Portofino at DAMAC Lagoons Construction Updates

The Register Record of 867 Villas, From the April 2022 Start to Handover

Portofino at DAMAC Lagoons reached 97.14% on the DLD register on 16 July 2026, leaving envelope, services and external works to finish before the Q4 2026 handover.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

97.14%Construction Progress
16 July 2026Latest RERA Inspection
867 villasTotal Units
Project 2356DLD Registration

Construction Snapshot

Portofino at DAMAC Lagoons at a Glance

Portofino is DAMAC's cluster of 867 villas in DAMAC Lagoons, on Hessa Street across from DAMAC Hills and built in 3, 4, 5 and 7 bedroom layouts. Its register record runs from the 31 January 2022 registration and the 24 April 2022 construction start to a reading of 97.14% on 16 July 2026, a span of 1,544 days of building. Because the work is spread across hundreds of villas in rows rather than one structure, the last points on this register measure envelope, services and infrastructure across whole rows of homes, which is why the figure moves in small steps this close to 100%.

DLD Project Number

2356

Project Status

Active

Construction Start

24 April 2022

Total Units

867 villas

Total Built-Up Area

169,471.20 sq m

Registered Completion Date

29 June 2025 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Portofino at DAMAC Lagoons Construction Update Timeline

Portofino's dated record is short and arrives late in the build: the project entered the DLD register on 31 January 2022, construction started on 24 April 2022, and the first reading published here is the 97.14% of 16 July 2026. The register shows one earlier reading of 96.9% beside it without a date, so that figure sits on the track below as a dot but not as a table row, while the July 2026 row links the full monthly update.

Inspection MonthConstruction ProgressInspection DateFull Update
July 202697.14%16 July 2026View the July 2026 update
!

Reading the dates: the DLD-registered completion date for project 2356 is 29 June 2025, while the register reading of 16 July 2026, taken 382 days after that date, recorded 97.14%. The registered date is an administrative anchor held on the project record since registration on 31 January 2022; DAMAC's estimated handover for Portofino is Q4 2026, and actual handover is confirmed by DAMAC as the final works close.

Pace Analysis

How Fast Portofino at DAMAC Lagoons Has Been Built

With a single dated reading on file, Portofino's pace can only be read as arithmetic across the whole build rather than phase by phase. Two figures frame it, and neither is a forecast:

  • 24 Apr 2022 to 16 Jul 2026: whole-build average, start to 97.14% over 1,544 daysAbout 1.89 points per month
  • 16 Jul 2026 to 31 Dec 2026: arithmetic to 100% by the end of Q4 2026, 2.86 points over 168 daysAbout 0.51 points per month

Read together, the two numbers describe a build whose structural work the RERA report already lists as substantially completed. Averaged from the April 2022 start, Portofino's register gained about 1.89 points a month, and closing the remaining 2.86 points by the last day of Q4 2026 needs roughly a quarter of that rate. The register also shows only a 0.24 point difference between the undated 96.9% reading and the 16 July 2026 figure, which fits a cluster where the RERA report placed every open package, from envelope and MEP to finishes, infrastructure and external works, at very advanced stages: work of that kind moves the percentage in small increments across 867 villas. Both figures are arithmetic, not a forecast, and handover timing is set by DAMAC. For an end user, the useful signal is how close the record sits to 100%; for an investor, it is that the distance left is measured in finishing and external works across the villa rows, not in structure.

Get the Next Inspection Figure First

Tell me you are tracking Portofino at DAMAC Lagoons and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Portofino at DAMAC Lagoons

A register percentage means more once you know what it measures. At Portofino it measures 867 villas, and the project guide sets out what this record is building toward:

Portofino by DAMAC in DAMAC Lagoons project rendering of a modern villa with broad glazed façades, a swimming pool, a waterfall feature and landscaped gardens in Dubai - Presented by Tohid Fetrat

Portofino at DAMAC Lagoons: Italian Harbour-Village Villas

Portofino at DAMAC Lagoons is a DAMAC cluster of 867 villas with three to seven bedrooms, designed around an Italian theme.

View the Portofino at DAMAC Lagoons Project Guide

Considering a Near-Handover Entry?

At 97.14% on the register on 16 July 2026, entering Portofino now means a short wait for keys rather than a multi-year build. Availability across the four villa sizes keeps moving as handover approaches, so ask me what is open today before the remaining choice narrows further.

Ask About Remaining Availability on WhatsApp

Stage Record

Portofino at DAMAC Lagoons Build Stages, Mapped to the Inspections

Each stage below is pinned to Portofino's own dates: the January 2022 registration, the April 2022 start, and the RERA report and register reading of 16 July 2026, which together show which packages were substantially completed and which were still open at 97.14%.

Jan 2022 to Apr 2022

Registration and Site Activation

Portofino entered the DLD register on 31 January 2022, and construction started on 24 April 2022, the date every pace figure on this page counts from.

Apr 2022 to Jul 2026

Enabling Works and Foundations

The 16 July 2026 RERA report lists the enabling and foundation works under the cluster's villa rows as substantially completed.

Apr 2022 to Jul 2026

Villa Substructure and Superstructure

Concrete structure and blockwork for the G+1 and G+2 villas described in the RERA report, recorded as substantially completed by 16 July 2026.

Recorded on 16 Jul 2026

Internal Works and Building Services

Internal works were substantially completed at the 16 July 2026 inspection, while the MEP services were among the packages at very advanced stages.

Current Phase96.9% previous, 97.14% on 16 Jul 2026

Envelope, Finishes, External Works and Handover

External envelope, finishes, infrastructure and external works were at very advanced stages on 16 July 2026, ahead of DAMAC's estimated Q4 2026 handover.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Portofino at DAMAC Lagoons's own record.

Buyer Position

Tracking Your Position at Portofino at DAMAC Lagoons

This page is one of four project resources that together cover a Portofino at DAMAC Lagoons purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Portofino by DAMAC in DAMAC Lagoons construction updates cover image featuring a project rendering of a modern multi-storey villa with illuminated glazing, a front driveway and a construction updates graphic overlay in Dubai - Presented by Tohid Fetrat
You Are Here

Portofino at DAMAC Lagoons Construction Updates

This page: the DLD register record for Portofino's 867 villas, from the April 2022 start onward.

Portofino by DAMAC in DAMAC Lagoons Golden Visa concept graphic with a gold card marked Golden Visa above colorful attached homes, a road and landscaped planting in Dubai - Presented by Tohid Fetrat

Portofino at DAMAC Lagoons Golden Visa: 5 and 7 Bedroom Villas

Portofino at DAMAC Lagoons, 867 DAMAC villas, qualifies at the 5 and 7 bedroom types; 3 and 4 bedrooms do not.

Read the Portofino at DAMAC Lagoons Golden Visa Guide
Portofino by DAMAC in DAMAC Lagoons escrow account concept graphic showing a shield and padlock above a rendering of colorful attached homes, street parking and greenery in Dubai - Presented by Tohid Fetrat

Portofino at DAMAC Lagoons Escrow: An 867-Unit Account at 97%

Portofino at DAMAC Lagoons stood 97.14% certified July 2026; DLD project 2356 escrows 867 units at Emirates NBD.

Verify the Portofino at DAMAC Lagoons Escrow Account
Portofino by DAMAC in DAMAC Lagoons snagging inspection concept graphic overlay on a furnished living and dining room with full-height glazing, seating and pendant lights in Dubai - Presented by Tohid Fetrat

Portofino at DAMAC Lagoons Snagging for Italian-Themed Villas

Portofino at DAMAC Lagoons is DAMAC Properties' cluster of 867 villas, offered in 3, 4, 5 and 7 bedroom layouts.

Book Portofino at DAMAC Lagoons Snagging

Approaching Handover

Between 97.14% and Handover: What Portofino at DAMAC Lagoons Buyers Should Do Now

The 2.86 points still open after the 16 July 2026 reading are spread across facades and roofs, MEP systems, finishes, and the roads and landscaping that tie each villa row into the cluster, so most of what remains is easy to miss from the street but decisive on handover day. DAMAC's handover notice will set a fixed window for your completion payment and inspection appointment, which is why the three steps below belong before the Q4 2026 estimate rather than after the notice arrives.

First, line up an independent snagging inspection so defects across both main floors, and the roof level on 5 and 7 bedroom villas, are documented before you accept keys; the Portofino at DAMAC Lagoons snagging page explains timing and scope.

Second, check that any payment your SPA still requires lands in the Emirates NBD escrow account for project 2356, using the Portofino escrow account page to match it against progress recorded on the DLD register.

Third, if you bought a 5 or 7 bedroom villa with residency in mind, settle eligibility early through the Portofino at DAMAC Lagoons Golden Visa guide, since title deed timing shapes the application route.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore DAMAC Lagoons Structure

Portofino's register record is one cluster's story. These three pages set it beside the DAMAC Lagoons market, the master community and the developer building it:

DAMAC Lagoons properties for sale in Dubai including villas, townhouses and apartments within landscaped residential surroundings, Presented by Tohid Fetrat

DAMAC Lagoons: Mediterranean-Themed Villas, Townhouses, Apartments and Offices

DAMAC Lagoons sits opposite DAMAC Hills in Dubailand, with 11 themed clusters and 3 projects of villas, townhouses, apartments and offices.

See DAMAC Lagoons Properties for Sale
DAMAC Lagoons master community with crystal lagoon waterfront villas sandy beaches palm trees and leisure amenities in Dubai Presented by Tohid Fetrat

DAMAC Lagoons Community Overview

Read the DAMAC Lagoons guide: Mediterranean-themed clusters and crystal lagoons across a 45 million sq ft waterfront masterplan.

Explore the DAMAC Lagoons Community
DAMAC Properties development overlooking Dubai skyline and waterfront with modern architecture at sunset in Dubai Presented by Tohid Fetrat

DAMAC Properties: Lagoon Communities, Golf Villas and Branded Collaborations

Founded in 2002, DAMAC has delivered 48,000 homes and is known for large-scale master communities, luxury residential projects and branded collaborations.

View the DAMAC Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Portofino at DAMAC Lagoons Construction Updates Frequently Asked Questions

Portofino at DAMAC Lagoons is an active project on the DLD register under number 2356, recorded at 97.14% construction progress on 16 July 2026. The RERA report of that date lists the structural and internal works as substantially completed, with the envelope, MEP, finishes and external works at very advanced stages; every reading so far is laid out in the Portofino inspection timeline above.

Portofino moved from 96.9% to 97.14% on the DLD register, a difference of 0.24 points, with the newer figure dated 16 July 2026. The register shows no date for the 96.9% reading, so no monthly rate is drawn from that pair; the inspection detail sits in the July 2026 Portofino construction report.

29 June 2025 is the registered completion date held on the DLD record for project 2356, and it had passed 382 days before the 16 July 2026 reading of 97.14%. It is an administrative date recorded with the project rather than a handover announcement; DAMAC's estimated handover for Portofino is Q4 2026, and this page's record is updated when the closing reading is recorded.

Portofino has 867 villas, the count shown on the DLD register for project 2356, in 3, 4, 5 and 7 bedroom layouts that the RERA report of 16 July 2026 describes as G+1 and G+2 villas. Sizes, floor levels and prices for each layout are covered in the Portofino at DAMAC Lagoons villa guide.

Averaged across the build, Portofino gained about 1.89 points per month: 97.14 points over the 1,544 days from the 24 April 2022 start to the 16 July 2026 reading. Reaching 100% by the end of Q4 2026 works out to about 0.51 points per month on the remaining 2.86 points; both figures are arithmetic, not a forecast, and are set out in the Portofino pace analysis above.

Construction at Portofino started on 24 April 2022 according to the DLD register, 83 days after the project was registered on 31 January 2022. The first dated reading on this record is 97.14% on 16 July 2026, so the years between the start and that reading are marked by the register dates rather than by earlier published inspections.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Portofino at DAMAC Lagoons construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status