Portside Square by Ellington in Rashid Yachts & Marina construction updates cover image featuring a project rendering of contemporary towers and surrounding buildings in Dubai - Presented by Tohid Fetrat

Ellington · Rashid Yachts & Marina

Portside Square Construction Updates

Three Marina Towers on Plot 488, Tracked From the January 2026 Baseline at Mina Rashid

Portside Square shows 0% in the DLD register for its 12 January 2026 inspection, a bare-plot baseline that every later reading of its three towers starts from.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

0%Construction Progress
12 January 2026Latest RERA Inspection
413 unitsTotal Units
Project 4213DLD Registration

Construction Snapshot

Portside Square at a Glance

Portside Square is Ellington's 408-residence development on plot 488 at Rashid Yachts & Marina, registered with DLD as project 4213 and shown at 0% in the DLD register for the 12 January 2026 inspection, the only reading on file. The cards below are the registration anchors for a scope of three 16-floor residential towers over a shared podium, a separate amenities building, and a ground-level retail frontage.

DLD Project Number

4213

Project Status

Active

Construction Start

01 September 2026

Total Units

413 units

Total Built-Up Area

39,728.55 sq m

Registered Completion Date

31 December 2029 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Portside Square Construction Update Timeline

One inspection makes up the Portside Square record so far: the 12 January 2026 RERA visit to plot 488, which found no works under way, left the report's progress indicator at N/A, and appears as 0% in the DLD app. The single dot below marks that baseline at the far left of the track, and the table row links the January 2026 update; every later reading for project 4213 joins both as it publishes.

Inspection MonthConstruction ProgressInspection DateFull Update
January 20260%12 January 2026View the January 2026 update

Pace Analysis

How Fast Portside Square Has Been Built

One reading cannot show a measured pace, so no rate has been recorded for Portside Square yet. What the dates on file allow is plain arithmetic: spreading 0% to 100% evenly from each start point to the end of the Q4 2029 handover quarter gives the averages below, which are arithmetic, not a forecast:

  • 12 January 2026 reading (0%) to end of Q4 2029: 1,449 daysAbout 2.1 points per 30 days, arithmetic
  • 01 September 2026 register start to end of Q4 2029: 1,217 daysAbout 2.5 points per 30 days, arithmetic

Neither figure is a measured pace or a forecast, and neither implies a delay or an early delivery: each simply divides 100 points by the days between dates already in the project 4213 file. A measured pace needs two dated readings, so the first one appears here only after a second RERA reading publishes and can be set against the 12 January 2026 baseline. For an end user, the arithmetic is a yardstick for reading later figures against Q4 2029; for an investor, the reading to watch first is 20%, the threshold that triggers the first construction-linked 5% installment under the 70/30 plan.

Get the Next Inspection Figure First

Tell me you are tracking Portside Square and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Portside Square at Mina Rashid

A 0% reading from 12 January 2026 says little until it is set against what plot 488 is meant to become. The full project guide covers the residences and terms this record is tracking toward:

Portside Square by Ellington in Rashid Yachts & Marina aerial waterfront view of the Dubai skyline, port and surrounding city at dusk in Dubai - Presented by Tohid Fetrat

Portside Square: Three Curved Towers at Rashid Yachts & Marina

Portside Square is Ellington's first address at Mina Rashid: 408 homes around a shared amenity pavilion, with shops and restaurants.

View the Portside Square Project Guide

Considering an Entry Before Construction?

Availability at Portside Square shifts as each release sells through, and entering while the record stands at its 0% baseline of 12 January 2026 means carrying the full build period to Q4 2029. If the baseline on this page is what brought you here, ask me for current availability before the remaining inventory narrows.

Ask About Remaining Availability on WhatsApp

Stage Record

Portside Square Build Stages, Mapped to the Inspections

Only the first of these five stages has a reading behind it so far, the 0% baseline of 12 January 2026. The other four are anchored to the 01 September 2026 register start date, the 20% to 50% payment thresholds, and the Q4 2029 handover already on file for project 4213, so each window will be confirmed or corrected as Portside Square inspections publish.

Current PhaseJan 2026, 0% at last reading

Baseline Inspection on an Open Plot

The 12 January 2026 inspection found plot 488 with no works under way, its report leaving the RERA progress status at N/A, shown as 0% by DLD.

From the 01 Sep 2026 register start date

Enabling Works and Shared Podium

Site enabling, foundations, and the shared ground and podium level beneath all three towers, counted from the 01 September 2026 register start date; no reading yet.

Toward the 20% to 50% readings

Three-Tower Structure

Floor plates for Portside Residences I, II and III, each 16 floors plus roof, rise here, the window in which 5% installments fall due at 20%, 30%, 40% and 50%.

Beyond 50%, ahead

Facades, Amenities Building, and Retail Frontage

The curved tower facades, the G+P+2 amenities building, and the ground-level retail, office, and restaurant space follow the structural phase.

Toward Q4 2029 handover

Finishing, Commissioning, and Handover

Apartment finishing and building systems commissioning toward the Q4 2029 handover, when the final 30% of the 70/30 plan falls due on completion.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Portside Square's own record.

Buyer Position

Tracking Your Position at Portside Square

This page is one of four project resources that together cover a Portside Square purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Portside Square by Ellington in Rashid Yachts & Marina construction updates cover image featuring a project rendering of contemporary towers and surrounding buildings in Dubai - Presented by Tohid Fetrat
You Are Here

Portside Square Construction Updates

This page: Portside Square's inspection record for project 4213, from its January 2026 baseline to handover.

Portside Square by Ellington in Rashid Yachts & Marina Golden Visa concept graphic with a gold card over a project rendering of landscaped residential towers in Dubai - Presented by Tohid Fetrat

Portside Square Golden Visa: Four of Five Layouts Qualify, Studios Do Not

Portside Square at Mina Rashid qualifies from the 1 bedroom tier upward; only its studios start below the Golden Visa threshold.

Read the Portside Square Golden Visa Guide
Portside Square by Ellington in Rashid Yachts & Marina escrow account concept graphic with shield and padlock symbols beside a rendering of residential buildings in Dubai - Presented by Tohid Fetrat

Portside Square Escrow: Abu Dhabi Commercial Bank Trust Account, Plot 488

Portside Square's trust account at Abu Dhabi Commercial Bank, opened for DLD project 4213, holds payments on 413 registered units.

Verify the Portside Square Escrow Account

Approaching Handover

Between 0% and Handover: What Portside Square Buyers Should Do Now

From the 0% baseline of 12 January 2026, the next Portside Square readings are set to cover enabling works and the shared podium, while the payment schedule keeps its own calendar. Under the 70/30 plan, half the price is scheduled by calendar within the first 360 days after reservation, ahead of the first construction-linked 5% at the 20% reading, so the three steps below matter now rather than once the towers are visible.

First, check every date-fixed installment against the escrow account registered for project 4213 with Abu Dhabi Commercial Bank; the Portside Square escrow verification page shows how to confirm it before you transfer.

Second, follow the record toward the 20% reading that triggers the first construction-linked installment; the January 2026 Portside Square baseline report holds the inspection detail every later reading will be compared against.

Third, if your unit is a 1 bedroom or larger, priced from AED 2.44M ≈ USD 664K, check how the purchase fits a 10-year residency application through the Portside Square residency eligibility guide while the date-fixed payments are still running.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Mina Rashid Structure

A record that opened at 0% on 12 January 2026 reads more clearly beside what already stands around plot 488. These three pages place Portside Square's progress in its marina, community, and developer context:

Waterfront apartment buildings with modern architecture overlooking a marina filled with luxury yachts at Rashid Yachts and Marina by Emaar in Dubai Presented by Tohid Fetrat

Mina Rashid Properties for Sale

Browse waterfront apartments for sale at Rashid Yachts & Marina, with projects, prices and payment plans.

See Mina Rashid Properties for Sale
Luxury yachts at Rashid Yachts and Marina waterfront community with modern residences and marina promenade in Mina Rashid Dubai Presented by Tohid Fetrat

Mina Rashid Community Overview

Read the Rashid Yachts & Marina guide: Emaar's transformation of historic Port Rashid into a marina lifestyle community.

Explore the Mina Rashid Community
Exterior view of Ocean House by Ellington featuring sculptural architecture, curved balconies, lush landscaping, and luxury waterfront residences in Dubai. Presented by Tohid Fetrat.

Ellington Properties: Design-Led Boutique Residences With Curated Interiors

Ellington Properties, founded in 2014, is a design-led developer of apartments, villas and waterfront homes, with 30 developments launched and delivered.

View the Ellington Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Portside Square Construction Updates Frequently Asked Questions

Portside Square is an active DLD-registered project (number 4213) at its pre-construction baseline, shown at 0% in the DLD register for the inspection of 12 January 2026, when no works had begun on plot 488. The full record is in the inspection timeline above.

The 12 January 2026 inspection found no construction activity on site: its report leaves the RERA progress status at N/A, and the DLD register shows the same visit as 0%. It is the first reading in the Portside Square record, so there is no earlier figure to measure a point change against. Site detail is in the Portside Square January 2026 construction update.

Portside Square is scheduled for handover in Q4 2029, close to four years after the 0% DLD register reading of 12 January 2026. As arithmetic, not a forecast, moving from 0% to 100% across the 1,217 days between the 01 September 2026 register start date and the end of Q4 2029 averages about 2.5 percentage points per 30 days. This page's record is updated as each inspection is recorded.

Portside Square includes 408 residential units across three towers, Portside Residences I, II and III, ranging from studios to 4 bedroom penthouses. All three rise 16 floors plus roof over one shared podium on plot 488, registered as DLD project 4213.

The DLD project record, as shown in October 2026, lists 01 September 2026 as the start date for Portside Square (project 4213). The only tracked inspection is dated 12 January 2026 and is shown at 0% in the DLD register with no site activity; no inspection reading dated after 01 September 2026 has been published, so physical works are not yet shown on this record.

Nothing had been built at Portside Square as of the 12 January 2026 inspection, which found no works under way and is shown at 0% in the DLD register. The scope listed on that report is three residential buildings of 16 floors plus roof over a shared ground and podium level, a G+P+2 amenities building, and ground-level retail, office, and restaurant space, all still ahead of the first progress reading.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Portside Square construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status