Emaar Properties · The Heights
Salva at The Heights Construction Updates
A Dated Register Record for 483 G+2 Villas, Opened at Enabling Works
Salva at The Heights logged 0.5% in the Dubai Land Department register on 9 June 2026, opening the dated record for 483 villas still at enabling works.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Salva at The Heights at a Glance
Emaar's Salva at The Heights is a 483-villa G+2 cluster in The Heights Country Club & Wellness, entered in the Dubai Land Department register as project 4240, Salva The Heights, on plot 3407 in Al Yelayiss 5. Registration on 26 November 2025 came 173 days before the 18 May 2026 construction start, and the only dated reading so far, 0.5% on 9 June 2026, followed 22 days after that start. Because Salva is a low-rise cluster rather than a single tower, that one register figure covers 483 separate villas at once, which is why this page reads the record in stages rather than floor by floor.
4240
Active
18 May 2026
483 villas (G+2)
235,619.25 sq m
31 July 2030 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Salva at The Heights Construction Update Timeline
The Salva record holds a single dated reading so far: 0.5% on 9 June 2026, logged in the Dubai Land Department register 22 days after the 18 May 2026 construction start. The register also shows a previous inspection at 0% with no date attached, so it appears on the track below as an unlabelled baseline dot rather than as a table row, and the one row links the full June 2026 update with the RERA report's enabling works notes.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| June 2026 | 0.5% | 9 June 2026 | View the June 2026 update |
Pace Analysis
How Fast Salva at The Heights Has Been Built
Pace is measured between dated inspections, and the Salva register holds one, 0.5% on 9 June 2026. These are the figures that can be set side by side today, with no rate drawn from them:
- 18 May 2026 start to the 9 June 2026 reading0.5% after 22 days
- Previous inspection figure shown in the register0%, no date recorded
- Dated readings on record for a pace calculation1 of the 2 needed
- 9 June 2026 reading to the 31 July 2030 registered completion date99.5 points, 1,513 days
There is no curve to read yet, only a starting point. The RERA report filed for the 9 June 2026 visit records mobilisation and enabling works on plot 3407 and prints no percentage of its own, so the 0.5% is the register's figure alone, logged while the ground was being prepared rather than while villas were rising. A monthly rate drawn from the 22 days after the 18 May 2026 start would describe mobilisation, not construction, so none is published here, and neither is a forecast. The second dated reading will turn this section into a measured pace; until it arrives, an end user can hold the July 2030 handover schedule as the reference point, and an investor should treat the 99.5 points still unrecorded as the whole build still in front of the project.
Get the Next Inspection Figure First
Tell me you are tracking Salva at The Heights and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Salva at The Heights
A 0.5% reading from 9 June 2026 only means something next to what it is building toward. The full project guide covers the villas this record will follow from enabling works to July 2030:

Salva at The Heights: Emaar Villas in a Wellness-Led Community
Salva at The Heights is Emaar's 483-villa cluster of family villas, planned around a Wellness Centre, lakes and nature trails.
View the Salva at The Heights Project GuideConsidering an Early-Stage Entry?
Availability at Salva moves with each Emaar release, and entering at enabling works leaves most of the build and most of the payment schedule ahead of you. If the record on this page is what brought you here, ask me for current availability before the next release changes it.
Ask About Remaining Availability on WhatsAppStage Record
Salva at The Heights Build Stages, Mapped to the Inspections
The first dated Salva reading came 22 days after the registered start, so only two of the five stages below carry dates; the other three wait for register entries that have not been made yet, and each window will be dated from the reading that first places Salva inside it.
Registration and Pre-Start
Entered in the DLD register as project 4240 on 26 November 2025, with its trust account at Emirates Islamic Bank, 173 days before the registered 18 May 2026 start.
Mobilisation and Enabling Works
The RERA report for 9 June 2026 found mobilisation and enabling works ongoing on plot 3407, recorded as Enabling Works, Progressing, with the register at 0.5%.
Villa Foundations
Foundations for the 483 villas across the cluster. No register reading has yet placed Salva in this stage; the first one that does will date this window.
G+2 Villa Structures
Ground and first floors on every villa type, plus the roof floor on the 4 and 5 bedroom villas. Emaar's payment schedule estimates its 40% construction milestone for June 2028.
Finishing, Cluster Amenities, and Handover
Villa finishes and the cluster's pools, sport courts, community centre, mosque and cafe, completed toward the handover scheduled for July 2030.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Salva at The Heights's own record.
Buyer Position
Tracking Your Position at Salva at The Heights
This page is one of four project resources that together cover a Salva at The Heights purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Salva at The Heights Construction Updates
This page: the DLD register record for Salva at The Heights, from enabling works to handover.

Salva at The Heights Golden Visa: Every Villa Tier Clears
Salva at The Heights, Emaar Properties' 483 villas in The Heights Country Club & Wellness, qualifies at all three villa types.
Read the Salva at The Heights Golden Visa Guide
Salva at The Heights Escrow: Emaar's Heights Account at Emirates Islamic
Emirates Islamic holds Salva at The Heights escrow as DLD project 4240 for 483 units, certified 0.5% in June 2026.
Verify the Salva at The Heights Escrow AccountApproaching Handover
Between 0.5% and Handover: What Salva at The Heights Buyers Should Do Now
The Salva payment plan runs on the calendar while its record runs on the register. On Emaar's published 80/20 schedule, 30% of the price, the 10% down payment and the instalments dated March 2026 and September 2026, falls on or before September 2026, while the register stood at 0.5% on 9 June 2026 and the first construction-linked row, the 40% milestone, is dated June 2028. The next dated instalment on that schedule is March 2027, so the three checks below belong before it, not after it; how earlier dated rows apply to a buyer entering now is settled in the SPA.
First, before any transfer, match the account you are paying to the project 4240 trust account at Emirates Islamic Bank on the Salva at The Heights escrow account page, so every instalment lands where the DLD framework holds it.
Second, if residency is part of the plan, settle eligibility early through the Salva Golden Visa eligibility guide, since all three villa tiers clear the property threshold on price and the off-plan application path is worth fixing before further instalments fall due.
Third, follow the record itself: each new dated register reading is added to the timeline on this page, and the Salva June 2026 construction update holds the full detail of the first one, from the RERA report's notes to the register panel.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore The Heights Structure
The 0.5% recorded at Salva on 9 June 2026 sits inside a much larger build: the villa market across The Heights, a master community of 7.5M sq m laid out around it, and the developer whose schedule sets the July 2030 date. These three pages cover each layer:

The Heights Properties for Sale
Explore villas for sale across The Heights by Emaar, with current availability, prices, floor plans, payment plans, and upcoming developments.
See The Heights Properties for Sale
The Heights Community Overview
The Heights Country Club & Wellness by Emaar is an 81 million sq ft master community in Dubai, featuring luxury villas, 21 residential clusters, landscaped parks, and wellness facilities.
Explore the The Heights Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Salva at The Heights Construction Updates Frequently Asked Questions
Salva at The Heights, DLD project 4240, is at the enabling works stage: the Dubai Land Department project register recorded 0.5% on 9 June 2026, and the RERA monitoring report for that visit lists the stage as Enabling Works, Progressing. That reading is the latest in the record supplied for this page, and the full record sits in the Salva inspection timeline above.
The register moved from a previous inspection figure of 0%, which carries no date, to 0.5% on 9 June 2026, a change of 0.5 points. Because the earlier figure is undated, that 0.5-point change cannot be spread over any period, and 9 June 2026 stands as the first dated entry in the Salva record.
At the 9 June 2026 reading of 0.5%, Salva at The Heights had 99.5 percentage points and 1,513 days to go before its registered completion date of 31 July 2030, the date behind the July 2030 handover schedule. That registered date has not passed, and this page is updated as each new dated register reading is published.
The record covers 483 villas under DLD project 4240, described in the RERA monitoring report as a residential development of G+2 villas, in three, four and five bedroom layouts. The 0.5% register reading of 9 June 2026 is a project-level figure for the whole cluster rather than a reading for any individual villa.
The Dubai Land Department entry lists the project as Salva The Heights, number 4240, status Active, registered on 26 November 2025, with construction started on 18 May 2026 and completion registered for 31 July 2030. Its inspection panel shows two figures: current progress of 0.5% dated 9 June 2026 and a previous inspection of 0% without a date. Only the dated figure becomes a row in this page's timeline.
A pace needs two dated readings, and the Salva register holds one: 0.5% on 9 June 2026. The only earlier figure, 0%, has no date, and the 22 days between the 18 May 2026 construction start and that reading cover mobilisation and enabling works rather than villa construction, so no rate is published. The Salva pace analysis will carry the first measured figure once a second dated reading exists.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Salva at The Heights construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.