Rosewater at Dubai Creek Harbour by Emaar Properties in Dubai Creek Harbour construction updates cover image featuring a project rendering of waterfront residential buildings beside the lagoon with high-rise towers in the background in Dubai - Presented by Tohid Fetrat

Emaar Properties · Dubai Creek Harbour

Rosewater at Dubai Creek Harbour Construction Updates

The Closed Build Record of a Three-Building Creek Beach Cluster

Rosewater at Dubai Creek Harbour reached 100% construction on the 07 November 2024 register reading, closing the record for its three mid-rise buildings beside Creek Beach.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

100%Construction Progress
07 November 2024Latest RERA Inspection
211 residential unitsTotal Units
Project 2193DLD Registration

Construction Snapshot

Rosewater at Dubai Creek Harbour at a Glance

Rosewater at Dubai Creek Harbour is Emaar's 211-residence cluster at the northern tip of the Creek Beach district, and its register record is already closed: project 2193 went from registration on 28 October 2019 and a construction start on 01 April 2020 to 100% on 07 November 2024, and the DLD register now lists it as Finished. Because the cluster tops out at G+M+11 and its three blocks share one courtyard, the monitoring report treats all of it as a single delivery rather than tower by tower, and the six entries below are the register anchors behind that record.

DLD Project Number

2193

Project Status

Finished

Construction Start

01 April 2020

Total Units

211 residential units

Total Built-Up Area

310,997.66 sq m

Registered Completion Date

31 March 2023 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Rosewater at Dubai Creek Harbour Construction Update Timeline

Only one dated reading exists in Rosewater's published record: 100% on 07 November 2024. The register reached it from a previous figure of 95.08% that it leaves undated, so that earlier number is described here but carries no dot and no table row. The track therefore runs straight from the April 2020 groundbreaking to the completion reading, and the single row below links the November 2024 update, the only monthly report in this series. At this page's 23 September 2026 build, that reading was 685 days old.

Inspection MonthConstruction ProgressInspection DateFull Update
November 2024100%07 November 2024View the November 2024 update
!

Reading the dates: the DLD-registered completion date for project 2193 is 31 March 2023. The completion documents listed in the 07 November 2024 monitoring report are dated 09 August 2024 for the DCD certificate and 21 October 2024 for the BCC, and the register recorded 100% on 07 November 2024. The registered date is the anchor set when Rosewater entered the register; the register now shows the project as Finished, with handover status Ready.

Pace Analysis

How Fast Rosewater at Dubai Creek Harbour Has Been Built

One dated reading cannot produce a points-per-month figure, and none is invented here. What Rosewater's record does support is the time between its dated milestones, computed from the register and the monitoring report:

  • Oct 2019 to Apr 2020: registration to construction startAbout 5 months
  • Apr 2020 to Aug 2024: construction start to the DCD certificateAbout 52 months
  • Aug 2024 to Nov 2024: DCD, then BCC, then 100% on 07 Nov 202490 days
  • Undated reading to 07 Nov 2024: 95.08% to 100%+4.92 points, no monthly rate

Read as a shape, Rosewater's record is a long build followed by a fast close. About 52 months separate the 01 April 2020 start from the DCD certificate of 09 August 2024; after that the paperwork moved in weeks, with the BCC 73 days later on 21 October 2024 and the 100% register reading 17 days after the BCC. The last recorded step, from 95.08% to 100%, was only 4.92 points, but because the register gives the 95.08% no date, any monthly rate built on it would be a guess. For an end user, the practical meaning is that all three buildings were certified before the November 2024 reading and nothing remains to be built; for an investor, the dates that matter are the DCD and BCC, which turn this into a ready-property comparison, while 31 March 2023 remains the registered date on file.

Get the Next Inspection Figure First

Tell me you are tracking Rosewater at Dubai Creek Harbour and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Rosewater at Dubai Creek Harbour

A 100% reading from 07 November 2024 tells you the building work is done; the project guide tells you what that work delivered and what it costs to own today:

Rosewater at Dubai Creek Harbour by Emaar Properties panoramic view of Creek Beach waterfront residences and Dubai skyline in Dubai Presented by Tohid Fetrat

Rosewater at Dubai Creek Harbour: Apartments and Penthouses at Creek Beach

Rosewater at Dubai Creek Harbour sets 211 apartments and penthouses in three mid-rise buildings around an inner plaza at Creek Beach.

View the Rosewater at Dubai Creek Harbour Project Guide

Considering a Ready Rosewater Residence?

Limited units are available at Rosewater, and in a finished 211-residence cluster each sale narrows what is left. If this completion record is what brought you here, ask me what is available now, before the remaining choice gets smaller.

Ask About Remaining Availability on WhatsApp

Stage Record

Rosewater at Dubai Creek Harbour Build Stages, Mapped to the Inspections

Rather than a generic construction sequence, each stage below is pinned to what Rosewater's own documents date: the register entries of October 2019 and April 2020, the 2024 certificates and the 07 November 2024 reading. With only one dated percentage on file, the earlier windows are bounded by those documents rather than by inspection figures.

Oct 2019 to Apr 2020

Registration and Site Activation

Project 2193 entered the DLD register on 28 October 2019, and construction started on 01 April 2020 on plot 169, Al Khairan First, where the three buildings meet the canal edge of Creek Beach.

Apr 2020 onward

Three Concrete Frames

Concrete frames with block walls rose for all three buildings, to G+M+10, G+M+11 and G+M+7; the published record holds no dated percentage from this period.

Before Aug 2024, 95.08% undated

Finishes, Services, and Meters

Internal and external finishes, services rooms, and main and sub-meters were completed and connected, carrying the register to a previous reading of 95.08% that it leaves undated.

Aug 2024 to Oct 2024

Completion Certificates Issued

The DCD certificate is dated 09 August 2024 and the BCC 21 October 2024; both, with lift safety certificates, are listed as received in the November 2024 monitoring report.

Current Phase07 Nov 2024 onward, 100% and Finished

Completion Reading and Handover

The register recorded 100% on 07 November 2024 and lists project 2193 as Finished, with the pool area, gym, parking areas and lobbies recorded as ready and handover status Ready.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Rosewater at Dubai Creek Harbour's own record.

Buyer Position

Tracking Your Position at Rosewater at Dubai Creek Harbour

This page is one of four project resources that together cover a Rosewater at Dubai Creek Harbour purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Rosewater at Dubai Creek Harbour by Emaar Properties in Dubai Creek Harbour construction updates cover image featuring a project rendering of waterfront residential buildings beside the lagoon with high-rise towers in the background in Dubai - Presented by Tohid Fetrat
You Are Here

Rosewater at Dubai Creek Harbour Construction Updates

This page: the register record for Rosewater, from October 2019 registration to 100% in November 2024.

Rosewater at Dubai Creek Harbour by Emaar Properties in Dubai Creek Harbour Golden Visa concept with a Golden Visa card above a landscaped lagoon-style swimming pool and residential buildings in Dubai - Presented by Tohid Fetrat

Rosewater at Dubai Creek Harbour Golden Visa: Three Tiers Above the Line

Rosewater at Dubai Creek Harbour, three Emaar buildings around a shared plaza, qualifies at 2 and 3 bedrooms and the penthouses.

Read the Rosewater at Dubai Creek Harbour Golden Visa Guide
Rosewater at Dubai Creek Harbour by Emaar Properties in Dubai Creek Harbour escrow account protection concept with shield and padlock icons above a landscaped pedestrian promenade, fountain, and residential buildings in Dubai - Presented by Tohid Fetrat

Rosewater at Dubai Creek Harbour: The Mashreq Escrow, Fully Certified

Rosewater at Dubai Creek Harbour is DLD project 2193, 211 units escrowed with Mashreq and 100% certified by November 2024.

Verify the Rosewater at Dubai Creek Harbour Escrow Account
Rosewater at Dubai Creek Harbour by Emaar Properties in Dubai Creek Harbour snagging inspection graphic showing a furnished kitchen and dining area with balcony access in Dubai - Presented by Tohid Fetrat

Rosewater at Dubai Creek Harbour Snagging for Apartments and Penthouses

Rosewater at Dubai Creek Harbour is three Emaar mid-rise buildings around an inner plaza, holding 211 apartments and penthouses.

Book Rosewater at Dubai Creek Harbour Snagging

Approaching Handover

Between 100% and Handover: What Rosewater at Dubai Creek Harbour Buyers Should Do Now

At Rosewater the construction gap is already closed: the register reads 100% and Finished from 07 November 2024, the BCC is dated 21 October 2024, and handover status is Ready, so what stands between an original buyer and the keys is paperwork and acceptance rather than building work. Handover notices typically give buyers a short window to complete their appointment, so the three steps below belong before that notice lands, not after it.

First, arrange independent snagging so defects in your residence are documented before you accept it; the Rosewater snagging page explains what gets checked in a finished unit and why the rectification clock starts at building completion, not at move-in.

Second, if any balance remains on your unit, confirm it against the Rosewater escrow account page before it moves, so a payment tied to the completion milestone goes only into project 2193's escrow account at Mashreq Bank PSC.

Third, if your unit is a 2 bedroom apartment or larger, settle residency eligibility early through the Rosewater Golden Visa guide; the 1 bedroom tier at AED 1.70M ≈ USD 463K sits below the AED 2M ≈ USD 545K line, and title deed timing shapes the application path.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Dubai Creek Harbour Structure

A finished record reads differently next to what is still rising around it. These three pages set Rosewater's completion against the Dubai Creek Harbour listings, the wider masterplan and Emaar's developer record:

Dubai Creek Harbour Properties for Sale waterfront community view with Creek waters modern residential towers and Downtown Dubai skyline Presented by Tohid Fetrat

Dubai Creek Harbour Properties for Sale

Browse waterfront apartments, branded residences and penthouses for sale in Dubai Creek Harbour.

See Dubai Creek Harbour Properties for Sale
Dubai Creek Harbour skyline with The Grand by Emaar and Dubai Creek Tower – luxury waterfront community with marina and skyline views, presented by Tohid Fetrat.

Dubai Creek Harbour: Emaar's Waterfront City With a Marina and Urban Beach

Dubai Creek Harbour is Emaar's waterfront city between Downtown Dubai and the Creek, planned for 48,500 homes with skyline views.

Explore the Dubai Creek Harbour Community
Emaar Properties developer showcasing Downtown Dubai skyline with Burj Khalifa and surrounding residential and commercial towers at dusk Presented by Tohid Fetrat

Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities

Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.

View the Emaar Properties Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Rosewater at Dubai Creek Harbour Construction Updates Frequently Asked Questions

Rosewater at Dubai Creek Harbour is complete: the DLD project register lists project 2193 as Finished, at 100% construction progress on its 07 November 2024 reading, and handover status is Ready. On 23 September 2026 that reading was 685 days old, so any later register change would appear only on the live record; the full history sits in the inspection timeline above.

Rosewater's latest dated reading is 100%, entered on the DLD project register on 07 November 2024; it rose 4.92 points from an earlier 95.08% that the register leaves undated, so no monthly rate can be drawn from the step. The monitoring report of the same date records all construction at site as completed, and the full detail is in the Rosewater November 2024 construction update.

Rosewater at Dubai Creek Harbour was certified complete in 2024: its DCD certificate carries the date 09 August 2024 and its BCC 21 October 2024, and the register recorded 100% on 07 November 2024. The DLD-registered completion date for project 2193 was 31 March 2023; the register now lists the project as Finished with handover status Ready, and this page's record is updated if that register entry changes.

The DLD register counts 211 residential units at Rosewater at Dubai Creek Harbour across three mid-rise buildings of G+M+10, G+M+11 and G+M+7, all recorded complete at the 07 November 2024 reading. They divide into 1, 2 and 3 bedroom apartments starting at 711 sq ft (66 sq m) and 3 and 4 bedroom penthouses of 3,000+ sq ft (279+ sq m).

Construction at Rosewater at Dubai Creek Harbour started on 01 April 2020, about five months after project 2193 entered the DLD register on 28 October 2019. The first dated reading in the published record is also its last: 100% on 07 November 2024.

Counting from the 01 April 2020 start, Rosewater at Dubai Creek Harbour took about 52 months to reach its DCD certificate of 09 August 2024, about 55 months to reach its BCC of 21 October 2024, and 1,681 days in total to the 100% register reading of 07 November 2024. Because the record holds only one dated percentage, the pace analysis above works from these milestone intervals rather than a monthly rate.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Rosewater at Dubai Creek Harbour construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.