Silva at Dubai Creek Harbour Construction Updates

A Foundation-Stage Build Record Beside Green Gate Park

Silva at Dubai Creek Harbour reached 10.16% at the 19 July 2026 RERA inspection, a first dated reading with the podium and 47 floors still to rise.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

10.16%Construction Progress
19 July 2026Latest RERA Inspection
434 residential unitsTotal Units
Project 3710DLD Registration

Construction Snapshot

Silva at Dubai Creek Harbour at a Glance

Silva is Emaar's single 434-unit tower in the Green Gate district of Dubai Creek Harbour, registered as DLD project 3710 on plot 296. Just under eleven months separate its 31 August 2025 construction start from the 10.16% recorded on 19 July 2026, and the registered figures below are the anchors that record is measured against. Because Silva's three bedroom townhouses are built into the same tower rather than a separate villa cluster, one inspection percentage speaks for every unit type on sale here.

DLD Project Number

3710

Project Status

Active

Construction Start

31 August 2025

Total Units

434 residential units

Total Built-Up Area

49,737.60 sq m

Registered Completion Date

30 September 2029 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Silva at Dubai Creek Harbour Construction Update Timeline

Silva's record holds two readings so far: a previous inspection of 6.3%, which the DLD register lists without a date, and the 10.16% dated 19 July 2026, a step of 3.86 points. Because the two sit so close together on a track that runs to 100%, the earlier dot carries no label; the table beneath gives both readings, and the July 2026 row links the full monthly update built from that inspection report.

Inspection MonthConstruction ProgressInspection DateFull Update
July 202610.16%19 July 2026View the July 2026 update

Pace Analysis

How Fast Silva at Dubai Creek Harbour Has Been Built

With the earlier 6.3% reading undated, Silva's record cannot yet produce an inspection-to-inspection pace. The figures below are labelled arithmetic benchmarks built from the registered dates, not measured velocity:

  • 31 Aug 2025 start to 19 Jul 2026: 0% to 10.16%, arithmetic start average over about 10.6 monthsAbout 1.0 points per month
  • Previous Inspection to 19 Jul 2026: 6.3% to 10.16%, earlier reading undated in the DLD registerUp 3.86 points, no monthly rate
  • 19 Jul 2026 to 30 Sep 2029 DLD completion: 10.16% to 100%, required average over about 38.4 monthsAbout 2.3 points per month

Read together, the two benchmarks frame a question rather than answer it. About 1.0 points per month is what 10.16% works out to across the months since the August 2025 start, a stretch the July 2026 report covers with enabling, foundations, and substructure, and no superstructure floors described yet. About 2.3 points per month is the straight-line average the remaining 89.84 points would need to reach 100% by the 30 September 2029 completion date in the DLD register. Neither number is a forecast, and the gap between them is not a delivery signal on its own. The first dated pair of Silva inspections will produce a measured rate, and that is the figure an investor timing the 40% instalment trigger, or an end user planning a Q3 2029 move, should wait to see.

Get the Next Inspection Figure First

Tell me you are tracking Silva at Dubai Creek Harbour and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Silva at Dubai Creek Harbour at Dubai Creek Harbour

A 10.16% reading only means something next to the finished building it is measured toward. The Silva project guide covers what this record is tracking:

Silva at Dubai Creek Harbour by Emaar Properties residential tower exterior overlooking landscaped surroundings and Dubai skyline at sunset in Dubai - Presented by Tohid Fetrat

Silva at Dubai Creek Harbour in Green Gate's Park District

Silva at Dubai Creek Harbour sets 434 apartments and three bedroom townhouses in Green Gate, a park-focused district with sports grounds.

View the Silva at Dubai Creek Harbour Project Guide

Considering an Early-Stage Entry?

Emaar releases and sells Silva inventory throughout the build, so what is available changes between inspections. If the foundation-stage record on this page is what brought you here, ask me for current availability before choosing a tier or a view.

Ask About Remaining Availability on WhatsApp

Stage Record

Silva at Dubai Creek Harbour Build Stages, Mapped to the Inspections

Only the first two stages below have entered Silva's record; the other three are tied to the construction percentages that Emaar's 80/20 plan attaches to instalments four to eight, so each future inspection can be placed against them as it is published.

May 2025 to Aug 2025

Registration and Site Start

Project 3710 was entered in the DLD register on 02 May 2025, and construction formally started on 31 August 2025 on plot 296 in Al Khairan First.

Current PhaseAug 2025 onward, 10.16% at last reading

Enabling, Foundations, and Substructure

At 10.16% on 19 July 2026, enabling works were reported complete, foundations were at an advanced stage, and substructure works were progressing, up from an undated 6.3%.

Not yet recorded, 40% milestone

Podium and Tower Frame

Ground, two podium levels, and 47 floors are still to rise; the fourth instalment is tied to 40% completion, which Emaar's schedule estimates for March 2027.

Not yet recorded, 60% to 90% milestones

Enclosure, Fit-Out, and Townhouse Levels

Facade and interiors for all 434 units, including the townhouses at the tower's lower levels; instalments five to seven attach to 60%, 80%, and 90%.

Registered for 30 Sep 2029

Completion and Handover

The final 20% instalment is tied to 100% completion, and the DLD register shows 30 September 2029, consistent with the Q3 2029 handover.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Silva at Dubai Creek Harbour 's own record.

Buyer Position

Tracking Your Position at Silva at Dubai Creek Harbour

This page is one of four project resources that together cover a Silva at Dubai Creek Harbour purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Silva at Dubai Creek Harbour by Emaar Properties in Dubai Creek Harbour construction updates cover image featuring a project rendering of a private terrace overlooking landscaped community and skyline views in Dubai - Presented by Tohid Fetrat
You Are Here

Silva at Dubai Creek Harbour Construction Updates

This page: the verified inspection record for Silva, from the 31 August 2025 start to handover.

Silva at Dubai Creek Harbour by Emaar Properties in Dubai Creek Harbour Golden Visa card graphic above an outdoor community pavilion with landscaped surroundings and residential tower backdrop in Dubai - Presented by Tohid Fetrat

Silva at Dubai Creek Harbour Golden Visa From the 2 Bedroom Tier

Silva at Dubai Creek Harbour is a 434-unit Emaar tower in Green Gate; every type but the 1 bedroom apartment qualifies.

Read the Silva at Dubai Creek Harbour Golden Visa Guide
Silva at Dubai Creek Harbour by Emaar Properties in Dubai Creek Harbour escrow account protection graphic with shield and padlock above a landscaped community park and residential towers in Dubai - Presented by Tohid Fetrat

Silva at Dubai Creek Harbour Escrow Account

See how Silva instalments held at Emirates Islamic Bank track construction milestones from 40% onward.

Verify the Silva at Dubai Creek Harbour Escrow Account

Approaching Handover

Between 10.16% and Handover: What Silva at Dubai Creek Harbour Buyers Should Do Now

At 10.16% on 19 July 2026, Silva sits 29.84 points below the 40% completion that its fourth instalment is tied to, a milestone Emaar's schedule estimates for March 2027. Every instalment from the fourth onward falls due when a construction percentage is reached rather than on a fixed date, so the three checks below belong before the record reaches 40%, not after the payment request arrives.

First, before any further transfer, confirm the Emirates Islamic Bank escrow account registered to project 3710; the Silva escrow account page explains how to check it against the DLD record.

Second, map your sale and purchase agreement against the milestones: Silva instalments attach to 40%, 60%, 80%, 90%, and 100% completion, and each new reading in the timeline above shows how far away the next one is.

Third, if residency is part of the plan, check your tier in the Silva Golden Visa eligibility guide: the one bedroom at AED 1.79M ≈ USD 487K sits below the AED 2M ≈ USD 545K property threshold on its own.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Dubai Creek Harbour Structure

Silva's 10.16% reading sits inside a 7.4M sq m masterplan where Emaar has several launches under construction at once. These three pages put that record in its market, community, and developer context:

Dubai Creek Harbour Properties for Sale waterfront community view with Creek waters modern residential towers and Downtown Dubai skyline Presented by Tohid Fetrat

Dubai Creek Harbour Properties for Sale

Browse waterfront apartments, branded residences and penthouses for sale in Dubai Creek Harbour.

See Dubai Creek Harbour Properties for Sale
Dubai Creek Harbour skyline with The Grand by Emaar and Dubai Creek Tower – luxury waterfront community with marina and skyline views, presented by Tohid Fetrat.

Dubai Creek Harbour: Emaar's Waterfront City With a Marina and Urban Beach

Dubai Creek Harbour is Emaar's waterfront city between Downtown Dubai and the Creek, planned for 48,500 homes with skyline views.

Explore the Dubai Creek Harbour Community
Emaar Properties developer showcasing Downtown Dubai skyline with Burj Khalifa and surrounding residential and commercial towers at dusk Presented by Tohid Fetrat

Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities

Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.

View the Emaar Properties Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Silva at Dubai Creek Harbour Construction Updates Frequently Asked Questions

Silva at Dubai Creek Harbour is an active DLD-registered project (number 3710) in its foundation and substructure stage, recorded at 10.16% at the RERA inspection of 19 July 2026, with enabling works complete and the main contract listed as progressing. Every reading so far is in the Silva inspection timeline above.

The 19 July 2026 inspection recorded 10.16% construction progress for Silva, up 3.86 points from a previous inspection reading of 6.3% that the DLD register lists without a date. Foundations were at an advanced stage and substructure works were progressing on plot 296; the full reading is covered in the Silva July 2026 construction update.

Handover at Silva at Dubai Creek Harbour is expected in Q3 2029, and the DLD register records a completion date of 30 September 2029 for project 3710 as of the 19 July 2026 inspection, which put the tower at 10.16%. The registered date has not lapsed, and this page's record is updated as each new inspection is published.

Silva at Dubai Creek Harbour includes 434 residential units in a single tower of basement, ground, two podium levels, and 47 floors, combining one to three bedroom apartments with three bedroom townhouses at the tower's lower levels. Layouts for each tier are in the Silva at Dubai Creek Harbour project guide.

Construction at Silva at Dubai Creek Harbour started on 31 August 2025, about four months after the project's 02 May 2025 DLD registration. The first dated reading on this record is 10.16% from the 19 July 2026 inspection; the earlier 6.3% previous inspection appears in the DLD register without a date.

Silva's record does not yet support a measured monthly pace, because the 6.3% previous inspection carries no date. As arithmetic benchmarks only, 10.16% on 19 July 2026 averages about 1.0 points per month over the 10.6 months since the 31 August 2025 start, and reaching 100% by the 30 September 2029 DLD completion date would need about 2.3 points per month across the remaining 38.4 months. The method is set out in the pace analysis above.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Silva at Dubai Creek Harbour construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.