Ellington · Rashid Yachts & Marina · Construction Update

Portside Square Construction Update - January 2026

DLD Register Reads Portside Square at 0% for the January 2026 Inspection, Before Construction Start in Rashid Yachts & Marina

No construction activity had started on plot 488 when Portside Square was inspected on 12 January 2026, a visit the DLD register records as a 0% reading.

Direct advisor access. Every message answered personally, never by a call center.

0%DLD Register Reading
12 January 2026Inspection Date
Q4 2029Expected Completion
4213DLD Project Number

Verified DLD Inspection Data

Portside Square Construction Snapshot

A 0% reading with an untouched site places Portside Square at the very start of the enabling and foundations band, where what protects a buyer is the escrow account and the registration paperwork rather than anything visible on the plot.

Project Name

Portside Square by Ellington

Project Number

4213

Project Status

Active

Construction Progress

0%

Inspection Date

12 January 2026

Construction Start

01 September 2026

Total Units

413 units

Total Built Area

39,728.55 sq m

Expected Completion

31 December 2029

Data source: DLD Register Reading of 0% for the 12 January 2026 inspection of project 4213; the Independent Progress Monitoring Report itself prints the progress status as N/A. This was still the latest reading in the DLD project record checked in October 2026, which is also the source of the construction start date. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: October 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Portside Square Construction Progress Summary

The Independent Progress Monitoring Report dated 12 January 2026 states that no construction activity had started at site and leaves the RERA progress status as N/A; the 0% figure is the DLD Register Reading for that inspection. With no earlier reading to compare against, this cycle fixes the starting line from which every later Portside Square figure will be measured.

Completed
  • Independent RERA site inspection of plot 488 on 12 January 2026
  • Trust account bank on the record: Abu Dhabi Commercial Bank
  • Project scope logged as mixed use with ground level retail, office and restaurant space
In Progress at 0%
  • No construction activity recorded on site at the time of inspection
  • Plot shown as open, level sand in the inspection photograph
  • RERA progress status listed as N/A in the January 2026 report
Ahead of Handover
  • Enabling and foundation works for the shared ground and podium levels
  • Superstructure of three residential buildings, each 16 floors plus roof
  • G+P+2 amenities building and the ground level retail frontage
  • Completion scheduled for Q4 2029
Next inspectionPublished in the DLD project register after the next RERA site visit; the DLD record checked in October 2026 lists construction start as 01 September 2026.
Completion targetQ4 2029, close to four years beyond the 12 January 2026 inspection date.
Remaining distanceAll 100 percentage points remain; the first construction linked installment falls due at the 20% reading.

Payment Linked Progress

What 0% Progress Means for Portside Square Buyers

The Portside Square 70/30 plan front loads payments by date, not by progress: 50% of the price falls due within 360 days of reservation, while only four 5% installments follow the 20%, 30%, 40% and 50% construction readings. At a 0% reading, four actions matter most.

Before Every Transfer

Verify the escrow account

With half the price due on a calendar schedule before any structural milestone, each transfer should go only to the DLD regulated escrow account for project 4213, which the inspection record places with Abu Dhabi Commercial Bank. Portside Square escrow account verification sets out the check; the lookup itself takes about two minutes against the official DLD project record.

Within the First 360 Days

Reread your SPA payment schedule

Confirm how your sale and purchase agreement dates the 60, 120, 240 and 360 day installments, and which inspection reading triggers the first construction linked 5%. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the DLD register readings.

After the Booking Payment

Confirm your Oqood registration

Off plan purchases are recorded with the DLD through Oqood registration, typically once the 20% booking installment and the 4% DLD registration fee are settled. Ask for the Oqood registration record and check that it names project 4213 and your exact unit.

Every Cycle

Track the readings toward 20%

The first construction linked installment is due at the 20% reading, so each new inspection shows how close that payment is. Portside Square construction updates hub logs every reading as it publishes.

General framework, not legal advice: installment dates, Oqood timing, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 0%?

Entering before construction begins gives the longest runway to Q4 2029 at current list prices, in exchange for carrying the full build period from the first excavation. Every payment goes to the DLD-registered escrow account for project 4213, released against construction progress as recorded in the DLD register.

Entering Now at 0%
  • Site status documented: the 12 January 2026 inspection recorded no construction activity
  • 50% of the price due within 360 days of reservation under the 70/30 plan
  • 30% due on completion, scheduled for Q4 2029
Typical Launch Entry
  • Purchase often made before any independent inspection report exists
  • The whole construction period, usually several years, still ahead
  • Installment terms fixed at release, before site progress can be checked
AED 1.22M ≈ USD 331KStarting Price
70/30 Plan30% Due on Completion
Q4 2029Expected Handover
Ask What Is Available at Portside Square

13 units listed available on the project page as of this update; availability shifts between cycles.

About the Development

Portside Square Project Details

Portside Square by Ellington in Rashid Yachts & Marina aerial waterfront view of the Dubai skyline, port and surrounding city at dusk in Dubai - Presented by Tohid Fetrat
Rashid Yachts & Marina · Ellington

At the January 2026 inspection Portside Square was still a bare plot, with 408 residences from studios to 4 bedroom penthouses planned across three 16 floor buildings above a shared podium. Starting prices: AED 1.22M ≈ USD 331K.

For buyers entering at this stage, the trade off is the longest wait and the most installments still ahead, in return for an entry made before any structure exists, with handover scheduled for Q4 2029.

Portside Square by Ellington Project Guide

Site Context This Cycle

Explore Portside Square Location on Dubai Map

Portside Square is registered on plot 488 in Madinat Dubai Almelaheyah, the official DLD area name for Mina Rashid, inside Rashid Yachts & Marina between Marina View and Marina Cubes Street. The January 2026 inspection photograph shows that plot as open, level sand with no equipment on it, so the first real works this project records will be enabling and foundations for the shared ground and podium levels.

Because the marina, the Queen Elizabeth 2 and the Mina Rashid cruise terminal already operate around it, Portside Square is starting from zero inside a functioning waterfront district rather than an empty one; at this baseline, buyers can judge the setting as it stands today while the building itself only becomes measurable in later readings. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Portside Square by Ellington on Dubai Map

Buyer Resources for This Project

Investing in Portside Square Before Construction Begins

The enabling and foundations band is when payment protection and residency planning need settling, because half the price is paid before the first construction milestone. Each resource below matches where Portside Square stands at 0%.

Portside Square by Ellington in Rashid Yachts & Marina construction updates cover image featuring a project rendering of contemporary towers and surrounding buildings in Dubai - Presented by Tohid Fetrat
You Are Here

Portside Square Construction Updates

This page: the 12 January 2026 baseline inspection for Portside Square, recorded before any site works.

Portside Square by Ellington in Rashid Yachts & Marina Golden Visa concept graphic with a gold card over a project rendering of landscaped residential towers in Dubai - Presented by Tohid Fetrat

Portside Square Golden Visa: Four of Five Layouts Qualify, Studios Do Not

Portside Square at Mina Rashid qualifies from the 1 bedroom tier upward; only its studios start below the Golden Visa threshold.

Read Portside Square Golden Visa Guide
Portside Square by Ellington in Rashid Yachts & Marina escrow account concept graphic with shield and padlock symbols beside a rendering of residential buildings in Dubai - Presented by Tohid Fetrat

Portside Square Escrow: Abu Dhabi Commercial Bank Trust Account, Plot 488

Portside Square's trust account at Abu Dhabi Commercial Bank, opened for DLD project 4213, holds payments on 413 registered units.

Verify Portside Square Escrow Account

Update Timeline

Other Portside Square Construction Updates

January 2026 opens the Portside Square inspection record; each later reading joins this timeline as its RERA cycle publishes.

All Portside Square Construction Updates

FAQs

Portside Square Construction Progress in January 2026: Frequently Asked Questions

For the inspection of 12 January 2026, Portside Square (DLD project 4213) stands at 0% construction progress as a DLD Register Reading: the inspection report itself lists its progress status as N/A, and its notes record that no construction activity had started on site. No earlier inspection reading is published in this update series, so January 2026 serves as the baseline for every later comparison.

As of this January 2026 update, Portside Square is scheduled for completion in Q4 2029, close to four years after the 12 January 2026 inspection. Completion dates in the DLD project register can be revised between inspection cycles, and a project starting from a 0% baseline has the longest stretch in which a revision could occur; any change would be reported plainly in a later monthly update. How completion dates are recorded and revised is covered on the Portside Square construction updates hub.

The independent report dated 12 January 2026 found no construction activity at site, so there was no completed work to score and the RERA progress indicator was left as N/A. The DLD project register shows the same 12 January 2026 inspection as a 0% reading for project 4213, and that DLD Register Reading is the figure used on this page.

The inspection photograph in the 12 January 2026 report shows plot 488 as open, level sand with no structures or construction equipment on it, and existing buildings of the surrounding district in the background. The same report describes the planned scope as three residential buildings over a shared ground and podium level, each rising 16 floors plus roof, and a G+P+2 amenities building, with retail, office and restaurant space at ground level.

Under the 70/30 payment plan, 20% is paid at booking together with the 4% DLD registration fee, followed by 10% at 60 days, 10% at 120 days, 5% at 240 days and 5% at 360 days after the reservation date, all fixed by date rather than by site progress. The first construction linked installment, 5%, is due on completion of 20% construction, so from the 0% reading of January 2026, 50% of the price is scheduled on dates that do not depend on the build; the exact dates in your own SPA govern.

The DLD project record, checked in October 2026, lists 01 September 2026 as the construction start date for project 4213, which is after the 12 January 2026 inspection that found the site untouched. Progress from that start will show up in the next published inspection reading, not in this January 2026 baseline.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the January 2026 inspection record for Portside Square correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts