RAW District 2 by Imtiaz Developments in Downtown Jebel Ali project rendering used for the July 2026 construction update showing the planned mixed use buildings beside a road at dusk in Dubai - Presented by Tohid Fetrat

Imtiaz Developments · Downtown Jebel Ali · Construction Update

RAW District 2 Construction Update - July 2026

July 2026 Inspection Records RAW District 2 at 0% Before Construction Starts in Downtown Jebel Ali

No construction activities had started when RERA inspected the RAW District 2 site on 08 July 2026, so this first DLD reading of 0% sets the baseline.

Direct advisor access. Every message answered personally, never by a call center.

0%DLD Register Reading
08 July 2026Inspection Date
Q2 2029Expected Handover
4526DLD Project Number

Verified DLD Inspection Data

RAW District 2 Construction Snapshot

A first reading of 0% on 08 July 2026 puts RAW District 2 at the opening line of the earliest stage band, ahead of enabling and foundation works, the point where buyers are weighing a payment schedule and a developer rather than a structure.

Project Name

RAW District 2 by Imtiaz

Project Number

4526

Project Status

Active

Construction Progress

0%

Inspection Date

08 July 2026

Construction Start

01 December 2026

Total Units

770 units

Total Built Area

56,998.22 sq m

Expected Completion

Q2 2029

Data source: DLD project register reading of 0% for project 4526, inspection dated 08 July 2026, together with the RERA Independent Progress Monitoring Report of the same date, which records that no construction activities had been started and a Progress Status of N/A. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Images on this page are developer renderings of the planned buildings, not site photographs. Last updated: October 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

RAW District 2 Construction Progress Summary

This is the first reading on record for RAW District 2, so there is no earlier inspection to compare against and no measured pace. The RERA monitoring report dated 08 July 2026 found no construction activities started and gives a Progress Status of N/A; the DLD register then lists the project as registered on 24 July 2026, with a registered construction start date of 01 December 2026.

Completed
  • Baseline RERA inspection of the site on 08 July 2026
  • DLD project registration under number 4526 on 24 July 2026
  • Trust account bank on record: Dubai Islamic Bank (DIB)
In Progress at 0%
  • No construction activities started at the 08 July 2026 inspection
  • RERA Progress Status recorded as N/A
  • Pre-construction period ahead of the 01 December 2026 registered start
Ahead of Handover
  • Works from the registered construction start date of 01 December 2026
  • Three basements, ground, five podium levels, 16 floors and roof (3B + G + 5P + 16 + R)
  • A residential tower and an office tower over a shared podium with ground-floor retail, 770 units in all
  • Handover expected in Q2 2029
Next inspectionNo date is set in the record; a newer reading appears in the DLD project register after the next RERA site visit, and a new monthly update follows when it does.
Completion targetHandover expected in Q2 2029 per the developer, earlier than the registered completion date of 01 December 2029 listed in the DLD register; confirm the date that applies in your SPA.
Remaining distance100 percentage points from the 0% baseline. Labelled arithmetic, not a forecast: the 1,096 days from the registered start of 01 December 2026 to the registered completion date of 01 December 2029 would need about 2.74 points per 30-day month. No whole-build average exists yet because works have not begun.

Payment Linked Progress

What 0% Progress Means for RAW District 2 Buyers

Both published RAW District 2 payment plans take 20% at booking, and the first dated instalment, 5% on 15 November 2026, falls before the registered construction start of 01 December 2026. With the register at 0%, those early payments are made before works begin, so four checks come first.

Before the First Instalment

Verify the escrow account

Every instalment should go only to the DLD regulated escrow account registered for project 4526; the RERA report of 08 July 2026 names Dubai Islamic Bank as the trust account bank. RAW District 2 escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before You Sign

Reread your SPA milestone schedule

Check how your sale and purchase agreement dates each instalment from 15 November 2026 onward, how it defines the completion payment, and which handover date it records against Q2 2029. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

After Booking

Confirm your Oqood registration

An off plan unit at RAW District 2 is registered with the Dubai Land Department through Oqood after the SPA is signed and the 4% DLD registration fee is paid. Check that the Oqood record names your unit and your details exactly; your SPA and the developer set the timing.

Every Cycle

Watch for the first reading above zero

With works registered to start on 01 December 2026, the next meaningful change is the first reading above the 0% baseline. RAW District 2 construction updates hub records each new reading as it is published.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 0%?

Entering before construction starts trades the longest wait for the longest payment runway: launch release pricing, 20% at booking, and instalments spread through the build to Q2 2029, or beyond it on the post-handover plan. Every instalment goes to the DLD-registered escrow account for project 4526, released against construction progress as RERA inspections record it.

Entering Now at 0%
  • Baseline DLD register reading of 0% on 08 July 2026, before works start
  • 20% plus the 4% DLD registration fee at booking on either plan
  • Option to pay 40% over three years after handover on the 60/40 plan
Typical Late Stage Entry
  • Structure visible on site before you commit
  • Shorter wait, with less of the payment plan left to spread
  • Pricing from a later release rather than the launch
AED 666K ≈ USD 181KStarting Price
50/50 or 60/40Post-Handover Option
Q2 2029Expected Handover
Ask What Is Available at RAW District 2

20+ Units Available on the project page as of this update; availability shifts between cycles.

About the Development

RAW District 2 Project Details

RAW District 2 by Imtiaz Developments in Downtown Jebel Ali mixed use towers with illuminated podium frontage and a street view at sunset in Dubai - Presented by Tohid Fetrat
Downtown Jebel Ali · Imtiaz Developments

With no works started at the 08 July 2026 inspection, RAW District 2 is a pre-construction launch of 770 units: furnished studios to 3 bedroom apartments in one tower, offices in the other, and podium retail on Sheikh Zayed Road. Starting prices: AED 666K ≈ USD 181K.

Buying at this stage trades the longest wait to the Q2 2029 handover for launch release pricing and the full span of either payment plan, with every date and obligation fixed in your SPA.

RAW District 2 by Imtiaz Project Guide

Site Context This Cycle

Explore RAW District 2 Location on Dubai Map

RAW District 2 sits on Sheikh Zayed Road in Downtown Jebel Ali, fronted by the 80,000 sq ft Flame Tree Park with a Dubai Metro station on its far side. No construction activity had started on the site at the 08 July 2026 inspection, and with three basement levels in the configuration, below-ground works have to come before anything rises above ground level.

Around the site, the metro link across the park and the first RAW District a short walk away are already part of the setting, so buyers at the 0% baseline are committing to an address whose transport is in place while the building itself has yet to begin. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view RAW District 2 by Imtiaz on Dubai Map

Buyer Resources for This Project

Investing in RAW District 2 Before Construction Starts

Before works begin, the questions that matter most are residency eligibility and where your instalments are held. Each resource below is matched to where RAW District 2 stands at its 0% baseline.

RAW District 2 by Imtiaz Developments in Downtown Jebel Ali construction updates cover image featuring a project rendering of the mixed use buildings with landscaped surroundings in Dubai - Presented by Tohid Fetrat
You Are Here

RAW District 2 Construction Updates

This page: the 08 July 2026 baseline reading for RAW District 2, recorded before works began.

RAW District 2 by Imtiaz Developments in Downtown Jebel Ali Golden Visa concept graphic with a gold card beside a project rendering of the mixed use buildings in Dubai - Presented by Tohid Fetrat

RAW District 2 Golden Visa: Six Tiers, One Above the Line

RAW District 2, Imtiaz's 770-unit mixed-use building, has only retail above the threshold; apartments and offices sit below.

Read RAW District 2 Golden Visa Guide
RAW District 2 by Imtiaz Developments in Downtown Jebel Ali escrow account protection concept with shield and padlock icons above a project rendering of the mixed use buildings in Dubai - Presented by Tohid Fetrat

RAW District 2 Escrow, a Dubai Islamic Bank Account in Jebel Ali

RAW District 2 holds 770 units' escrow at Dubai Islamic Bank, DLD project 4526, 0% certified July 2026.

Verify RAW District 2 Escrow Account

Update Timeline

Other RAW District 2 Construction Updates

The RAW District 2 inspection record begins with this July 2026 reading; each later reading joins the timeline on the construction updates hub as it is published.

All RAW District 2 Construction Updates

FAQs

RAW District 2 Construction Progress in July 2026: Frequently Asked Questions

RAW District 2 stands at 0% in the Dubai Land Department project register for project 4526, from the inspection dated 08 July 2026. It is the first and only reading on record for this update, so there is no earlier figure to compare it with. The RERA monitoring report of the same date prints no percentage: it records a Progress Status of N/A.

Because RAW District 2 is being sold off plan before works begin. When the site was inspected on 08 July 2026 no construction activity had started, and the registered construction start date in the DLD record is 01 December 2026, so the 0% figure is the starting baseline for the project rather than a measure of slow work.

The Independent Progress Monitoring Report dated 08 July 2026 states: "At time of inspection found: no construction activities have been started". The same report describes the project as a mixed-use building of three basements, ground, five podium levels, 16 floors and roof for residential, office and retail use, lists Dubai Islamic Bank as the trust account bank, and gives a Progress Status of N/A.

The DLD record lists the 0% inspection on 08 July 2026, project registration on 24 July 2026 and a registered construction start date of 01 December 2026. The July 2026 reading therefore comes before both the registration and the start date, and it serves as the baseline that every later RAW District 2 reading will be measured against.

No. A 0% reading taken before the registered construction start does not move any date: the developer's published handover remains Q2 2029, and the DLD register lists a registered completion date of 01 December 2029. Either date can be revised in later cycles, and your SPA records the date that applies to your unit. How readings are tracked through to handover is explained on the RAW District 2 construction updates hub.

No date for the next inspection appears in the record, and no reading later than 08 July 2026 is on file for this update. A new reading is added to the DLD project register after each RERA site visit, and readings above 0% depend on works starting, which the register dates to 01 December 2026.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the July 2026 inspection record for RAW District 2 correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts