Sunridge by Emaar in Rashid Yachts & Marina construction updates cover image featuring a project rendering of landscaped swimming pools, palm trees and modern residential buildings in Dubai - Presented by Tohid Fetrat

Emaar · Rashid Yachts & Marina

Sunridge at Rashid Yachts & Marina Construction Updates

A Low-Rise Build Record Beside the Canal Pool at Mina Rashid

Sunridge reached 100% at its 17 March 2026 RERA inspection, so only the Feb 2027 handover, not construction, separates this canal-pool building from its buyers.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

100%Construction Progress
17 March 2026Latest RERA Inspection
130 residential unitsTotal Units
Project 2678DLD Registration

Construction Snapshot

Sunridge at Rashid Yachts & Marina at a Glance

Sunridge is Emaar's 130-apartment building on the Burj View axis of Rashid Yachts & Marina, registered with the DLD as project 2678 on 12 June 2023. Construction started on 30 September 2023, and the RERA inspection of 17 March 2026 recorded 100%, a build of about 29.5 months from start to full reading. At B+G+5+R, a basement, ground floor, five upper levels, and a roof, it is a compact block in a masterplan where the other apartment buildings listed around it are still sold off plan, so its record closes while theirs has barely begun.

DLD Project Number

2678

Project Status

Finished

Construction Start

30 September 2023

Total Units

130 residential units

Total Built-Up Area

11,981.15 sq m

Registered Completion Date

March 2026

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Sunridge at Rashid Yachts & Marina Construction Update Timeline

The Sunridge record carries a single dated reading: 100% at the RERA inspection of 17 March 2026, about 29.5 months after the 30 September 2023 construction start. The register also shows a previous reading of 97.88% but gives it no date, so it enters the pace figures below as a step rather than as a dot on the track. The one dot marks that March 2026 inspection, and the table row links its full monthly update.

Inspection MonthConstruction ProgressInspection DateFull Update
March 2026100%17 March 2026View the March 2026 update

Pace Analysis

How Fast Sunridge at Rashid Yachts & Marina Has Been Built

With one dated reading on record, the Sunridge pace can only be read across the whole build, from the 30 September 2023 start to the 100% recorded on 17 March 2026:

  • Sep 2023 to Mar 2026: whole build, construction start to 100%About 3.4 points per month
  • Final register step: undated 97.88% to 100% on 17 Mar 20262.12 points, no dated interval
  • Mar 2026 to Feb 2027: recorded completion to scheduled handover0 points left to build

There is no curve inside this record, only its two ends, and the ends are the finding. The Sunridge launch payment schedule tied its final instalment to an estimated 100% construction completion in Feb 2027; the register recorded 100% on 17 March 2026, about eleven months earlier, with the Civil Defence certificate dated 08 December 2025 and the building completion certificate dated 29 December 2025 already on file. Over roughly 29.5 months for a basement, ground floor, five upper levels, and a roof, that averages about 3.4 points a month. An investor reads it as a build that finished ahead of its own estimate; an end user reads it as a building with no construction risk left, where the open question before the Feb 2027 handover is the handover programme, not the site.

Get the Next Inspection Figure First

Tell me you are tracking Sunridge at Rashid Yachts & Marina and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Sunridge at Rashid Yachts & Marina at Mina Rashid

The 100% reading of 17 March 2026 only matters next to what it delivers. The full project guide sets out what the Sunridge record on this page has been tracking toward:

Sunridge at Rashid Yachts & Marina by Emaar private balcony overlooking resort style pools palm trees and modern residences in Dubai - Presented by Tohid Fetrat

Sunridge at Rashid Yachts & Marina, Between the Park and Canal Pool

Sunridge at Rashid Yachts & Marina holds 130 Emaar apartments of one and two bedrooms near the community park and promenade.

View the Sunridge at Rashid Yachts & Marina Project Guide

Considering a Near-Handover Entry?

Sunridge is listed with limited units available, and what remains can narrow in the months between a recorded completion and the Feb 2027 handover. If the record on this page is what brought you here, ask me for current availability before the remaining choice of layouts and floors shrinks further.

Ask About Remaining Availability on WhatsApp

Stage Record

Sunridge at Rashid Yachts & Marina Build Stages, Mapped to the Inspections

Each stage below is pinned to a date the Sunridge record actually carries, from DLD registration on 12 June 2023 to the 100% inspection of 17 March 2026, rather than to a generic construction sequence.

Jun 2023 to Sep 2023

Registration and Construction Start

Project 2678 was registered with the DLD on 12 June 2023, and the register dates the Sunridge construction start to 30 September 2023, about three and a half months later.

Sep 2023 to late 2025

Structure, Blockwork, and Finishes

The RERA report records a concrete frame with block walls, finished inside and out, across basement, ground, five levels, and roof; no interim reading in this window carries a date.

Dec 2025

Civil Defence and Completion Certificates

Per the RERA report, the Civil Defence certificate is dated 08 December 2025 and the building completion certificate, issued by Ports, Customs and Free Zone Corporation, 29 December 2025.

17 Mar 2026 at 100%

Construction Recorded Complete

The RERA inspection of 17 March 2026 recorded 100% with a Completed progress status, water, electrical and gas meters connected, and snagging works listed as ongoing on that date.

Current PhaseMar 2026 to Feb 2027 handover

Handover Preparation

With nothing left to build, the Sunridge record now runs from the 100% reading of 17 March 2026 toward the scheduled Feb 2027 handover; no handover is recorded yet.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Sunridge at Rashid Yachts & Marina's own record.

Buyer Position

Tracking Your Position at Sunridge at Rashid Yachts & Marina

This page is one of four project resources that together cover a Sunridge at Rashid Yachts & Marina purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Sunridge by Emaar in Rashid Yachts & Marina construction updates cover image featuring a project rendering of landscaped swimming pools, palm trees and modern residential buildings in Dubai - Presented by Tohid Fetrat
You Are Here

Sunridge at Rashid Yachts & Marina Construction Updates

This page: the Sunridge register record from the September 2023 start to 100% in March 2026.

Sunridge by Emaar in Rashid Yachts & Marina Golden Visa graphic with a gold visa card above a landscaped swimming pool and modern residences in Dubai - Presented by Tohid Fetrat

Sunridge at Rashid Yachts & Marina Golden Visa: The Two Bedroom

Sunridge at Rashid Yachts & Marina, 130 Emaar apartments, qualifies only at the 2 bedroom; the 1 bedroom starts below.

Read the Sunridge at Rashid Yachts & Marina Golden Visa Guide
Sunridge by Emaar in Rashid Yachts & Marina escrow account graphic with shield and padlock icons above a landscaped community plaza and residential buildings in Dubai - Presented by Tohid Fetrat

Sunridge at Rashid Yachts & Marina: A Fully Certified Marina Escrow

Sunridge at Rashid Yachts & Marina read 100% certified March 2026; DLD project 2678 held 130 units' money at Emirates Islamic.

Verify the Sunridge at Rashid Yachts & Marina Escrow Account
Sunridge by Emaar in Rashid Yachts & Marina snagging inspection graphic above a furnished balcony overlooking landscaped residential buildings in Dubai - Presented by Tohid Fetrat

Sunridge at Rashid Yachts & Marina Snagging Beside the Canal Pool

Sunridge at Rashid Yachts & Marina is a B+G+5+R Emaar building of 130 apartments beside the community park and canal pool.

Book Sunridge at Rashid Yachts & Marina Snagging

Approaching Handover

Between 100% and Handover: What Sunridge at Rashid Yachts & Marina Buyers Should Do Now

At Sunridge the build figure has nowhere left to climb: the 17 March 2026 inspection put it at 100%, so the months before the Feb 2027 handover are about buyer readiness rather than site progress. A handover notice usually leaves only a short window to arrange the appointment, which is why the three steps below are worth settling before that notice arrives.

First, plan an independent inspection of your apartment ahead of the Feb 2027 handover so any defects are on record before you accept it; the Sunridge apartment snagging guide explains timing and scope.

Second, check that anything still payable before handover goes to project 2678's registered trust account at Emirates Islamic Bank, using the Sunridge escrow account page, so the final payment follows the certified record rather than a request.

Third, if you hold or are weighing a 2 bedroom unit, settle residency eligibility before keys through the Sunridge Golden Visa guide, because the move from Oqood registration to title deed at handover affects which documents the application relies on.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Mina Rashid Structure

A finished building is only half the picture; around Sunridge, the other apartment buildings listed in Rashid Yachts & Marina are still off plan. These three pages set its record in market, community, and developer context:

Waterfront apartment buildings with modern architecture overlooking a marina filled with luxury yachts at Rashid Yachts and Marina by Emaar in Dubai Presented by Tohid Fetrat

Mina Rashid Properties for Sale

Browse waterfront apartments for sale at Rashid Yachts & Marina, with projects, prices and payment plans.

See Mina Rashid Properties for Sale
Luxury yachts at Rashid Yachts and Marina waterfront community with modern residences and marina promenade in Mina Rashid Dubai Presented by Tohid Fetrat

Mina Rashid Community Overview

Read the Rashid Yachts & Marina guide: Emaar's transformation of historic Port Rashid into a marina lifestyle community.

Explore the Mina Rashid Community
Emaar Properties developer showcasing Downtown Dubai skyline with Burj Khalifa and surrounding residential and commercial towers at dusk Presented by Tohid Fetrat

Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities

Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.

View the Emaar Properties Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Sunridge at Rashid Yachts & Marina Construction Updates Frequently Asked Questions

Sunridge at Rashid Yachts & Marina, DLD project 2678, is listed as Finished in the DLD project register, and the RERA inspection of 17 March 2026 recorded it at 100% with a progress status of Completed. That reading was about six months old at this page's September 2026 update, and handover remains scheduled for Feb 2027. The dated record is in the Sunridge inspection timeline above.

The RERA inspection of 17 March 2026 recorded Sunridge at 100% construction progress, 2.12 points above the previous register reading of 97.88%, which the DLD record shows without a date. Because only the March 2026 figure is dated, no monthly rate can be drawn from that final step. The report behind the reading is summarised in the Sunridge March 2026 construction update.

The completion field in the DLD project register for Sunridge, project 2678, holds a system placeholder rather than a real date, so this page quotes no registered completion date. What the record does date is the 100% reading of 17 March 2026 and the building completion certificate of 29 December 2025, while handover is scheduled for Feb 2027. With no registered date on file, there is no lapsed deadline to measure the Sunridge build against.

Sunridge includes 130 residential units according to the DLD project register, all of them 1 and 2 bedroom apartments, in a B+G+5+R building: a basement, a ground floor, five upper levels, and a roof, as described in the RERA inspection report of 17 March 2026. The register carries no labelled built-up area figure for project 2678, so none is quoted here.

Construction at Sunridge started on 30 September 2023, according to the DLD project register, about three and a half months after project 2678 was registered on 12 June 2023. The first dated reading in the Sunridge record came at the RERA inspection of 17 March 2026, which already recorded 100%.

Sunridge took about 29.5 months from its 30 September 2023 construction start to the 100% reading of 17 March 2026, an average of about 3.4 points per month across the whole build. The launch payment schedule had estimated 100% construction completion for Feb 2027, so the recorded finish came about eleven months ahead of that estimate. The working is in the Sunridge pace analysis above.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Sunridge at Rashid Yachts & Marina construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.