Riverton House Construction Update - December 2025

December 2025 Inspection Set the Riverton House Baseline at 0% in Meydan Horizon

Three weeks after its recorded start date, Riverton House had its first RERA inspection on 22 December 2025: no construction activities on site, 0% on the register.

Direct advisor access. Every message answered personally, never by a call center.

0%DLD Register Reading
22 December 2025Inspection Date
Q4 2027Expected Completion
4036DLD Project Number

Verified DLD Inspection Data

Riverton House Construction Snapshot

A first reading of 0% on 22 December 2025 placed Riverton House at the very start of the earliest stage band, before any of the 70/30 plan's construction-linked instalments could fall due; every later reading is measured from this baseline.

Project Name

Riverton House by Ellington

Project Number

4036

Project Status

Active

Construction Progress

0%

Inspection Date

22 December 2025

Construction Start

01 December 2025

Total Units

151 units

Total Built Area

14,230.19 sq m

Expected Completion

Q4 2027

Data source: RERA Independent Progress Monitoring Report for the inspection of 22 December 2025 (project 4036, plot 182, Bukadra; registered developer RIVERTON HOUSE DEVELOPMENT L.L.C; trust account bank Commercial Bank of Dubai (PSC)), read with the DLD project register, which supplies the 0% figure; the RERA report itself prints no percentage. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. This reading was more than ten months old by October 2026: re-verify project 4036 on Dubai REST for any newer reading before relying on it. The header image is a dated developer rendering of the planned building, not a photograph of the site. Last updated: December 2025.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Riverton House Construction Progress Summary

As the first entry in the Riverton House record, the 22 December 2025 inspection had no earlier reading to compare against. RERA's report described a residential and commercial building of B+G+4P+19F+R, showed its progress status as N/A, and noted no construction activities on site at the time of the visit, while the DLD register entered 0% as the opening figure.

On the Record
  • DLD project 4036, Riverton House, status Active
  • Construction start date in the register: 01 December 2025
  • Registration date in the register: 02 July 2026
  • Trust account bank: Commercial Bank of Dubai (PSC)
Observed at 0%
  • No construction activities on site at the time of inspection, per the RERA note
  • RERA progress status shown as N/A
  • DLD register reading of 0%, the first on record
  • Inspection photographs held in the RERA report
Ahead of Handover
  • The full B+G+4P+19F+R building described by RERA
  • 149 residences in 1, 2 and 3 bedroom layouts
  • Four construction-linked instalments, at 20%, 30%, 40% and 50% construction
  • Expected handover in Q4 2027
Next inspectionPublished in the DLD project register after the next RERA site visit; no later reading appears on this December 2025 record page.
Completion targetQ4 2027 expected handover; the DLD register lists a registered completion date of 31 December 2027, about two years after this inspection.
Remaining distance100 percentage points separated the 22 December 2025 reading from handover readiness.

Payment Linked Progress

What 0% Progress Means for Riverton House Buyers

Riverton House runs on a 70/30 plan in which four 5% instalments are tied to construction stages, at 20%, 30%, 40% and 50% construction, while the others follow each buyer's reservation date or completion. At the 0% reading of 22 December 2025, none of those four construction-linked instalments had been triggered, and at this earliest stage four actions matter most.

Before Every Instalment

Verify the escrow account

Each construction-period payment should reach only the DLD regulated escrow account registered for project 4036 with Commercial Bank of Dubai. Riverton House escrow account verification comes before the booking transfer; the lookup itself takes about two minutes against the official DLD project record.

Before Your Next Instalment

Map your SPA schedule

Your sale and purchase agreement dates the 60, 120, 180, 240 and 360 day instalments from your own reservation date, so their timing differs from buyer to buyer, while the four construction-linked instalments wait for the 20% to 50% stages. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

After Booking

Confirm your Oqood registration

Oqood is the Dubai Land Department's register of off-plan sales, and your unit's entry there is the record that ties your purchase to this inspection history. Ask the developer for your Oqood confirmation after booking and check that the project number on it reads 4036.

Every Cycle

Track the next readings

With a single 0% entry on record, each new DLD reading shows how close the 20% stage, and the first construction-linked instalment with it, has come. The Riverton House construction updates hub holds the dated record as it grows; confirm the current construction timetable with the developer in writing.

General framework, not legal advice: instalment triggers, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 0%?

Entering a project at its first reading trades certainty for runway: the 22 December 2025 record showed no construction activity on site, and in exchange the whole 70/30 schedule, all four construction-linked instalments included, still lay ahead. Every payment goes to the DLD-registered escrow account for project 4036, released against recorded construction progress.

Entering at the 0% Baseline
  • Recorded start 01 December 2025; first reading 0% on 22 December 2025
  • About two years from the reading to the Q4 2027 expected handover
  • No construction-linked instalment triggered at the reading
Typical Later Stage Entry
  • Visible building progress on record before the first payment
  • A shorter wait between signing and handover
  • Less of the instalment runway left, more due near completion
AED 2.01M ≈ USD 546KStarting Price
70/30 Plan30% Due on Completion
Q4 2027Expected Handover
Ask What Is Available at Riverton House

Limited Units Available, as listed on the project page at the time of writing; availability shifts between cycles.

About the Development

Riverton House Project Details

Riverton House by Ellington in Meydan Horizon project rendering of a slender residential tower above a landscaped podium and trees in Dubai - Presented by Tohid Fetrat
Meydan Horizon · Ellington

At the 22 December 2025 inspection, Riverton House had a recorded construction start and no construction activities on site: a planned B+G+4P+19F+R tower of 149 residences in 1, 2 and 3 bedroom apartments, sold on a 70/30 plan. Starting prices: AED 2.01M ≈ USD 546K.

A buyer joining at the first reading accepts the longest wait for the keys in return for the fullest payment runway, with handover expected in Q4 2027.

Riverton House by Ellington Project Guide

Site Context This Cycle

Explore Riverton House Location on Dubai Map

Ellington's plans place Riverton House on a plot with the Meydan Horizon lagoon and its promenade to one side and the community park to the other, reached from the lagoon at ground level. At the 22 December 2025 inspection the RERA inspector recorded no construction activities on that plot, so this cycle's record describes the site as a starting point rather than a building taking shape against its lagoon frontage.

On the developer's location guide, the Al Ain - Dubai Road and Ras Al Khor Road (E44) carry traffic to and from the community, the airport (DXB) sits roughly 14 minutes away by car, and the map marks a proposed metro line nearby, a planned route rather than an operating station. For a buyer weighing a Q4 2027 move-in or rental plan against a site recorded at 0% in December 2025, those road links are the access that matters on the developer's map. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Riverton House by Ellington on Dubai Map

Buyer Resources for This Project

Investing in Riverton House at the 0% Baseline

At the earliest stage band, the useful questions are about protection and eligibility before any construction-linked instalment falls due. Each resource below is matched to where Riverton House stood at the December 2025 reading.

Riverton House by Ellington in Meydan Horizon construction updates cover image featuring a project rendering of a slender residential tower above landscaped grounds in Dubai - Presented by Tohid Fetrat
You Are Here

Riverton House Construction Updates

This page: the dated December 2025 inspection record for Riverton House, from its 0% baseline.

Riverton House by Ellington in Meydan Horizon Golden Visa concept graphic with a gold visa card above a rendered poolside terrace in Dubai - Presented by Tohid Fetrat

Riverton House Golden Visa: All Three Apartment Types Above the Line

All three Riverton House apartment types start above the Golden Visa threshold, the 1 bedroom by the narrowest of margins.

Read Riverton House Golden Visa Guide
Riverton House by Ellington in Meydan Horizon escrow account concept graphic with shield and padlock icons over a rendered residential building and landscaped podium in Dubai - Presented by Tohid Fetrat

Riverton House Escrow: One Supervised Account at Commercial Bank of Dubai

Riverton House payments, from 20% booking instalment on, go to Commercial Bank of Dubai's escrow for DLD project 4036's 151 units.

Verify Riverton House Escrow Account

Update Timeline

Other Riverton House Construction Updates

The December 2025 reading opens the Riverton House inspection history; each later reading joins the timeline on the construction updates hub as the register publishes it.

All Riverton House Construction Updates

FAQs

Riverton House Construction Progress in December 2025: Frequently Asked Questions

The Dubai Land Department project register recorded 0% for Riverton House, project 4036, at the RERA inspection of 22 December 2025. It was the first reading on record, with no earlier inspection to compare against, so it marks the baseline that every later reading is measured from.

Yes. The DLD register lists a registered completion date of 31 December 2027, and the developer's expected handover is Q4 2027; registered dates can be revised between inspection cycles, and a single 0% reading does not show whether or how they will move. Confirm the current construction timetable with the developer in writing, and see the Riverton House construction updates hub for how register dates and readings are followed over the build.

The RERA Independent Progress Monitoring Report for 22 December 2025 notes that at the time of inspection there were no construction activities on site, and it shows the RERA progress status as N/A rather than a percentage. The 0% figure comes from the DLD project register, while the report describes the planned building as a residential and commercial building of B+G+4P+19F+R: a basement, ground floor, four podium levels, 19 floors and a roof.

The DLD register records a construction start date of 01 December 2025, three weeks before the inspection. At the 22 December 2025 visit, however, the RERA inspector observed no construction activities on site and the register logged 0%: the start date was on record, while measurable site progress had not yet appeared in it.

No. The header image is a developer rendering of the planned building, showing a furnished balcony overlooking water, chosen to illustrate this update; it does not show the site or its progress. The RERA report for 22 December 2025 carries its own inspection photographs as part of the official record.

The reading dates from the inspection of 22 December 2025 and was more than ten months old by October 2026, so later inspections may since have been published. The current figure for project 4036 can be checked in the Dubai REST app, which lists each inspection date with its reading.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the December 2025 inspection record for Riverton House correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts