Emaar Properties · Emaar Beachfront
South Beach at Emaar Beachfront Construction Updates
The Closed Build Record of Tower 1 on the Dubai Harbour Beachfront
South Beach at Emaar Beachfront reached a 100% DLD register reading on 23 February 2023, closing the build record of this furnished tower above a shared podium.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
South Beach at Emaar Beachfront at a Glance
South Beach is Emaar's 270-apartment holiday-home tower at Emaar Beachfront, and the Dubai Land Department files it as Tower 1 of project 2094, registered under the name "Marina Vista". Its podium partner on that one entry is the taller tower sold as Marina Vista, so every register figure below speaks for both buildings at once. Construction started on 27 December 2018 and the register read 100% on 23 February 2023: this is the closed record of a Ready building rather than a build still in progress, and on Dubai REST it surfaces only under the number 2094.
2094 (register name Marina Vista)
Finished (DLD register)
27 December 2018
270 apartments (South Beach)
60,083.29 sq m
30 March 2023 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
South Beach at Emaar Beachfront Construction Update Timeline
The register record behind South Beach is short: one dated reading, 100% on 23 February 2023, and an earlier 94.06% that Dubai REST shows only as the previous inspection, with no date attached. The track below therefore carries a single dot at the finish line, and the table holds one row, linked to the February 2023 update that sets out that inspection in full.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| February 2023 | 100% | 23 February 2023 | View the February 2023 update |
Reading the dates: the DLD-registered completion date for project 2094 is 30 March 2023, and the register had already read 100% on 23 February 2023, 35 days before it. With the registration now listed as Finished, that date belongs to a completed-building record rather than an open deadline, and the building is sold today as Ready.
Pace Analysis
How Fast South Beach at Emaar Beachfront Has Been Built
Pace cannot be measured the usual way here, because the only earlier reading on the South Beach register carries no date. What the record does fix is a set of spans between dated events:
- Undated previous reading to 23 Feb 2023: 94.06% to 100%+5.94 points, no monthly rate
- Construction start 27 Dec 2018 to the 100% reading1,519 days, about 50 months
- DCD 21 Sep 2022 and BCC 9 Dec 2022 to the 100% reading155 and 76 days before it
- 100% reading to the 30 Mar 2023 registered completion35 days ahead of the date
Read together, those spans describe a close-out rather than a race. Civil Defence approval arrived 155 days before the final reading and the Building Completion Certificate 76 days before it, so by the time the register moved from 94.06% to 100% the approvals that define a finished building were already in hand, and what the February 2023 visit still found under way was finishing and cleaning. A 5.94 point step with no start date cannot be turned into points per month, and this page does not pretend otherwise. For an end user the useful conclusion is that the tower was recorded complete inside its registered window; for an investor, that the reading is now 1,316 days old, which makes today's register entry and the condition of the specific apartment the figures that matter.
Get the Next Inspection Figure First
Tell me you are tracking South Beach at Emaar Beachfront and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About South Beach at Emaar Beachfront
A 100% register reading only matters in the context of what was delivered. The project guide covers the finished apartments this record stands behind:

South Beach at Emaar Beachfront: Emaar's First Holiday-Home Tower
South Beach at Emaar Beachfront is an Emaar tower of 270 apartments with private beach access and an infinity-edge pool.
View the South Beach at Emaar Beachfront Project GuideConsidering a Ready Entry?
South Beach is listed with limited units available, and on a completed building the choice is between the specific apartments on the market. If the record on this page is what brought you here, ask me what is available before the remaining options narrow further.
Ask About Remaining Availability on WhatsAppStage Record
South Beach at Emaar Beachfront Build Stages, Mapped to the Inspections
Each stage below is pinned to the dated register and inspection events South Beach actually passed through, from registration in October 2018 to the 100% reading of February 2023, so the gaps in the record show as clearly as the dates.
Registration and Site Start
Project 2094 was registered on 28 October 2018 and construction started on 27 December 2018, 60 days later, for both towers on plot 3659.
Shared Podium and Foundations
The shared podium, recorded in the inspection report as G+1UG+1M+6P, carries both towers; no dated register reading from this stage appears in the South Beach record.
Tower 1 Structure and Envelope
South Beach's 27 residential floors, G+27F+1LR+R in the inspection report, belong to this stretch, which the record covers only through the undated 94.06% register reading.
Civil Defence and Completion Approvals
DCD (Dubai Civil Defence) approval was received on 21 September 2022 and the Building Completion Certificate by DDA on 9 December 2022, per the inspection report.
Completion, Close-Out and Ready Handover
The 23 February 2023 reading recorded 100%, with every DEWA meter connected and only finishing and cleaning left on site; the register now reads Finished and handover status is Ready.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on South Beach at Emaar Beachfront's own record.
Buyer Position
Tracking Your Position at South Beach at Emaar Beachfront
This page is one of four project resources that together cover a South Beach at Emaar Beachfront purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

South Beach at Emaar Beachfront Construction Updates
This page: the register and inspection record for South Beach, Tower 1 of project 2094.

South Beach at Emaar Beachfront Golden Visa: One Apartment Is Enough
South Beach at Emaar Beachfront, Emaar's 270-apartment holiday-home tower, qualifies at all three layouts on a single title.
Read the South Beach at Emaar Beachfront Golden Visa Guide
South Beach at Emaar Beachfront Escrow: Where Instalments Were Held
Every instalment toward South Beach at Emaar Beachfront, a finished Emaar release, was paid into one Dubai Islamic Bank escrow account.
Verify the South Beach at Emaar Beachfront Escrow Account
South Beach at Emaar Beachfront Snagging for a Furnished Holiday-Home Tower
South Beach at Emaar Beachfront has 270 furnished apartments over 27 residential floors, on a podium shared with a taller tower.
Book South Beach at Emaar Beachfront SnaggingApproaching Handover
Between 100% and Handover: What South Beach at Emaar Beachfront Buyers Should Do Now
South Beach has no construction gap left to close: the register read 100% in February 2023 and the handover status is Ready, so preparation now runs on your own timetable rather than the developer's. On a ready purchase there is no build period to absorb these checks, which is why the three steps below belong before you sign, not after the transfer is arranged.
First, arrange an independent inspection of the actual apartment, its finishes, systems and furniture inventory; the South Beach snagging page explains what a ready, furnished unit should be checked for.
Second, see how buyer money was protected while the tower was built on the South Beach escrow account page, and settle how your own payment will be handled at transfer.
Third, if residency is part of the plan, check eligibility through the South Beach Golden Visa guide before signing, since eligibility rests on the value shown on the title deed.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Emaar Beachfront Structure
A closed build record says what was finished; the pages below show what surrounds it, placing South Beach's completed tower in its listing, community and developer context:

Emaar Beachfront Properties for Sale
Browse apartments and penthouses for sale in Emaar Beachfront, Dubai's private beach community in Dubai Harbour.
See Emaar Beachfront Properties for Sale
Emaar Beachfront: A Private-Beach Island Community Inside Dubai Harbour
Emaar Beachfront holds 27 residential towers and around 10,000 homes along a private beachfront, with two marinas, retail and dining.
Explore the Emaar Beachfront Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
South Beach at Emaar Beachfront Construction Updates Frequently Asked Questions
South Beach at Emaar Beachfront is a completed building: Dubai REST lists its registration, project 2094, as Finished, and the RERA inspection report of 23 February 2023 gave the Progress Status as Completed alongside a DLD register reading of 100% on the same date. Finished is the register's closed status for the whole registration, Completed is the inspector's verdict on the building works, and the handover status for buyers today is Ready. The full record is in the inspection timeline above.
Dubai REST shows "Marina Vista" because South Beach is Tower 1 of DLD project 2094, which was registered on 28 October 2018 under that name. Its second, taller building is the one marketed under the Marina Vista name, and because the two rise from one shared podium the register keeps a single entry, one status and one set of readings for the pair. A search for "South Beach" on Dubai REST finds nothing useful; searching project number 2094 brings up the record this page tracks.
The South Beach record holds one dated reading: 100% on 23 February 2023, 5.94 points above the 94.06% the register held before it. Dubai REST shows that earlier figure only as the previous inspection, with no date, so it supports the delta but not a timeline row, and it yields no monthly rate. The dated reading is set out in the South Beach February 2023 construction update.
The RERA inspection report of 23 February 2023 records the Building Completion Certificate as received by DDA on 9 December 2022 and DCD (Dubai Civil Defence) approval as received on 21 September 2022, 76 and 155 days before the 100% register reading. Both entries belong to the whole project 2094 registration, so they cover South Beach together with the second tower rather than being issued for South Beach alone.
The 30 March 2023 date for South Beach is the completion date entered when project 2094 was registered, and it stays on the register as a record after the event. The building reached 100% before it, on 23 February 2023, 35 days earlier, and the entry now reads Finished. The date is history rather than a pending deadline, and the handover status buyers deal with today is Ready.
South Beach at Emaar Beachfront contains 270 apartments, split across 1, 2 and 3 bedroom types and specified as fully furnished in the developer brochure. The inspection report of 23 February 2023 describes Tower 1 as G+27F+1LR+R, which the developer's plans present as 27 residential floors above a podium shared with the second tower. No built-up area is given on this page, because no measured figure for Tower 1 on its own is available in the record.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the South Beach at Emaar Beachfront construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.