Emaar Properties · Rashid Yachts & Marina
Sera 1 at Rashid Yachts & Marina Construction Updates
Tracking Emaar's Marina Phase From Its First Certified Reading
Sera 1 recorded 0.04% certified progress at its 02 June 2026 RERA inspection, the first reading on a marina-side build registered to complete in November 2029.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Sera 1 at Rashid Yachts & Marina at a Glance
Sera 1 is Emaar's 203-apartment pair of buildings on plot 653 at Madinat Dubai Almelaheyah, registered with the Dubai Land Department as project 4031 on 25 August 2025 and under construction since 26 February 2026. Its certified record currently runs to a single entry, the 0.04% logged on 02 June 2026, which makes this one of the shortest build records tracked anywhere on this site. The figures below are the registered anchors that every future reading will be measured against.
4031
Active
26 February 2026
203 residential units
21,420.98 sq m
30 November 2029 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Sera 1 at Rashid Yachts & Marina Construction Update Timeline
One inspection sits on this record so far. The RERA-appointed inspector attended on 02 June 2026 and certified 0.04% against a previous reading of 0%, entering the progress status as Enabling Works - Progressing with mobilisation ongoing on plot 653. The single dot on the track below is that reading, and the row beneath it links the full June 2026 update. Each later inspection is added here as the register records it, which is what turns a one-line record into a pace.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| June 2026 | 0.04% | 02 June 2026 | View the June 2026 update |
Pace Analysis
How Fast Sera 1 at Rashid Yachts & Marina Has Been Built
Pace is the distance between two certified readings divided by the months between them. Sera 1 has one certified reading, so what follows is a baseline and a requirement rather than a measured speed:
- 26 Feb 2026 construction start to 02 Jun 2026 inspection: mobilisation and enabling works, 0% to 0.04%About 0.0 points per month
- 02 Jun 2026 to the registered completion of 30 Nov 2029: 99.96 points across about 41 monthsAbout 2.4 points per month required
Ninety-six days separate the 26 February 2026 construction start from the 02 June 2026 inspection, and across that window the certified figure moved four hundredths of a point. That is the arithmetic of an enabling-works entry rather than a verdict on the site: the RERA scale spreads across two buildings and all 203 apartments, so the stage recorded here registers close to zero by design. The second figure is the one worth holding on to. Reaching 100% by the registered date of 30 November 2029 implies an average of about 2.4 points a month from June 2026 onward, and that average only becomes readable once Tower A and Tower B begin posting structural readings. Until a second certified figure exists this record has a starting point and a destination but no measured speed, which is exactly why the next inspection carries more weight here than a mid-build reading would on a project already halfway up.
Get the Next Inspection Figure First
Tell me you are tracking Sera 1 at Rashid Yachts & Marina and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Sera 1 at Rashid Yachts & Marina at Mina Rashid
A 0.04% reading only means something next to what it is building toward. The full project guide covers the development this record is tracking:

Sera 1 at Rashid Yachts & Marina: Two Low-Rise Waterfront Buildings
Sera 1 at Rashid Yachts & Marina holds 203 Emaar apartments in two low rise buildings near the marina.
View the Sera 1 at Rashid Yachts & Marina Project GuideConsidering an Early-Stage Entry?
Availability at Sera 1 shifts while the record is still at its first reading, and early-stage inventory is where the Emaar payment schedule stretches furthest. If this record is what brought you here, ask me what remains before the next release.
Ask About Remaining Availability on WhatsAppStage Record
Sera 1 at Rashid Yachts & Marina Build Stages, Mapped to the Inspections
Each stage below is tied to where it actually sits in this project's register entries, so nothing here describes work that has not been certified. Only the first two stages carry dates; the remaining three are listed with the entry that will date them.
Registration and Pre-Construction
Six months separate the 25 August 2025 registration of project 4031 from the 26 February 2026 construction start recorded against plot 653 at Madinat Dubai Almelaheyah.
Mobilisation and Enabling Works
The 02 June 2026 inspection entered the progress status as Enabling Works - Progressing with mobilisation ongoing, certifying 0.04% against the previous reading of 0%.
Substructure and Foundations
The next entry due on the Sera 1 register. No certified reading yet covers foundation work on plot 653, and this page will date the stage from the inspection that first records it.
Superstructure Across Both Buildings
The 02 June 2026 report registers Tower A at G+P+7 with 96 units and Tower B at G+P+8 with 107 units. Neither building carries a certified structural reading.
Finishing, Commissioning and Handover
The registered completion date for project 4031 is 30 November 2029, the Q4 2029 handover quarter. No part of this stage appears anywhere on the record yet.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Sera 1 at Rashid Yachts & Marina's own record.
Buyer Position
Tracking Your Position at Sera 1 at Rashid Yachts & Marina
This page is one of four project resources that together cover a Sera 1 at Rashid Yachts & Marina purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Sera 1 at Rashid Yachts & Marina Construction Updates
This page: the certified inspection record for Sera 1, from the 02 June 2026 reading onward.

Sera 1 at Rashid Yachts & Marina Golden Visa From 1 Bedroom
All three tiers at Sera 1 at Rashid Yachts & Marina, Emaar's 203-apartment release, qualify, so no second property is needed.
Read the Sera 1 at Rashid Yachts & Marina Golden Visa Guide
Sera 1 at Rashid Yachts & Marina: The 203-Apartment Escrow Record
Sera 1 at Rashid Yachts & Marina, DLD project 4031: 203 units, First Abu Dhabi Bank escrow, 0.04% certified June 2026.
Verify the Sera 1 at Rashid Yachts & Marina Escrow AccountApproaching Handover
Between 0.04% and Handover: What Sera 1 at Rashid Yachts & Marina Buyers Should Do Now
The distance between the June 2026 reading and the first structural entry on this record is closed by foundation work rather than by anything visible from the marina promenade, which makes this the stretch where paperwork protects a buyer more than photographs do. The Emaar schedule does not wait for the register either: the booking, October 2025 and April 2026 instalments have already fallen due, and the next fixed date is October 2026.
First, confirm that your instalments are reaching the registered trust account and nowhere else. The Sera 1 escrow account page sets out the First Abu Dhabi Bank P.J.S.C. account behind project 4031 and how certified progress releases what sits in it.
Second, line your own dates up against the schedule. From March 2027 the Emaar instalments carry construction-completion tags, so each of those payments is keyed to a certified reading of the kind recorded on this page; the full schedule is set out in the Sera 1 project guide.
Third, if residency is part of why you bought, settle eligibility now rather than at the end, because the title deed follows completion in November 2029. The Sera 1 Golden Visa guide covers how an off-plan purchase is treated.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Mina Rashid Structure
A build record reads differently next to what surrounds it. These three pages place the Sera 1 inspection history inside its listing set, its community and its developer:

Mina Rashid Properties for Sale
Browse waterfront apartments for sale at Rashid Yachts & Marina, with projects, prices and payment plans.
See Mina Rashid Properties for Sale
Mina Rashid Community Overview
Read the Rashid Yachts & Marina guide: Emaar's transformation of historic Port Rashid into a marina lifestyle community.
Explore the Mina Rashid Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Sera 1 at Rashid Yachts & Marina Construction Updates Frequently Asked Questions
Progress at Sera 1 is certified by an independently appointed inspector reporting to RERA, not by the developer. The Independent Progress Monitoring Report dated 02 June 2026 covers project 4031 on plot 653 at Madinat Dubai Almelaheyah, names MINA RASHID PROPERTIES L.L.C as the registered developer, and records 0.04% with the progress status entered as Enabling Works - Progressing. The same figure then carries onto the Dubai Land Department register. How that verification chain works across every project tracked here is set out once on the Dubai Construction Updates hub.
One. The record opens with the inspection of 02 June 2026, which certified 0.04% against a previous reading of 0%, a movement of 0.04 percentage points. Every inspection recorded after that date is added to the Sera 1 inspection timeline on this page, and the detail behind each reading is published as its own monthly update.
This page is updated when a new RERA inspection is recorded for project 4031, not on a fixed calendar. June 2026 is the first entry, and the progress status and inspection notes behind it appear in the Sera 1 June 2026 construction update. The split is deliberate: this page holds the history, the stage record and the pace arithmetic, while each monthly page holds one visit.
The Dubai Land Department register records 30 November 2029 as the completion date for project 4031, which places handover in Q4 2029. At the 02 June 2026 inspection the project stood at 0.04%, leaving 99.96 points of the certified scale across roughly 41 months. That registered date is the anchor every reading on this page is measured against, and any revision to it appears on the register before it appears anywhere else.
The 02 June 2026 report describes Sera 1 as a residential development of two buildings totalling 203 units: Tower A at G+P+7 with 96 units and Tower B at G+P+8 with 107 units. Those 203 apartments sit on plot 653 at Madinat Dubai Almelaheyah under DLD project number 4031. No built-up area figure is published on this page, because the area shown on the register is not labelled as one.
Construction start is recorded as 26 February 2026, six months after project 4031 was registered on 25 August 2025. The first certified reading followed 96 days later, on 02 June 2026, at 0.04%. A gap of that shape between start and first reading is what an opening stage of enabling works produces, because very little of the certified scale is allocated to it.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Sera 1 at Rashid Yachts & Marina construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.