Seagate at Rashid Yachts & Marina by Emaar Properties in Rashid Yachts & Marina construction updates cover image featuring a project rendering of residential buildings beside a palm lined waterfront promenade in Dubai - Presented by Tohid Fetrat

Emaar Properties · Rashid Yachts & Marina

Seagate at Rashid Yachts & Marina Construction Updates

The Closed Build Record of Four Waterfront Buildings at Mina Rashid

Seagate reached 100% in the DLD project register on 14 April 2025, now seventeen months ago, closing a four-building Mina Rashid build that started in September 2019.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

100%Construction Progress
14 April 2025Latest RERA Inspection
282 apartmentsTotal Units
Project 2163DLD Registration

Construction Snapshot

Seagate at Rashid Yachts & Marina at a Glance

Seagate at Rashid Yachts & Marina is Emaar's 282-apartment development on plot 359 at Mina Rashid, and its construction record is now closed: registered on 01 May 2019, started on 01 September 2019, and shown at 100% in the DLD project register on 14 April 2025. Because Seagate is four buildings stepping from 15 floors down to 5 rather than a single tower, that register figure describes the whole complex, not any one block, and the cards below are the anchors behind it.

DLD Project Number

2163

Project Status

Finished

Construction Start

01 September 2019

Total Units

282 apartments

Total Built-Up Area

35,568.37 sq m

Registered Completion Date

30 September 2025

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Seagate at Rashid Yachts & Marina Construction Update Timeline

Seagate's record holds a single dated inspection: 100% in the DLD project register on 14 April 2025, a 4.55-point step from a previous reading of 95.45% that the register shows without a date. The undated figure is named here but not plotted, so the track below carries one dot at the finish line, and the table links the full April 2025 update for project 2163.

Inspection MonthConstruction ProgressInspection DateFull Update
April 2025100%14 April 2025View the April 2025 update
!

Reading the dates: the DLD-registered completion date for project 2163 is 30 September 2025, and that date has now passed. Seagate's register had already reached 100% on 14 April 2025, 169 days earlier, the status now reads Finished, and handover took place in September 2025, so the registered date stands as a reference point in the record rather than a deadline still in play.

Pace Analysis

How Fast Seagate at Rashid Yachts & Marina Has Been Built

Seagate's record cannot support a points-per-month rate: the DLD project register dates only the 100% reading of 14 April 2025, and the 95.45% before it carries no date. The one measurable step is the closing phase:

  • Undated reading to 14 Apr 2025: finishing and commissioning, 95.45% to 100%+4.55 points, interval undated

What the record does show is where those last points fell. By the 14 April 2025 inspection, the IPMR already listed the DCD as issued on 26 December 2024 and the BCC as issued by PCFC on 31 December 2024, so the final 4.55 points were recorded 104 days after certification, as closeout of the four buildings rather than active construction. Measured end to end, the build ran about five years and seven months from the 01 September 2019 start to the 100% reading, and that reading came 169 days before the 30 September 2025 registered completion date. For an end user, the sequence adds up to a certified building handed over in September 2025; for an investor, it is a delivery that closed its progress record ahead of the registered date instead of chasing it.

Get the Next Inspection Figure First

Tell me you are tracking Seagate at Rashid Yachts & Marina and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Seagate at Rashid Yachts & Marina at Mina Rashid

A 100% reading only matters alongside what was delivered. The project guide covers the finished Seagate apartments this record describes:

Seagate at Rashid Yachts & Marina by Emaar marina view with yachts and modern waterfront residences in Dubai - Presented by Tohid Fetrat

Seagate at Rashid Yachts & Marina, a Four-Building Waterfront Address

Seagate at Rashid Yachts & Marina holds 282 Emaar apartments of one to four bedrooms across four buildings in Mina Rashid.

View the Seagate at Rashid Yachts & Marina Project Guide

Considering a Finished Seagate Apartment?

Most Seagate apartments have passed to their owners since the September 2025 handover, and what remains on offer changes at short notice. If this record is what brought you here, ask me what is available now before you weigh it against the off-plan launches around it.

Ask About Remaining Availability on WhatsApp

Stage Record

Seagate at Rashid Yachts & Marina Build Stages, Mapped to the Inspections

Only the final window of Seagate's build carries dates in the record: the certificates of December 2024 and the 100% reading of 14 April 2025. The earlier stages are bounded by the 01 September 2019 start and the IPMR's description of four buildings from 5 to 15 floors, so they appear as windows rather than dated readings.

May 2019 to Sep 2019

Registration and Site Activation

Seagate was registered with the DLD on 01 May 2019 as project 2163 on plot 359, and construction started four months later, on 01 September 2019.

From Sep 2019, no dated reading

Basements and Foundations

The IPMR describes every Seagate building with a basement and ground level beneath its upper floors; no dated inspection from this window appears in the record published here.

Before the 95.45% reading

Concrete Frames Across Four Buildings

Concrete structures rose to 15 floors on Building 1, 10 on Building 3, 6 on Building 2 and 5 on Building 4, each topped by a roof level, with no dated reading from this stage.

Up to the undated 95.45%

Blockwork and Finishes

The IPMR pairs the concrete frames with blockwork and internal and external finishes; the last figure before completion was 95.45%, which the DLD project register lists without a date.

Current PhaseDec 2024 to Sep 2025, 100% on 14 Apr 2025

Certification, 100%, and Handover

DCD was issued on 26 December 2024 and the BCC by PCFC on 31 December 2024; the DLD project register reached 100% on 14 April 2025, and handover followed in September 2025.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Seagate at Rashid Yachts & Marina's own record.

Buyer Position

Tracking Your Position at Seagate at Rashid Yachts & Marina

This page is one of four project resources that together cover a Seagate at Rashid Yachts & Marina purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Seagate at Rashid Yachts & Marina by Emaar Properties in Rashid Yachts & Marina construction updates cover image featuring a project rendering of residential buildings beside a palm lined waterfront promenade in Dubai - Presented by Tohid Fetrat
You Are Here

Seagate at Rashid Yachts & Marina Construction Updates

This page: Seagate's closed construction record, from 2019 registration to the 100% April 2025 reading.

Seagate at Rashid Yachts & Marina by Emaar Properties in Rashid Yachts & Marina Golden Visa card graphic above a balcony and yacht marina view in Dubai - Presented by Tohid Fetrat

Seagate at Rashid Yachts & Marina Golden Visa: Four Buildings, Title Deeds

Seagate at Rashid Yachts & Marina, Emaar's four-building complex, transfers on title deed; 2, 3 and 4 bedroom apartments qualify.

Read the Seagate at Rashid Yachts & Marina Golden Visa Guide
Seagate at Rashid Yachts & Marina by Emaar Properties in Rashid Yachts & Marina escrow account protection graphic with shield and padlock icons above a yacht marina view in Dubai - Presented by Tohid Fetrat

Seagate at Rashid Yachts & Marina Escrow, Certified 100% in 2025

Seagate at Rashid Yachts & Marina, DLD project 2163, read 100% certified April 2025; 302 units escrowed at Dubai Islamic Bank.

Verify the Seagate at Rashid Yachts & Marina Escrow Account
Seagate at Rashid Yachts & Marina by Emaar Properties in Rashid Yachts & Marina snagging inspection graphic over a modern living room with full height windows and marina view in Dubai - Presented by Tohid Fetrat

Seagate at Rashid Yachts & Marina Snagging Before You Sign

Seagate at Rashid Yachts & Marina is a four-building Emaar Properties complex of 282 apartments on the promenade at Mina Rashid.

Book Seagate at Rashid Yachts & Marina Snagging

Approaching Handover

Between 100% and Handover: What Seagate at Rashid Yachts & Marina Buyers Should Do Now

With the register at 100% since 14 April 2025 and handover completed in September 2025, nothing is left to build at Seagate; what remains is buyer-side work on one specific apartment. The timing still matters: defect liability runs from building completion, which Seagate reached before handover, not from the day a buyer moves in, so each month of delay shortens the cover left rather than starting it.

First, have the specific apartment inspected independently before you sign acceptance; the Seagate snagging inspection page sets out what gets documented in a finished four-building complex.

Second, check how the construction-period instalments were handled through the Seagate at Rashid Yachts & Marina escrow account page, especially on a resale unit whose seller paid the original schedule.

Third, if residency matters, confirm the tier before you commit: 1 bedroom apartments from AED 1.75M ≈ USD 476K sit below the AED 2M ≈ USD 545K threshold, and the Seagate at Rashid Yachts & Marina Golden Visa guide covers the 2, 3 and 4 bedroom route.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Mina Rashid Structure

Seagate is finished, but the masterplan around it is not. These three pages set its closed record against the apartment market, the Mina Rashid community still building out, and Emaar's wider delivery pipeline:

Waterfront apartment buildings with modern architecture overlooking a marina filled with luxury yachts at Rashid Yachts and Marina by Emaar in Dubai Presented by Tohid Fetrat

Mina Rashid Properties for Sale

Browse waterfront apartments for sale at Rashid Yachts & Marina, with projects, prices and payment plans.

See Mina Rashid Properties for Sale
Luxury yachts at Rashid Yachts and Marina waterfront community with modern residences and marina promenade in Mina Rashid Dubai Presented by Tohid Fetrat

Mina Rashid Community Overview

Read the Rashid Yachts & Marina guide: Emaar's transformation of historic Port Rashid into a marina lifestyle community.

Explore the Mina Rashid Community
Emaar Properties developer showcasing Downtown Dubai skyline with Burj Khalifa and surrounding residential and commercial towers at dusk Presented by Tohid Fetrat

Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities

Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.

View the Emaar Properties Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Seagate at Rashid Yachts & Marina Construction Updates Frequently Asked Questions

Seagate at Rashid Yachts & Marina is complete: DLD project 2163 carries the status Finished, and its register showed 100% construction progress at the inspection dated 14 April 2025. The IPMR of that date lists the DCD as issued on 26 December 2024 and the BCC as issued by PCFC on 31 December 2024, and handover followed in September 2025. The single dated reading sits in the Seagate inspection timeline above.

The inspection dated 14 April 2025 took Seagate to 100% in the DLD project register, 4.55 points above a previous reading of 95.45% that the register shows without a date. That reading was 527 days old on 23 September 2026, when this page was prepared, and the report behind it is summarised in the Seagate at Rashid Yachts & Marina April 2025 construction update.

Seagate reached 100% in the DLD project register on 14 April 2025 and was handed over in September 2025. Its registered completion date in the DLD record, 30 September 2025, has now passed and works as a reference point rather than a forecast; the building was certified well before it, with the BCC issued by PCFC on 31 December 2024, 273 days earlier.

Seagate at Rashid Yachts & Marina has 282 apartments in 1, 2, 3 and 4 bedroom layouts, spread across four buildings of 15, 6, 10 and 5 floors, and the 100% reading of 14 April 2025 covers all four together. Sizes run from about 706 sq ft (66 sq m) for a 1 bedroom to 3,242 sq ft (301 sq m) for the largest 4 bedroom, set out tier by tier in the Seagate at Rashid Yachts & Marina layouts and prices.

The DLD project register for Seagate shows two figures: 100% at the inspection dated 14 April 2025 and a previous reading of 95.45% with no date attached. Without a second date, no points-per-month pace can be calculated honestly, so this page reports the 4.55-point closing step and the overall span instead: about five years and seven months from the 01 September 2019 construction start to the 100% reading. The Seagate pace analysis above sets out what that span does and does not show.

Seagate was handed over in September 2025, while four other Emaar apartment projects in Rashid Yachts & Marina covered on this site, Avonlea, Ocean Star, Ocean Cove and Marina Views, are scheduled for handover between November 2027 and December 2028. Seagate is finished while those neighbours remain off-plan, so construction on surrounding plots is likely to continue for some years; the Rashid Yachts & Marina community guide tracks that wider build-out.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Seagate at Rashid Yachts & Marina construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.