Emaar Properties · Rashid Yachts & Marina
Pier Point 2 at Rashid Yachts & Marina Construction Updates
From Piling on Plot 513 to Handover on the Marina Front
Pier Point 2 recorded 8.48% construction progress at its 14 May 2026 RERA inspection, the first certified readings establishing how this marina front build starts.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Pier Point 2 at Rashid Yachts & Marina at a Glance
Pier Point 2 is Emaar Properties' 117 residence pair of buildings on the inner edge of the superyacht basin at Rashid Yachts & Marina, registered as ground plus one podium level, ten floors and roof. Just under fifteen months separate its 22 February 2025 construction start from the 8.48% recorded at the May 2026 inspection, and the figures below are the DLD registered anchors behind that record. Because plot 513 sits on marina frontage, the opening stretch of this record is ground work rather than anything visible above the hoarding, which is why the certified percentage is still counted in single digits.
3305
Active
22 February 2025
117 residential units
12,723.04 sq m
31 October 2028 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Pier Point 2 at Rashid Yachts & Marina Construction Update Timeline
Two certified readings exist for Pier Point 2 so far, and they sit 2.23 points apart: a previous reading of 6.25% and the 8.48% recorded on 14 May 2026. Both appear on the track below, close enough together that the earlier one carries no label of its own. The table holds the dated reading and links the full May 2026 update, where the inspection notes for mobilization, enabling and piling are published with the figure.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| May 2026 | 8.48% | 14 May 2026 | View the May 2026 update |
Pace Analysis
How Fast Pier Point 2 at Rashid Yachts & Marina Has Been Built
With one dated reading on the register, pace at Pier Point 2 is read two ways: against the construction start behind it, and against what the registered completion date still demands. Three measures frame the record:
- Feb 2025 to May 2026: mobilization, enabling and piling, 0% to 8.48%About 0.6 points per month
- Previous certified reading to 14 May 2026: 6.25% to 8.48%Plus 2.23 points
- May 2026 to the registered 31 October 2028 completion: 8.48% to 100%About 3.1 points per month needed
A shallow opening slope is what a piling programme produces, not a warning sign: the certified weighting attached to enabling works and bored piles is small next to the time they consume, so more than fourteen months of site activity converts into single figures on the register. What the arithmetic does say is that the curve has to steepen sharply. Holding the 31 October 2028 registered date means averaging roughly five times the pace recorded so far, and that jump is normally earned in one place, the moment the superstructure starts rising floor by floor above the podium. For an investor the useful test is therefore the next two or three readings rather than this one: if the substructure closes out and the first floor plates appear, the required 3.1 points per month becomes routine. For an end user planning around October 2028, the same readings are the early warning system, published here as each inspection lands.
Get the Next Inspection Figure First
Tell me you are tracking Pier Point 2 at Rashid Yachts & Marina and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Pier Point 2 at Rashid Yachts & Marina at Mina Rashid
A percentage only means something next to what it delivers. The full project guide covers the development this record is tracking:

Pier Point 2 at Rashid Yachts & Marina: Twin Promenade Towers
Pier Point 2 at Rashid Yachts & Marina sets 117 Emaar apartments and townhouses in two towers above a landscaped podium.
View the Pier Point 2 at Rashid Yachts & Marina Project GuideConsidering an Early Construction Entry?
Availability at Pier Point 2 keeps moving while the build runs, and the floor, orientation and outlook attached to what is left change faster than the headline price does. If this record is what brought you here, ask me what remains before the next certified reading lands.
Ask About Remaining Availability on WhatsAppStage Record
Pier Point 2 at Rashid Yachts & Marina Build Stages, Mapped to the Inspections
Rather than a generic construction sequence, each stage below is tied to the window it actually occupies in this project's register, so you can see where the 8.48% reading of 14 May 2026 sits in the programme.
Registration and Site Activation
Project 3305 was entered on the Dubai Land Department register on 25 September 2024 with its trust account held at Emirates NBD Bank (P.J.S.C), and construction was recorded as started on 22 February 2025.
Mobilization, Enabling and Piling
The inspection of 14 May 2026 found mobilization, enabling and piling works in progress on plot 513, certifying 8.48% and putting 2.23 points on the register since the previous reading of 6.25%.
Substructure and Podium
Pile caps, the parking podium and the ground plus one podium levels of the registered profile. This is the stage that ends the flat part of the curve on the track above.
Ten Floors of Superstructure
Floor plates and cores rising across both buildings to the roof level registered for the development, the phase where the 3.1 points per month the schedule needs is normally earned.
Facade, Fit-Out and Handover
Cladding, apartment finishing, podium landscaping and commissioning of the 117 residences, closing the distance between the last recorded reading and the October 2028 handover.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Pier Point 2 at Rashid Yachts & Marina's own record.
Buyer Position
Tracking Your Position at Pier Point 2 at Rashid Yachts & Marina
This page is one of four project resources that together cover a Pier Point 2 at Rashid Yachts & Marina purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Pier Point 2 at Rashid Yachts & Marina Construction Updates
This page: the certified inspection record for Pier Point 2, from the February 2025 construction start.

Pier Point 2 at Rashid Yachts & Marina Golden Visa: Ten Years
At Pier Point 2 at Rashid Yachts & Marina, 117 Emaar homes, the one bedroom sits below while three releases qualify.
Read the Pier Point 2 at Rashid Yachts & Marina Golden Visa Guide
Pier Point 2 at Rashid Yachts & Marina Escrow with Emirates NBD
Emirates NBD keeps Pier Point 2 at Rashid Yachts & Marina escrow, DLD project 3305, 121 units, 8.48% certified May 2026.
Verify the Pier Point 2 at Rashid Yachts & Marina Escrow AccountApproaching Handover
Between 8.48% and Handover: What Pier Point 2 at Rashid Yachts & Marina Buyers Should Do Now
At this reading the money still moves on dates and certified milestones rather than on keys, which makes this the window where the paperwork behind a Pier Point 2 purchase matters more than the building does. The June 2026 stage on the published schedule has already passed and the next dated stage falls in November 2026, so the three checks below belong in the gap between certified readings, not at handover.
First, confirm that every instalment reaches the DLD registered trust account for project 3305; the Pier Point 2 escrow account page sets out the bank on record and what releases money to the developer.
Second, read your own sale and purchase agreement against the certified record, because whether your November 2026 payment is triggered by the date or by a construction milestone is decided by that document rather than by the 8.48% reading itself.
Third, if the purchase may support residency, settle eligibility early through the Pier Point 2 Golden Visa eligibility guide, since the application path for an off plan unit years ahead of its title deed is not the same as for a completed home.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Mina Rashid Structure
A build record is only half the picture; the other half is what is rising around it. These three pages place the 8.48% reading in its marina, its masterplan and its developer context:

Mina Rashid Properties for Sale
Browse waterfront apartments for sale at Rashid Yachts & Marina, with projects, prices and payment plans.
See Mina Rashid Properties for Sale
Mina Rashid Community Overview
Read the Rashid Yachts & Marina guide: Emaar's transformation of historic Port Rashid into a marina lifestyle community.
Explore the Mina Rashid Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Pier Point 2 at Rashid Yachts & Marina Construction Updates Frequently Asked Questions
Pier Point 2 is an active DLD registered project (number 3305) in its enabling and piling phase, recorded at 8.48% at the RERA inspection of 14 May 2026, with the progress status logged as Main Contract - Progressing. The full record is in the inspection timeline above.
The inspection dated 14 May 2026 recorded 8.48% construction progress, 2.23 points above the previous certified reading of 6.25%, and its notes describe mobilization, enabling and piling works as ongoing. The full site report is in the Pier Point 2 May 2026 construction update.
Measured from the 22 February 2025 construction start to the inspection of 14 May 2026, the record averages about 0.6 percentage points per month, the shallow opening slope a piling and enabling programme produces. Closing the remaining 91.52 points by the registered completion date of 31 October 2028 works out at about 3.1 points per month. The workings are in the pace analysis above.
The DLD registered completion date for project 3305 is 31 October 2028, consistent with the October 2028 handover published for the project. At 8.48% recorded on 14 May 2026 the build sits in the early band of that programme, and this page's record is updated when each new inspection is recorded.
Pier Point 2 holds 117 residential units across one, two and three bedroom apartments plus three bedroom townhouses, in a development registered as ground plus one podium level, ten floors and roof on plot 513 at Madinat Dubai Almelaheyah.
Construction was recorded as started on 22 February 2025, five months after the project was registered with the Dubai Land Department on 25 September 2024. The first dated reading tracked on this page is the 8.48% certified on 14 May 2026.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Pier Point 2 at Rashid Yachts & Marina construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.