Porto View at Rashid Yachts & Marina by Emaar Properties in Rashid Yachts & Marina project rendering used for the June 2026 construction update showing the planned waterfront promenade with marina yachts and residential buildings in Dubai - Presented by Tohid Fetrat

Emaar Properties · Rashid Yachts & Marina · Construction Update

Porto View Construction Update - June 2026

DLD Register Records Porto View at 6.26% Construction Progress After the June 2026 Inspection

Enabling, piling and foundation works are progressing at Porto View, with the DLD register recording 6.26 percent construction progress at the 02 June 2026 inspection.

Direct advisor access. Every message answered personally, never by a call center.

6.26%Construction Progress
02 June 2026Inspection Date
31 October 2028Expected Completion
3306DLD Project Number

Verified DLD Inspection Data

Porto View Construction Snapshot

6.26% recorded on 02 June 2026 places Porto View in the earliest construction band, where groundworks are the whole of the site story and payment timing, not delivery timing, is the decision in front of a buyer.

Project Name

Porto View

Project Number

3306

Project Status

Active

Construction Progress

6.26%

Inspection Date

02 June 2026

Construction Start

22 February 2025

Total Units

115 units per the DLD register

Total Built Area

12,277.86 sq m

Expected Completion

31 October 2028

Data source: the DLD project register for project 3306, which carries the 6.26% figure, read alongside the independent progress monitoring report dated 02 June 2026. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: September 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Porto View Construction Progress Summary

The June 2026 cycle describes a site still working below ground. The independent monitoring report dated 02 June 2026 puts enabling, piling and foundation works in progress and the main contract as progressing, and the DLD register shows no remarks recorded against project 3306. The 6.26% in the register is what that stage measures to across the whole build.

Completed
  • Project registration in the DLD register on 23 September 2024
  • Escrow account opened for project 3306 with First Abu Dhabi Bank
  • Construction start recorded in the register on 22 February 2025
In Progress at 6.26%
  • Enabling works across the plot 516 site
  • Piling beneath the two buildings and their shared podium
  • Foundation works to the six floor and nine floor parts
  • Main contract recorded as progressing on 02 June 2026
Ahead of Handover
  • Remaining inspection cycles from 6.26% toward 100%
  • The construction percentages that trigger the 2026 and 2027 instalments
  • Handover from the registered completion date of 31 October 2028
Next inspectionThe 02 June 2026 report is the reading on record; the next figure appears in the DLD register for project 3306 after the following site visit.
Completion target31 October 2028 per the current DLD register, roughly twenty nine months from this inspection date.
Remaining distance93.74 percentage points separate the June 2026 reading from handover readiness.

Payment Linked Progress

What 6.26% Progress Means for Porto View Buyers

Porto View sells on a construction linked plan whose later instalments are called against certified build percentages rather than calendar dates alone, so a register reading of 6.26% on 02 June 2026 sets the context for every payment still ahead. Four actions matter most at this point in the build.

Before Your Next Instalment

Verify the escrow account

Every instalment ahead of handover belongs in the DLD regulated escrow account registered for project 3306. Porto View escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before the 2026 and 2027 Triggers

Map your SPA to the certified milestones

The published plan dates the fourth instalment to June 2026 upon 10% construction completion, and the register recorded 6.26% on 02 June 2026. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the certified milestones.

After Booking

Confirm your Oqood registration

At this stage an off plan purchase exists on the interim register rather than as a title deed, and the entry should name you, project 3306 and your unit. Ask for the record if you have not yet seen it.

Every Cycle

Track the remaining cycles

Several readings separate 6.26% from the construction percentages written into the plan. Porto View construction updates hub keeps each new figure and its inspection date in one place.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 6.26%?

Entering at the groundworks stage trades waiting time for payment runway: at 6.26% on 02 June 2026 most of the construction linked plan still lies ahead of the buyer rather than behind. Every payment goes to the DLD-registered escrow account for project 3306, released against certified construction progress.

Entering Now at 6.26%
  • Certified groundworks: the 02 June 2026 record is the risk picture
  • Roughly twenty nine months to the registered completion date
  • 20% of the price falls due only at 100% construction completion
Typical Launch Entry
  • Price agreed before any inspection record exists
  • Full construction risk carried from the first cheque
  • Longest instalment runway, at launch pricing
AED 1.93M ≈ USD 0.53MStarting Price
10 / 70 / 20 Plan20% Due on Completion
Q4 2028Expected Handover
Ask What Is Available at Porto View

4 units listed available on the project page as of this update; availability shifts between cycles.

About the Development

Porto View Project Details

Porto View at Rashid Yachts & Marina by Emaar marina with luxury yachts waterfront residences and Dubai skyline at sunset in Dubai - Presented by Tohid Fetrat
Rashid Yachts & Marina · Emaar Properties

With foundation works still underway, Porto View is an early stage waterfront development of two buildings joined by a landscaped podium, holding 114 residences on Emaar's own count. Starting prices: AED 1.93M ≈ USD 0.53M.

For a buyer entering here the trade off is the longest wait against the longest payment runway, with Emaar stating handover in Q4 2028 and the DLD register carrying 31 October 2028 as the expected completion date.

Porto View at Rashid Yachts & Marina Project Guide

Site Context This Cycle

Explore Porto View Location on Dubai Map

Porto View occupies plot 516 in Madinat Dubai Almelaheyah, the location recorded for project 3306, at the water's edge inside Mina Rashid. A waterfront plot is precisely why this cycle reads as enabling and piling rather than visible building: the load path for a six floor part and a nine floor part sharing one podium has to be carried into the ground before anything stands above it.

Rashid Yachts & Marina is being built out around a working cruise port and a marina of 430 wet berths, so the roads, promenade and berthing arrive alongside the residences rather than years before them. For a buyer reading 6.26% that has one practical consequence: the district and the building mature on similar timelines, which is a different proposition from finishing into a neighbourhood that is already complete. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Porto View at Rashid Yachts & Marina by Emaar on Dubai Map

Buyer Resources for This Project

Investing in Porto View During Early Construction Progress

The groundworks band is where payment protection, residency planning, and cycle tracking do the most work. Each resource below is matched to where Porto View stands right now.

Porto View at Rashid Yachts & Marina by Emaar Properties in Rashid Yachts & Marina construction updates cover image featuring a project rendering of waterfront residences beside a yacht marina and promenade in Dubai - Presented by Tohid Fetrat
You Are Here

Porto View Construction Updates

This page: the verified June 2026 inspection record for Porto View, from enabling works onward.

Porto View at Rashid Yachts & Marina by Emaar Properties in Rashid Yachts & Marina Golden Visa graphic with a gold visa card above a waterfront terrace overlooking yachts and residential buildings in Dubai - Presented by Tohid Fetrat

Porto View at Rashid Yachts & Marina Golden Visa: Three Marina Tiers

Emaar's Porto View at Rashid Yachts & Marina, 114 waterfront residences, qualifies at 2 and 3 bedroom apartments and townhouses.

Read Porto View Golden Visa Guide
Porto View at Rashid Yachts & Marina by Emaar Properties in Rashid Yachts & Marina escrow account graphic with shield and padlock icons above a marina promenade with residential buildings and yachts in Dubai - Presented by Tohid Fetrat

Porto View at Rashid Yachts & Marina: The Marina Escrow Record

Porto View at Rashid Yachts & Marina escrows 115 units at First Abu Dhabi Bank, project 3306, 6.26% certified June 2026.

Verify Porto View Escrow Account

Update Timeline

Other Porto View Construction Updates

June 2026 is the first published inspection reading for Porto View, so the timeline starts here and every following cycle is added to the same record.

All Porto View Construction Updates

FAQs

Porto View Construction Progress in June 2026: Frequently Asked Questions

The DLD project register records Porto View at 6.26% construction progress for project 3306, following the independent site inspection carried out on 02 June 2026.

Yes. Expected completion dates held in the DLD project register are revised between inspection cycles whenever the delivery schedule moves. The 31 October 2028 entry shown here is the register position as of June 2026, and Emaar states handover in Q4 2028; any revision would surface in a later reading on this cluster.

The independent progress monitoring report dated 02 June 2026 records that enabling, piling and foundation works are progressing. It describes the built form as a shared ground and podium level with one part rising to six floors plus roof and another part to nine floors plus roof, and reports nothing above foundation level at this reading. How each cycle is recorded for this project is covered on the Porto View construction updates hub.

The DLD register displays 5.82% as the previous inspection figure for project 3306, alongside the 6.26% current reading. The register does not date that earlier figure in the view published here, so it is reported without a month attached rather than assigned to a cycle it may not belong to.

The published Porto View plan dates the fourth instalment to June 2026 and marks it upon 10% construction completion, while the register recorded 6.26% on 02 June 2026. Construction linked instalments are called by the developer against certified progress under the terms of each individual sale and purchase agreement, so the schedule written into your own contract governs when that payment actually falls due.

No. The June 2026 monitoring report gives the progress status of the main contract as progressing, and the DLD register shows no remarks recorded for project 3306 at that date.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the June 2026 inspection record for Porto View at Rashid Yachts & Marina correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts