Emaar · Dubai Hills Estate
Parkland at Dubai Hills Estate Construction Updates
The Verified Build Record on the Park and Retail Edge of Dubai Hills
Parkland recorded 50.02% construction at its 22 June 2026 RERA inspection, with structure, envelope and services now certified as running together toward Q4 2028 handover.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Parkland at Dubai Hills Estate at a Glance
Parkland is Emaar's 209-apartment address on plot 4944: one 23-storey tower over an amenity podium, positioned where Dubai Hills Estate turns from park into retail. Just over nineteen months of build sit between the 02 November 2024 construction start and the 50.02% logged on 22 June 2026, and every anchor figure below is drawn from the DLD register for project 3139. Because a single structure carries the entire project, the percentage on this page means exactly what it says rather than averaging buildings standing at different heights.
3139
Active
02 November 2024
209 residential units
23,252.54 sq m
30 November 2028 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Parkland at Dubai Hills Estate Construction Update Timeline
One reading in this record carries an inspection date: 22 June 2026, at 50.02%. The DLD register also publishes an earlier figure of 30.62% with no date attached to it, so that reading is stated here in prose and deliberately left off the track and the table below rather than plotted against a date nobody recorded. The 19.40 point difference between the two figures is verified; the interval that produced it is not.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| June 2026 | 50.02% | 22 June 2026 | View the June 2026 update |
Pace Analysis
How Fast Parkland at Dubai Hills Estate Has Been Built
With a single dated inspection on file, no phase velocity between readings can honestly be calculated for this project. Two figures can be, and both are stated as what they are:
- Nov 2024 to Jun 2026: whole build average, 0% to 50.02% (derived from the dated record)About 2.5 points per month
- Jun 2026 to Nov 2028: rate implied by the registered completion date, 49.98 points remainingAbout 1.7 points per month
The comparison between those two numbers is the whole analysis. Parkland has averaged roughly 2.5 points per month across 19.6 months that include the slowest part of any build, the months spent below ground on enabling, piling and foundations before a single floor plate registers as progress. The rate now required to certify the remaining 49.98 points by 30 November 2028 is about 1.7 points per month, and that comes from arithmetic on the registered date rather than from any recorded velocity. A project entering its fastest structural and envelope phase while carrying a lower required rate than its historic average has schedule headroom, which is what an investor should be reading at the halfway point and what an end user planning a Q4 2028 move should want confirmed at each further inspection.
Get the Next Inspection Figure First
Tell me you are tracking Parkland at Dubai Hills Estate and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Parkland at Dubai Hills Estate
The build percentage only matters in the context of what is being delivered. The full project guide covers what buyers are tracking toward on this page:

Parkland at Dubai Hills Estate: A Walk from the Business Park
Parkland at Dubai Hills Estate is a 209 apartment Emaar address on the park and retail side of the community.
View the Parkland at Dubai Hills Estate Project GuideConsidering a Mid-Build Entry?
Inventory at Parkland is listed as limited and moves between inspection cycles, and each certified reading shortens the construction window a new buyer carries. If the record on this page is what brought you here, I can tell you what is genuinely available today.
Ask About Remaining Availability on WhatsAppStage Record
Parkland at Dubai Hills Estate Build Stages, Mapped to the Inspections
Each stage below is tied to what the Parkland record actually documents rather than to a textbook build sequence, so you can see which packages the 22 June 2026 inspection signed off and which it caught still moving.
Registration and Site Activation
Project 3139 entered the DLD register on 12 July 2024, with construction formally starting on 02 November 2024 and enabling works opening plot 4944 for the tower footprint.
Piling and Foundations
Enabling, piling and foundation works are all listed as completed in the 22 June 2026 inspection notes, which is the below-ground half of the programme signed off in the record.
Tower Structure to the Twenty Third Floor
Structure works on the ground to twenty third floor frame were still progressing when the inspection recorded 50.02%, with the envelope and services packages already running alongside rather than queued behind topping out.
Envelope, MEP and Internal Finishes
External envelope installation, mechanical, electrical and plumbing works, internal works and internal finishes were each logged as progressing on 22 June 2026, which is what produced a 19.40 point gain on the previous figure.
Podium Completion, Commissioning and Handover
Amenity podium and landscaping completion, systems commissioning and final approvals sit between the current reading and the 30 November 2028 registered completion date.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Parkland at Dubai Hills Estate's own record.
Buyer Position
Tracking Your Position at Parkland at Dubai Hills Estate
This page is one of four project resources that together cover a Parkland at Dubai Hills Estate purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Parkland at Dubai Hills Estate Construction Updates
This page: the verified inspection record for Parkland, from the 02 November 2024 start toward handover.

Parkland at Dubai Hills Estate Golden Visa: The Qualifying Line
The qualifying line at Parkland at Dubai Hills Estate, a 209-apartment Emaar tower, sits between the 1 and 2 bedroom tiers.
Read the Parkland at Dubai Hills Estate Golden Visa Guide
Parkland at Dubai Hills Estate Escrow, the Mashreq Account Explained
Parkland at Dubai Hills Estate takes payments into Mashreq escrow as DLD project 3139, 209 units, 50.02% certified June 2026.
Verify the Parkland at Dubai Hills Estate Escrow AccountApproaching Handover
Between 50.02% and Handover: What Parkland at Dubai Hills Estate Buyers Should Do Now
Parkland runs a construction linked payment plan, which makes each certified reading a payment event rather than a news item. The developer schedule releases instalments at 20%, 40%, 50%, 70%, 80% and 100% completion, and the 22 June 2026 figure has already carried the project past the 50% threshold ahead of the March 2027 date set against it, so the three checks below belong in the window before the next inspection publishes, not after it.
First, confirm that every remaining instalment is routed to the account the regulator recognises for project 3139; the Parkland escrow account page covers the lookup and what each release is tied to.
Second, read your own sale and purchase agreement against the certified percentage rather than the calendar, because the June 2026 reading has put those two triggers out of step, and only the agreement decides which of them releases your next payment.
Third, if residency is part of why you bought, settle eligibility well before the title deed stage through the Parkland Golden Visa guide, since on this project the outcome is set by the tier you own rather than by the project itself.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Dubai Hills Estate Structure
A build record is only half the picture; the other half is what is already standing around it. These three pages put Parkland's progress in its community, masterplan, and developer context:

Dubai Hills Estate Properties for Sale
Compare the Emaar projects for sale in this community, with current prices, payment plans and handover dates.
See Dubai Hills Estate Properties for Sale
Dubai Hills Estate Community Overview
Read the Dubai Hills Estate guide: 2,700 acres of parks, an 18-hole championship golf course and Dubai Hills Mall.
Explore the Dubai Hills Estate Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Parkland at Dubai Hills Estate Construction Updates Frequently Asked Questions
Parkland at Dubai Hills Estate is an active DLD-registered project (number 3139) recorded at 50.02% construction progress at the RERA inspection of 22 June 2026, with structure works, external envelope, MEP and internal finishes all logged as progressing. Every recorded reading sits in the inspection timeline above.
The 22 June 2026 inspection recorded 50.02%, which is 19.40 points above the previous published reading of 30.62%. That earlier figure appears in the DLD register without an inspection date attached, so the length of the interval behind the gain is not part of the record. The site report for the current reading is in the June 2026 construction update.
Across the 19.6 months between the 02 November 2024 construction start and the 22 June 2026 inspection, the project averaged about 2.5 percentage points per month. Reaching 100% by the DLD-registered completion date of 30 November 2028 requires about 1.7 points per month across the roughly 29 months that remain. Both figures are derived from the dated record rather than recorded phase velocities, because only one reading in this register carries a date. The workings are in the pace analysis above.
Project 3139 carries 30 November 2028 as its completion date in the DLD register, which falls inside the Q4 2028 handover window Emaar publishes for Parkland. At 50.02% on 22 June 2026 there were 49.98 points left to certify, and this page's record is updated as each further inspection is published.
DLD registration records show 209 residential units across a total built-up area of 23,252.54 sq m, divided into 95 one bedroom, 69 two bedroom and 45 three bedroom homes inside a single tower rather than a multi tower phase. Layouts and sizes are in the Parkland at Dubai Hills Estate project guide.
Project 3139 was registered with the Dubai Land Department on 12 July 2024 and construction started on 02 November 2024. By the 22 June 2026 inspection, enabling works, piling and foundation works were all recorded as completed.
The 22 June 2026 inspection notes record enabling works across plot 4944, piling and foundation works as completed, while structure works on the ground to twenty third floor tower, external envelope installation, MEP, internal works and internal finishes were all progressing at the same time. That parallel sequencing is what carried the project to 50.02% at the midpoint of its programme.
Instalments on the Parkland schedule are released at 20%, 40%, 50%, 70%, 80% and 100% construction completion, which puts certified readings behind the remaining payments alongside the calendar dates. The 22 June 2026 figure of 50.02% clears the third of those thresholds. How instalments reach the registered account is set out on the Parkland at Dubai Hills Estate escrow account page, and each individual sale and purchase agreement governs which trigger applies.
Parkland stands on plot 4944, where Dubai Hills Estate meets its park and retail spine: a five minute walk to Dubai Hills Business Park, eight minutes to Dubai Hills Mall and a five minute drive to King's College Hospital. Because that infrastructure is already open, the tower is completing into a finished district instead of waiting on one. The wider masterplan is covered in the Dubai Hills Estate community guide.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Parkland at Dubai Hills Estate construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.