Sera 2 at Rashid Yachts & Marina Construction Updates
The Certified Inspection Record for Plot 656 in Mina Rashid
Sera 2 recorded 0.04% construction progress at its 02 June 2026 RERA inspection, the first certified reading on a plot 656 build registered to November 2029.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Sera 2 at Rashid Yachts & Marina at a Glance
Sera 2 is Emaar Properties' 183-home water garden phase on plot 656 in Madinat Dubai Almelaheyah, and its construction record is deliberately short: three months and one week separate the recorded start of 26 February 2026 from the 0.04% certified on 02 June 2026. The DLD-registered anchors below are what a buyer at this stage is actually judging, because there is no built form to judge instead. One of them is worth pausing on. The registered completion date of 30 November 2029 agrees with the November 2029 handover Emaar quotes at the sales desk, so nothing on this page has to reconcile two competing finish dates, which is not the case on every long dated phase tracked here.
4032
Active
26 February 2026
183 residential units
19,537.50 sq m
30 November 2029 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Sera 2 at Rashid Yachts & Marina Construction Update Timeline
This record currently holds one certified reading. The RERA inspection of 02 June 2026 placed Sera 2 at 0.04% against a previous inspection logged at 0%, and the monitoring note filed with it describes mobilization on going rather than any completed element. That is why the single dot on the track below sits almost against the left cap, and why the row beneath it is the only row: every future inspection joins the same table as it publishes.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| June 2026 | 0.04% | 02 June 2026 | View the June 2026 update |
Pace Analysis
How Fast Sera 2 at Rashid Yachts & Marina Has Been Built
With one reading on file there is no curve to interpret yet, only a starting position and the distance still to cover. Both are worth stating precisely:
- 26 Feb 2026 start to the 02 Jun 2026 inspection: enabling works, 0% to 0.04%About 0.01 points per month
- 02 Jun 2026 to the registered date of 30 Nov 2029: 0.04% to 100%About 2.4 points per month required
Those two numbers do different jobs. The first is not really a pace: 0.04 points across roughly three months is the arithmetic of a plot being cleared and mobilized, and it would read the same on any build that had just been handed to a contractor. The second is the figure worth keeping. Roughly 42 months separate the June 2026 inspection from 30 November 2029, and closing 99.96 points inside that window asks for an average near 2.4 points per month sustained across the whole run. For an end user planning a 2029 move, that average is the yardstick every later reading gets measured against, and one weak cycle proves nothing on its own. For an investor holding a booking deposit against a 2029 completion, the useful question is not what 0.04% looks like but whether the second and third certified readings land above or below 2.4, because the first pair of intervals is where a long dated phase either establishes a rhythm or starts eating its own float. Neither judgement can be made from this page yet, which is the honest answer at 0.04%.
Get the Next Inspection Figure First
Tell me you are tracking Sera 2 at Rashid Yachts & Marina and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Sera 2 at Rashid Yachts & Marina at Mina Rashid
A reading this early tells you about the register rather than about the building. What the 183 homes on plot 656 are actually meant to become is set out in full here:

Sera 2 at Rashid Yachts & Marina, Built Around a Water Garden
Sera 2 at Rashid Yachts & Marina is Emaar's low rise resort phase of two buildings around a central water garden.
View the Sera 2 at Rashid Yachts & Marina Project GuideEntering Sera 2 at the Enabling Stage?
What remains with the developer at Sera 2 shifts between inspection cycles, and entering while the record still reads 0.04% buys the longest instalment runway the launch schedule offers. If the record on this page is what brought you here, ask for the current list before the choice of layout narrows.
Ask About Remaining Availability on WhatsAppStage Record
Sera 2 at Rashid Yachts & Marina Build Stages, Mapped to the Inspections
Only the first two stages below sit inside the certified record; the rest are pinned to the dates and construction completion triggers Emaar published with the launch schedule, so you can see where the 0.04% of June 2026 falls in the sequence.
Registration and Pre-Construction
Project 4032 entered the DLD register on 14 August 2025, and construction was recorded against it on 26 February 2026. Nothing in that six month window is measured as progress.
Site Activation and Enabling Works
The 02 June 2026 inspection found mobilization on going and filed the project as Enabling Works - Progressing: access, site setup and preparation of plot 656 rather than built form.
Substructure and Podium
The launch schedule's first construction linked instalment is tied to 10% construction completion and dated March 2027, which makes it the next milestone a Sera 2 buyer's calendar is actually pinned to.
Tower A and Tower B Superstructure
Tower A rises to ground plus podium plus six floors and 83 units, Tower B to ground plus podium plus seven and 100 units. The schedule marks this stretch at November 2027, April 2028 and August 2028.
Finishing, Water Garden and Handover
The closing 20% instalment is tied to 100% construction completion in November 2029, and the DLD register carries 30 November 2029 as the registered completion date for project 4032.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Sera 2 at Rashid Yachts & Marina's own record.
Buyer Position
Tracking Your Position at Sera 2 at Rashid Yachts & Marina
This page is one of four project resources that together cover a Sera 2 at Rashid Yachts & Marina purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Sera 2 at Rashid Yachts & Marina Construction Updates
This page: the verified inspection record for Sera 2, from enabling works toward 2029 handover.

Sera 2 at Rashid Yachts & Marina Golden Visa: Entry Apartment Upward
Sera 2 at Rashid Yachts & Marina, 183 Emaar homes on plot 656, clears the threshold with all four typologies.
Read the Sera 2 at Rashid Yachts & Marina Golden Visa Guide
Sera 2 at Rashid Yachts & Marina: The Second Sera Escrow
Abu Dhabi Commercial Bank holds Sera 2 at Rashid Yachts & Marina escrow, DLD project 4032, 0.04% certified June 2026.
Verify the Sera 2 at Rashid Yachts & Marina Escrow AccountApproaching Handover
Between 0.04% and Handover: What Sera 2 at Rashid Yachts & Marina Buyers Should Do Now
At this end of the record the things a buyer can still influence are all administrative, and every one of them gets harder to correct once instalments start moving. Two dates from the launch calendar, October 2025 and April 2026, already sit behind the June 2026 reading, so the position a purchase opens from is settled at the moment of purchase rather than later in the build. The three steps below belong to the next few weeks, not to 2029.
First, confirm that every payment reaches the DLD registered trust account for project 4032 and nothing else; the Sera 2 escrow account page carries the verification route and the bank named on the inspection record.
Second, separate the date driven instalments in your sale and purchase agreement from the construction linked ones, because the first construction trigger on the launch schedule is 10% construction completion in March 2027 and nothing before it depends on site progress at all. The Sera 2 June 2026 inspection report is the reading those later triggers get measured from.
Third, if the purchase is meant to carry residency, settle eligibility now through the Sera 2 Golden Visa guide rather than in 2029, since a title deed issued at handover puts the application on a different footing than a completed property does.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Mina Rashid Structure
A percentage on its own says nothing about the address it belongs to. These three pages place the 0.04% of June 2026 inside the community it sits in, the resale market it will eventually join, and the delivery record of the developer behind it:

Mina Rashid Properties for Sale
Browse waterfront apartments for sale at Rashid Yachts & Marina, with projects, prices and payment plans.
See Mina Rashid Properties for Sale
Mina Rashid Community Overview
Read the Rashid Yachts & Marina guide: Emaar's transformation of historic Port Rashid into a marina lifestyle community.
Explore the Mina Rashid Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Sera 2 at Rashid Yachts & Marina Construction Updates Frequently Asked Questions
Sera 2 is an active DLD registered project, number 4032, recorded at 0.04% construction progress at the RERA inspection of 02 June 2026 and filed under the progress status Enabling Works - Progressing. The inspection note for that visit reads mobilization on going. The record itself is in the inspection timeline above.
The inspection of 02 June 2026 recorded 0.04%, a rise of 0.04 points on a previous inspection logged at 0%, and the independent progress monitoring report for that visit certifies mobilization rather than any completed element. The full report is covered in the June 2026 Sera 2 construction update.
The DLD register carries 30 November 2029 as the registered completion date for project 4032, which agrees with the November 2029 handover Emaar Properties quotes to buyers. Measured from the 0.04% of 02 June 2026, that leaves 99.96 percentage points across roughly 42 months, an average near 2.4 points per month. The arithmetic is set out in the pace analysis above.
DLD registration records 183 residential units across two buildings: Tower A at ground plus podium plus six floors holding 83 units, and Tower B at ground plus podium plus seven floors holding 100 units. The mix runs from 1 bedroom apartments through to 3 bedroom townhouses.
Construction is recorded against project 4032 from 26 February 2026, six months and twelve days after the project entered the DLD register on 14 August 2025. The first tracked inspection followed on 02 June 2026 and certified 0.04%, roughly three months and one week after the recorded start.
Nothing above ground is certified yet. At 0.04% the record measures preparation of plot 656 in Madinat Dubai Almelaheyah: the monitoring report of 02 June 2026 found mobilization under way and RERA files the project under Enabling Works - Progressing. Tower A and Tower B both sit ahead of the record rather than inside it.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Sera 2 at Rashid Yachts & Marina construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.