Emaar Properties · Dubai Creek Harbour · Construction Update
Silva at Dubai Creek Harbour Construction Update - July 2026
July 2026 Inspection Records Silva at 10.16% Construction Progress in Dubai Creek Harbour
Foundation works at an advanced stage and substructure progressing define site activity at Silva, recorded at 10.16 percent in the 19 July 2026 RERA inspection.
Direct advisor access. Every message answered personally, never by a call center.
Verified DLD Inspection Data
Silva at Dubai Creek Harbour Construction Snapshot
A 3.86 point rise from the previous inspection reading of 6.3% puts Silva at 10.16% and inside the enabling and foundations band, the stage where escrow checks, Oqood registration, and the shape of the 80/20 plan matter more than any handover date.
Silva at Dubai Creek Harbour by Emaar Properties
3710
Active
10.16%
19 July 2026
31 August 2025
434 residential units
49,737.60 sq m
30 September 2029
Data source: RERA inspection conducted on 19 July 2026, reported in an Independent Progress Monitoring Report marked "Independently inspected and progress audited for RERA", tracked against DLD inspection records for project 3710; the DLD register shows the earlier 6.3% reading as the previous inspection without a date. The image at the top of this page is a developer rendering, not a site photograph. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: September 2026.
Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp
This Inspection Cycle
Silva at Dubai Creek Harbour Construction Progress Summary
The DLD register moved Silva from 6.3% to 10.16% at the 19 July 2026 inspection, a gain of 3.86 points; because the register shows that earlier reading without a date, the gain cannot be converted into a monthly pace. The RERA report places the work beneath the residential floors: enabling finished, foundations at an advanced stage, and substructure progressing across plot 296.
- Enabling works on plot 296, reported complete on 19 July 2026
- DLD project registration on 2 May 2025
- Construction start recorded on 31 August 2025
- Mobilization works continuing on site
- Foundation works at an advanced stage
- Substructure works progressing at different stages
- Main contract status recorded as progressing
- Ground, two podium levels, and 47 residential floors of the single tower
- Fit out of the 434 residential units, including the three bedroom townhouses at the tower's lower levels
- Remaining RERA inspection cycles toward completion on 30 September 2029
Payment Linked Progress
What 10.16% Progress Means for Silva Buyers
Silva's 80/20 plan names a construction percentage for every instalment from the fourth onward, starting at 40% completion, so a July 2026 reading of 10.16% shows how far the site still is from the first milestone-linked payment. At this stage of Silva, four actions matter most.
Verify the escrow account
Every Silva instalment should go only to the DLD regulated escrow account registered for project 3710, which the July 2026 inspection report lists with Emirates Islamic Bank P.J.S.C. as the trust account bank. Silva escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.
Map your SPA to the 80/20 milestones
Check how your sale and purchase agreement defines the milestone instalments: from the fourth payment, each is tied to a construction percentage between 40% and 100%, and the dates beside them are the developer's estimates. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the certified milestones.
Confirm your Oqood registration
At the foundations stage, the Oqood certificate issued through the Dubai Land Department is the registered record of an off plan purchase until the title deed follows completion. Confirm your Silva unit is registered under project 3710 once the booking payment and the 4% DLD registration fee are settled.
Track the climb to 40%
The fourth instalment waits on 40% construction completion, 29.84 points above the July 2026 reading, with March 2027 as the developer's estimate. The Silva construction updates hub logs each new DLD reading as it is published.
General framework, not legal advice: milestone definitions, registration steps, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.
Buying at 10.16%?
Entering Silva while foundations and substructure are under way trades a longer wait for payment timing: 60% of the price sits in instalments tied to construction milestones from 40% to 100%, against a Q3 2029 handover. Every payment goes to the DLD-registered escrow account for project 3710, released against certified construction progress.
- Enabling works complete and foundations advanced per the 19 July 2026 RERA report
- Remaining instalments tied to 40% to 100% construction milestones
- Launch schedule dates for August 2025, January 2026, and June 2026 already passed
- No inspection record yet: the register starts at zero
- Every instalment still ahead, spread over the full build
- Construction risk carried from the first excavation
10 units listed available on the project page as of this update; availability shifts between cycles.
About the Development
Silva at Dubai Creek Harbour Project Details

With enabling works complete and foundations at an advanced stage, Silva is an early stage Emaar tower of 434 units in Green Gate, its ground, two podium levels, and 47 floors still to rise, pairing 1 to 3 bedroom apartments with 3 bedroom townhouses. Starting prices: AED 1.79M ≈ USD 487K.
For buyers entering at this stage, the trade off is the longest wait to handover, expected in Q3 2029, against the largest share of milestone-linked payments still ahead, with completion registered for 30 September 2029 in the current DLD record.
Silva at Dubai Creek Harbour Project GuideSite Context This Cycle
Explore Silva at Dubai Creek Harbour Location on Dubai Map
Silva stands on plot 296, registered in the Al Khairan First area, in the Green Gate district of Dubai Creek Harbour beside Green Gate Park. The July 2026 inspection found the work concentrated in foundations and substructure for a single tower of basement, ground, two podium levels, and 47 floors, so the floors that will look over the park and toward the Creek are still ahead in the build sequence.
Dubai Creek Harbour is a partly built 7.4M sq m masterplan, with occupied residential phases alongside launches still under construction and the Dubai Metro Blue Line announced as an upcoming connection rather than an operating one. For a Silva buyer at 10.16%, the district and the tower mature on overlapping timelines toward 2029, which matters when weighing an owner-occupier plan against a rental one. See the project’s position on the interactive Dubai real estate map.

Buyer Resources for This Project
Investing in Silva During Foundation Stage Construction
In the enabling and foundations band, the decisions that matter are about payment protection and residency eligibility rather than handover. Each resource below is matched to where Silva stands after the July 2026 inspection.

Silva Construction Updates
This page: the verified July 2026 inspection record for Silva, from enabling works to substructure.

Silva at Dubai Creek Harbour Golden Visa From the 2 Bedroom Tier
Silva at Dubai Creek Harbour is a 434-unit Emaar tower in Green Gate; every type but the 1 bedroom apartment qualifies.
Check Silva Golden Visa Eligibility
Silva Escrow Account
Confirm the Emirates Islamic Bank escrow account for project 3710 before sending instalments during foundation works.
Verify Silva Escrow AccountUpdate Timeline
Other Silva Construction Updates
July 2026 is the first month in the Silva record on this site; each later RERA reading will be added here as it is published, so the tower can be followed from its foundations upward, reading by reading.
Where This Update Fits
Explore Silva Structure
This July 2026 report is one node in a wider record: the Dubai Creek Harbour listings Silva competes with, the masterplan around Green Gate, and the developer building the tower.

Dubai Creek Harbour Properties for Sale
Browse waterfront apartments, branded residences and penthouses for sale in Dubai Creek Harbour.
See Dubai Creek Harbour Properties for Sale
Dubai Creek Harbour: Emaar's Waterfront City With a Marina and Urban Beach
Dubai Creek Harbour is Emaar's waterfront city between Downtown Dubai and the Creek, planned for 48,500 homes with skyline views.
Explore the Dubai Creek Harbour Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileFAQs
Silva at Dubai Creek Harbour Construction Progress in July 2026: Frequently Asked Questions
As of the RERA inspection conducted on 19 July 2026, Silva at Dubai Creek Harbour stands at 10.16% construction progress in the DLD project register under project number 3710. The register lists the previous inspection at 6.3% without a date, so the July 2026 reading is 3.86 points higher.
Yes. The DLD register shows completion on 30 September 2029 as of the 19 July 2026 inspection, consistent with the Q3 2029 handover, and registered completion dates can be revised between inspection cycles. Any revision would appear in the DLD record first and in a later update in this series; how readings and dates are followed over time is covered on the Silva construction updates hub.
The Independent Progress Monitoring Report dated 19 July 2026 recorded mobilization works ongoing, enabling works completed, foundation works at an advanced stage, and substructure works progressing at different stages on plot 296, with the progress status listed as Main Contract, Progressing. The report describes no superstructure floors of the tower at this reading.
The DLD register shows the previous Silva inspection at 6.3% but gives no date for it, so the 3.86 point gain to 10.16% on 19 July 2026 cannot be spread over a known number of months. Later updates in this series will compare dated readings, which allows a like-for-like comparison from then on.
The fourth instalment, 10% of the price, is linked to 40% construction completion, with March 2027 given as the developer's estimated date. At the 19 July 2026 reading of 10.16%, the project was 29.84 points short of that trigger; the later instalments follow at 60%, 80%, 90%, and 100% construction completion.
Yes. Oqood is the Dubai Land Department's interim register for off plan sales, and it records a purchase under the project number long before any construction milestone is reached. With Silva at 10.16% on 19 July 2026 and handover expected in Q3 2029, the Oqood certificate under project 3710 is the buyer's registered record of the unit until the title deed is issued after completion.
A Question the FAQ Can Not Answer?

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is helping you read the July 2026 inspection record for Silva at Dubai Creek Harbour correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.