold.
Ask About Remaining Availability on WhatsAppStage Record
Park Gate 2 at Dubai Hills Estate Build Stages, Mapped to the Inspections
Each stage below is tied to what the register and the June 2026 report actually record for Park Gate 2, with the window it occupied, so you can see which part of the work the 55.15% stands for.
Site Activation and Enabling Works
The register opens at the 17 June 2025 construction start, two months after project 3641 was registered on 9 April 2025: site enabling and piling on plot 5713.
Piling and Foundations
Piling and foundation works across all seventeen plots were listed as completed in the 8 June 2026 report, alongside the enabling package.
Ground-Plus-Two Villa Structure
The full G+2 frame of every villa is signed off as complete in the same report. That structural close-out is what carried the register past halfway to 55.15%.
Envelope, MEP, and Internal Finishes
Six packages sit open at this reading: external envelope, MEP, internal works, internal finishes, external works, and infrastructure. That is the phase 55.15% falls inside.
External Works, Infrastructure, and Delivery
The remaining 44.85 points cover external and infrastructure works, testing and commissioning, and building completion certification ahead of the Q1 2027 handover window.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Park Gate 2 at Dubai Hills Estate's own record.
Buyer Position
Tracking Your Position at Park Gate 2 at Dubai Hills Estate
This page is one of four project resources that together cover a Park Gate 2 at Dubai Hills Estate purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Park Gate 2 at Dubai Hills Estate Construction Updates
This page: every recorded inspection for Park Gate 2, from the June 2025 start toward handover.

Park Gate 2 at Dubai Hills Estate Golden Visa
Check how a Park Gate 2 villa purchase supports ten-year UAE Golden Visa residency eligibility.
Read the Park Gate 2 at Dubai Hills Estate Golden Visa Guide
Park Gate 2 at Dubai Hills Estate Escrow Account
Every instalment on project 3641 lands in the escrow trust account held with Emirates NBD.
Verify the Park Gate 2 at Dubai Hills Estate Escrow AccountApproaching Handover
Between 55.15% and Handover: What Park Gate 2 at Dubai Hills Estate Buyers Should Do Now
The remaining 44.85 points are earned in fit-out, external works, and infrastructure, work that is easy to under-read from outside a villa plot because nothing new rises above the roofline. Two payments on the Emaar schedule fall inside that window, one in October 2026 and the closing instalment at 100% construction completion in February 2027, so the checks below belong to the months before those dates rather than to handover week.
First, match your remaining payments to the register rather than to the calendar; the Park Gate 2 escrow account page sets out how funds for project 3641 are released against certified progress.
Second, follow the record itself, cycle by cycle. The June 2026 construction update is the current entry and carries the inspector notes behind the 55.15% figure, and each new reading is published the same way.
Third, if residency is part of the plan, settle eligibility before the title deed is issued using the Park Gate 2 Golden Visa guide, because the application path differs before and after registration.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Dubai Hills Estate Structure
Seventeen villas are being finished inside a community that was largely delivered before they broke ground. These three pages put the Park Gate 2 percentage in that setting:

Dubai Hills Estate Properties for Sale
Compare the Emaar projects for sale in this community, with current prices, payment plans and handover dates.
See Dubai Hills Estate Properties for Sale
Dubai Hills Estate Community Overview
Read the Dubai Hills Estate guide: 2,700 acres of parks, an 18-hole championship golf course and Dubai Hills Mall.
Explore the Dubai Hills Estate Community
Emaar Properties Developer Profile
Explore Emaar the developer behind Burj Khalifa, Downtown Dubai and more than twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Park Gate 2 at Dubai Hills Estate Construction Updates Frequently Asked Questions
Park Gate 2 is an active DLD-registered project, number 3641, recorded at 55.15% construction progress at the inspection of 8 June 2026. Everything structural is closed out at that reading: the enabling package, piling, foundations, and the villa frames themselves. What stays open is the fit-out side, six packages running at once across the plots. Every recorded reading is listed in the inspection timeline above.
The 8 June 2026 inspection recorded 55.15%, a rise of 7.46 points from the 47.69% carried at the previous audited cycle. The report behind that figure, including the inspector notes and site photographs, is published on the Park Gate 2 June 2026 construction update page.
Measured from the 17 June 2025 construction start to the 8 June 2026 inspection, the register averages about 4.7 percentage points per month to reach 55.15%. Closing the remaining 44.85 points by the registered date of 28 February 2027 would take roughly 5.2 points per month, modestly above that average. The working is set out in the pace analysis above.
The Dubai Land Department register carries 28 February 2027 as the completion date for project 3641, inside the Q1 2027 handover window quoted for the villas, and the latest recorded reading was 55.15% on 8 June 2026. Registered dates are administrative targets that can move as inspection cycles are audited, and the record on this page is updated when the next reading is published.
Seventeen. Thirteen four-bedroom villas carry a built-up area of 5,146 sq ft (478 sq m) each and four five-bedroom villas carry 5,392 sq ft (501 sq m) each. The RERA inspection report describes the project as G+2 villas consisting of 17 units, which is the same count held against project 3641 in the DLD register.
Project 3641 was registered on 9 April 2025 and construction started on 17 June 2025. The first reading published on this page is the 55.15% recorded on 8 June 2026, which represents just under twelve months of audited work on plot 5713.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Park Gate 2 at Dubai Hills Estate construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.