Sera 2 Construction Update - June 2026

June 2026 Inspection Records Sera 2 at 0.04% Construction Progress in Rashid Yachts & Marina

Enabling works and site mobilization define activity at Sera 2, with the first certified reading of 0.04 percent recorded in the 02 June 2026 RERA inspection cycle.

Direct advisor access. Every message answered personally, never by a call center.

0.04%Construction Progress
02 June 2026Inspection Date
30 November 2029Expected Completion
4032DLD Project Number

Verified DLD Inspection Data

Sera 2 Construction Snapshot

A first 0.04 points against a previous reading of zero places Sera 2 at the opening of the enabling band, the stage where registration paperwork and payment protection decide far more than anything visible on the plot.

Project Name

Sera 2 by Emaar Properties

Project Number

4032

Project Status

Active

Construction Progress

0.04%

Inspection Date

02 June 2026

Construction Start

26 February 2026

Total Units

183 residential units

Total Built Area

19,537.50 sq m

Expected Completion

30 November 2029

Data source: RERA inspection conducted on 02 June 2026, tracked against DLD inspection records. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: September 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Sera 2 Construction Progress Summary

Between the recorded construction start on 26 February 2026 and the inspection of 02 June 2026, Sera 2 moved from a zero reading to 0.04%, and RERA files the project under the progress status Enabling Works - Progressing. The monitoring note for the visit is short and exact: mobilization on going. At this point the record measures preparation of plot 656, not built form.

Completed
  • Project registration on the DLD register, dated 14 August 2025
  • Construction start recorded against project 4032 on 26 February 2026
  • Project trust account opened with Abu Dhabi Commercial Bank
In Progress at 0.04%
  • Site mobilization, found ongoing at the 02 June 2026 inspection
  • Enabling works, carrying the RERA status Enabling Works - Progressing
  • Preparation of plot 656 in Madinat Dubai Almelaheyah
Ahead of Handover
  • Tower A (G+P+6, 83 units) and Tower B (G+P+7, 100 units)
  • Every RERA inspection cycle from 0.04% toward 100%
  • Handover from the registered completion date of 30 November 2029
Next inspectionPublished in the DLD project register after the next RERA site visit; this page updates with each cycle.
Completion target30 November 2029 per the current DLD record, roughly three and a half years from this inspection date.
Remaining distance99.96 percentage points separate the June 2026 reading from handover readiness.

Payment Linked Progress

What 0.04% Progress Means for Sera 2 Buyers

Dubai off plan plans tie instalments either to calendar dates or to certified construction stages, so a verified 0.04% tells you which obligations sit closest and which protections apply now rather than later. At this stage of Sera 2, four actions matter most.

Before Any Early Instalment

Verify the escrow account

Every payment made this early should reach only the DLD regulated escrow account registered for project 4032, held with Abu Dhabi Commercial Bank on the inspection record. Sera 2 escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before the Next Calendar Date

Map your SPA instalment schedule

Read how your sale and purchase agreement splits date driven instalments from construction linked ones, then set those triggers against a build that has only just left zero. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the certified milestones.

Within the Registration Window

Confirm the Oqood registration

An off plan unit is recorded in the interim register under Oqood, and the 4% DLD registration fee sits on top of the purchase price. At 0.04% this paperwork, not the site, is where a Sera 2 buyer is genuinely exposed, so confirm both are done in your name.

Every Cycle

Track the early cycles

A build registered to 30 November 2029 has many readings ahead, and the early ones set the pace the later ones are judged against. Sera 2 construction updates hub keeps the whole sequence in one place.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 0.04%?

Entering a project at the enabling stage trades certainty about the finished building for the longest instalment runway the plan offers, and the record you are judging is a registration record rather than a structural one. Every payment goes to the DLD-registered escrow account for project 4032, released against certified construction progress.

Entering Now at 0.04%
  • A certified start: works recorded from 26 February 2026 and inspected on 02 June 2026
  • The full runway to the registered completion date of 30 November 2029
  • Two launch instalment dates already passed, so a booking now opens from a different position
Typical Launch Entry
  • A price agreed before any inspection record exists at all
  • Construction risk carried from an empty plot through to handover
  • The longest instalment runway, priced at launch levels
AED 2.10M ≈ USD 572KStarting Price
10 / 70 / 20 Plan20% Due on Completion
From November 2029Expected Handover
Ask What Is Available at Sera 2

More than 20 units listed available on the project page as of this update; availability shifts between cycles. The instalment split above is the launch schedule of record, not a live offer: several of its dates have passed and the developer confirms the remaining balance at booking.

About the Development

Sera 2 Project Details

Sera 2 at Rashid Yachts and Marina residential buildings overlooking a landscaped pool courtyard in the waterfront community context Dubai. Presented by Tohid Fetrat.
Rashid Yachts & Marina · Emaar Properties

With the plot certified at 0.04% and enabling works under way, Sera 2 is an early stage development of 183 homes in two low rise buildings, Tower A at ground plus podium plus six floors and Tower B at ground plus podium plus seven. Starting prices: AED 2.10M ≈ USD 572K.

For buyers entering at this stage, the trade off is the longest wait in the community against the widest choice of layout, with handover expected from November 2029 and a registered completion date of 30 November 2029 on the current DLD record.

Sera 2 at Rashid Yachts & Marina Project Guide

Site Context This Cycle

Explore Sera 2 Location on Dubai Map

Sera 2 occupies plot 656 in Madinat Dubai Almelaheyah, toward the landward end of the Rashid Yachts & Marina peninsula beside the masterplan's water garden and close to the road approach that carries site traffic in and out. That position is exactly what this cycle is about: the inspection found a plot being mobilized, with access, hoarding and enabling activity the only things a visitor would see.

Because Rashid Yachts & Marina is a part built masterplan, with the marina, the promenade and earlier residential phases already standing, Sera 2 is being started inside a community that is already forming rather than on an empty shoreline, which changes the risk a buyer is taking on a build that runs to 2029: the address matures while the building rises. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Sera 2 at Rashid Yachts & Marina on Dubai Map

Buyer Resources for This Project

Investing in Sera 2 During Early Construction Progress

The enabling band is where registration, payment protection and residency planning are settled, long before finishing decisions arrive. Each resource below is matched to where Sera 2 stands right now.

Sera 2 by Emaar Properties in Rashid Yachts & Marina construction updates cover image featuring a project rendering of low-rise residential buildings overlooking a landscaped community lawn in Dubai - Presented by Tohid Fetrat
You Are Here

Sera 2 Construction Updates

This page: the verified June 2026 inspection record for Sera 2, from enabling works toward handover.

Sera 2 by Emaar Properties in Rashid Yachts & Marina Golden Visa concept with a Golden Visa card above a landscaped lawn, swimming pool, cabanas and residential buildings in Dubai - Presented by Tohid Fetrat

Sera 2 at Rashid Yachts & Marina Golden Visa: Entry Apartment Upward

Sera 2 at Rashid Yachts & Marina, 183 Emaar homes on plot 656, clears the threshold with all four typologies.

Read the Sera 2 Golden Visa Guide
Sera 2 by Emaar Properties in Rashid Yachts & Marina escrow account protection concept with shield and padlock icons above a swimming pool and residential buildings in Dubai - Presented by Tohid Fetrat

Sera 2 at Rashid Yachts & Marina: The Second Sera Escrow

Abu Dhabi Commercial Bank holds Sera 2 at Rashid Yachts & Marina escrow, DLD project 4032, 0.04% certified June 2026.

Verify the Sera 2 Escrow Account

Update Timeline

Other Sera 2 Construction Updates

June 2026 is the first certified reading published for Sera 2, so the timeline starts here. Every cycle that follows joins the hub below, reading by reading.

All Sera 2 Construction Updates

FAQs

Sera 2 Construction Progress in June 2026: Frequently Asked Questions

As of the RERA inspection conducted on 02 June 2026, Sera 2 stands at 0.04% construction progress in the DLD project register, filed under the progress status Enabling Works - Progressing.

Construction start is recorded against Sera 2 on 26 February 2026, and the 02 June 2026 visit is the first inspection to certify a figure: 0.04%, against a previous reading of 0%. The monitoring note for that visit records mobilization on going rather than any completed structural element.

The June 2026 record shows no slippage: registered completion remains 30 November 2029, the same month Emaar quotes buyers as handover, with 99.96 percentage points between the 02 June 2026 reading and full certification. How the inspection sequence runs from enabling works through to completion is covered on the Sera 2 construction updates hub.

Yes. Registered completion dates in the DLD project register can be revised between inspection cycles, and a build that runs for more than three years from enabling works has many more cycles in which a revision can appear. The date shown here reflects the register as of June 2026; any revision would surface in a later update on this cluster.

The independent progress monitoring report for 02 June 2026 records site mobilization ongoing and files the project under Enabling Works - Progressing. Nothing above ground is certified yet: the two registered buildings, Tower A at ground plus podium plus six floors with 83 units and Tower B at ground plus podium plus seven floors with 100 units, are still ahead of the record.

No. The launch calendar fixes the down payment and the first three instalments to calendar dates and ties the later ones to certified construction stages, so a 0.04% reading sits before the first construction linked trigger. Two of those launch dates, October 2025 and April 2026, fall before this inspection, which is why a booking made now opens from a different position in the schedule and the developer confirms the remaining balance at the point of booking.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the June 2026 inspection record for Sera 2 at Rashid Yachts & Marina correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts