Ellington · Meydan Horizon · Construction Update
Riverton House Construction Update - December 2025
December 2025 Inspection Set the Riverton House Baseline at 0% in Meydan Horizon
Three weeks after its recorded start date, Riverton House had its first RERA inspection on 22 December 2025: no construction activities on site, 0% on the register.
Direct advisor access. Every message answered personally, never by a call center.
Verified DLD Inspection Data
Riverton House Construction Snapshot
A first reading of 0% on 22 December 2025 placed Riverton House at the very start of the earliest stage band, before any of the 70/30 plan's construction-linked instalments could fall due; every later reading is measured from this baseline.
Riverton House by Ellington
4036
Active
0%
22 December 2025
01 December 2025
151 units
14,230.19 sq m
Q4 2027
Data source: RERA Independent Progress Monitoring Report for the inspection of 22 December 2025 (project 4036, plot 182, Bukadra; registered developer RIVERTON HOUSE DEVELOPMENT L.L.C; trust account bank Commercial Bank of Dubai (PSC)), read with the DLD project register, which supplies the 0% figure; the RERA report itself prints no percentage. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. This reading was more than ten months old by October 2026: re-verify project 4036 on Dubai REST for any newer reading before relying on it. The header image is a dated developer rendering of the planned building, not a photograph of the site. Last updated: December 2025.
Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp
This Inspection Cycle
Riverton House Construction Progress Summary
As the first entry in the Riverton House record, the 22 December 2025 inspection had no earlier reading to compare against. RERA's report described a residential and commercial building of B+G+4P+19F+R, showed its progress status as N/A, and noted no construction activities on site at the time of the visit, while the DLD register entered 0% as the opening figure.
- DLD project 4036, Riverton House, status Active
- Construction start date in the register: 01 December 2025
- Registration date in the register: 02 July 2026
- Trust account bank: Commercial Bank of Dubai (PSC)
- No construction activities on site at the time of inspection, per the RERA note
- RERA progress status shown as N/A
- DLD register reading of 0%, the first on record
- Inspection photographs held in the RERA report
- The full B+G+4P+19F+R building described by RERA
- 149 residences in 1, 2 and 3 bedroom layouts
- Four construction-linked instalments, at 20%, 30%, 40% and 50% construction
- Expected handover in Q4 2027
Payment Linked Progress
What 0% Progress Means for Riverton House Buyers
Riverton House runs on a 70/30 plan in which four 5% instalments are tied to construction stages, at 20%, 30%, 40% and 50% construction, while the others follow each buyer's reservation date or completion. At the 0% reading of 22 December 2025, none of those four construction-linked instalments had been triggered, and at this earliest stage four actions matter most.
Verify the escrow account
Each construction-period payment should reach only the DLD regulated escrow account registered for project 4036 with Commercial Bank of Dubai. Riverton House escrow account verification comes before the booking transfer; the lookup itself takes about two minutes against the official DLD project record.
Map your SPA schedule
Your sale and purchase agreement dates the 60, 120, 180, 240 and 360 day instalments from your own reservation date, so their timing differs from buyer to buyer, while the four construction-linked instalments wait for the 20% to 50% stages. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.
Confirm your Oqood registration
Oqood is the Dubai Land Department's register of off-plan sales, and your unit's entry there is the record that ties your purchase to this inspection history. Ask the developer for your Oqood confirmation after booking and check that the project number on it reads 4036.
Track the next readings
With a single 0% entry on record, each new DLD reading shows how close the 20% stage, and the first construction-linked instalment with it, has come. The Riverton House construction updates hub holds the dated record as it grows; confirm the current construction timetable with the developer in writing.
General framework, not legal advice: instalment triggers, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.
Buying at 0%?
Entering a project at its first reading trades certainty for runway: the 22 December 2025 record showed no construction activity on site, and in exchange the whole 70/30 schedule, all four construction-linked instalments included, still lay ahead. Every payment goes to the DLD-registered escrow account for project 4036, released against recorded construction progress.
- Recorded start 01 December 2025; first reading 0% on 22 December 2025
- About two years from the reading to the Q4 2027 expected handover
- No construction-linked instalment triggered at the reading
- Visible building progress on record before the first payment
- A shorter wait between signing and handover
- Less of the instalment runway left, more due near completion
Limited Units Available, as listed on the project page at the time of writing; availability shifts between cycles.
About the Development
Riverton House Project Details

At the 22 December 2025 inspection, Riverton House had a recorded construction start and no construction activities on site: a planned B+G+4P+19F+R tower of 149 residences in 1, 2 and 3 bedroom apartments, sold on a 70/30 plan. Starting prices: AED 2.01M ≈ USD 546K.
A buyer joining at the first reading accepts the longest wait for the keys in return for the fullest payment runway, with handover expected in Q4 2027.
Riverton House by Ellington Project GuideSite Context This Cycle
Explore Riverton House Location on Dubai Map
Ellington's plans place Riverton House on a plot with the Meydan Horizon lagoon and its promenade to one side and the community park to the other, reached from the lagoon at ground level. At the 22 December 2025 inspection the RERA inspector recorded no construction activities on that plot, so this cycle's record describes the site as a starting point rather than a building taking shape against its lagoon frontage.
On the developer's location guide, the Al Ain - Dubai Road and Ras Al Khor Road (E44) carry traffic to and from the community, the airport (DXB) sits roughly 14 minutes away by car, and the map marks a proposed metro line nearby, a planned route rather than an operating station. For a buyer weighing a Q4 2027 move-in or rental plan against a site recorded at 0% in December 2025, those road links are the access that matters on the developer's map. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Buyer Resources for This Project
Investing in Riverton House at the 0% Baseline
At the earliest stage band, the useful questions are about protection and eligibility before any construction-linked instalment falls due. Each resource below is matched to where Riverton House stood at the December 2025 reading.

Riverton House Construction Updates
This page: the dated December 2025 inspection record for Riverton House, from its 0% baseline.

Riverton House Golden Visa: All Three Apartment Types Above the Line
All three Riverton House apartment types start above the Golden Visa threshold, the 1 bedroom by the narrowest of margins.
Read Riverton House Golden Visa Guide
Riverton House Escrow: One Supervised Account at Commercial Bank of Dubai
Riverton House payments, from 20% booking instalment on, go to Commercial Bank of Dubai's escrow for DLD project 4036's 151 units.
Verify Riverton House Escrow AccountUpdate Timeline
Other Riverton House Construction Updates
The December 2025 reading opens the Riverton House inspection history; each later reading joins the timeline on the construction updates hub as the register publishes it.
Where This Update Fits
Explore Riverton House Structure
The December 2025 record sits inside a wider picture: the Meydan Horizon listings it competes with, the community planned around its lagoon and park, and the developer responsible for the tower.

Meydan Horizon: The Symphony Apartments in a Lagoon District
Meydan Horizon, the Dubai Holding lagoon district beside Ras Al Khor Wildlife Sanctuary, has The Symphony apartments for sale.
See Meydan Horizon Properties for Sale
Meydan Horizon: Four Crystal Lagoons Facing Ras Al Khor Wildlife Sanctuary
Meydan Horizon is a lagoon district planned for 72,000 residents, with towers by Ellington, Imtiaz and Dubai Investments.
Explore the Meydan Horizon Community
Ellington Properties: Design-Led Boutique Residences With Curated Interiors
Ellington Properties, founded in 2014, is a design-led developer of apartments, villas and waterfront homes, with 30 developments launched and delivered.
View the Ellington Developer ProfileFAQs
Riverton House Construction Progress in December 2025: Frequently Asked Questions
The Dubai Land Department project register recorded 0% for Riverton House, project 4036, at the RERA inspection of 22 December 2025. It was the first reading on record, with no earlier inspection to compare against, so it marks the baseline that every later reading is measured from.
Yes. The DLD register lists a registered completion date of 31 December 2027, and the developer's expected handover is Q4 2027; registered dates can be revised between inspection cycles, and a single 0% reading does not show whether or how they will move. Confirm the current construction timetable with the developer in writing, and see the Riverton House construction updates hub for how register dates and readings are followed over the build.
The RERA Independent Progress Monitoring Report for 22 December 2025 notes that at the time of inspection there were no construction activities on site, and it shows the RERA progress status as N/A rather than a percentage. The 0% figure comes from the DLD project register, while the report describes the planned building as a residential and commercial building of B+G+4P+19F+R: a basement, ground floor, four podium levels, 19 floors and a roof.
The DLD register records a construction start date of 01 December 2025, three weeks before the inspection. At the 22 December 2025 visit, however, the RERA inspector observed no construction activities on site and the register logged 0%: the start date was on record, while measurable site progress had not yet appeared in it.
No. The header image is a developer rendering of the planned building, showing a furnished balcony overlooking water, chosen to illustrate this update; it does not show the site or its progress. The RERA report for 22 December 2025 carries its own inspection photographs as part of the official record.
The reading dates from the inspection of 22 December 2025 and was more than ten months old by October 2026, so later inspections may since have been published. The current figure for project 4036 can be checked in the Dubai REST app, which lists each inspection date with its reading.
A Question the FAQ Can Not Answer?

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is helping you read the December 2025 inspection record for Riverton House correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.