The Highgrove by Ellington in Meydan Horizon construction updates cover image featuring a project rendering of the tall residential tower beside landscaped waterways in Dubai - Presented by Tohid Fetrat

Ellington · Meydan Horizon

The Highgrove Construction Updates

The Register Record of a Lagoon-Side Tower in Meydan Horizon, From Groundworks Toward Q4 2028

The Highgrove read 7% on the DLD register at the 6 August 2026 inspection, an opening record of enabling, piling and foundation works in Meydan Horizon.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

7%Construction Progress
6 August 2026Latest RERA Inspection
291 residential unitsTotal Units
Project 4037DLD Registration

Construction Snapshot

The Highgrove at a Glance

The Highgrove is Ellington's 291-residence tower in Meydan Horizon, entered on the Dubai Land Department register as project 4037 with the building description G + 4P + 31F + R + UR. The register dates its construction start to 1 September 2025 and its registration to 12 September 2025, and the reading recorded on 6 August 2026 stood at 7%, roughly eleven months after that start. With enabling, piling and foundation works as the recorded activity on that date, all four podium levels and all 31 residential floors were still to rise, so the anchors below describe a record in its opening chapter rather than a visible frame.

DLD Project Number

4037

Project Status

Active

Construction Start

1 September 2025

Total Units

291 residential units

Total Built-Up Area

27,470.59 sq m

Registered Completion Date

31-12-2028 (DLD); handover expected Q4 2028

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

The Highgrove Construction Update Timeline

The Highgrove's record holds one dated reading so far: 7% on the DLD register, recorded on 6 August 2026, when the RERA report listed enabling, piling and foundation works as progressing. The register also shows a previous inspection at 4.31% but gives no date for it, so that figure sits on the track below as an undated dot rather than a table row, and the 2.69 points between the two readings cannot be spread over any period. Each new dated reading adds a row here, with a link to its own monthly update.

Inspection MonthConstruction ProgressInspection DateFull Update
August 20267%6 August 2026View the August 2026 update

Pace Analysis

How Fast The Highgrove Has Been Built

With one dated reading and one undated earlier figure, The Highgrove's record supports a single whole-build average from the registered start, not a measured velocity between two inspections:

  • Sep 2025 to Aug 2026: enabling, piling and foundation works, from the 1 September 2025 start to 7% on 6 August 2026 (arithmetic, not a forecast)About 0.62 points per month
  • Undated previous reading of 4.31% to 7% on 6 August 2026: the register shows no date for the earlier figureNo measured pace yet

Read as a curve, The Highgrove's record is so far a single point above its start: 7 points across 339 days of groundworks. That average reflects where the work sat on 6 August 2026, at and below ground level, where enabling, piling and foundation activity builds up the register's percentage gradually; the four podium levels and 31 residential floors of this G + 4P + 31F + R + UR tower had not yet begun to add to it. The shape becomes readable only when a second dated reading posts and the first measured velocity can be set against this opening average. For an end user planning around the Q4 2028 expected handover, the sensible step meanwhile is to confirm the current construction timetable with the developer in writing; for an investor, the next dated pair is the first real evidence of the rate this tower is being built at.

Get the Next Inspection Figure First

Tell me you are tracking The Highgrove and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About The Highgrove at Meydan Horizon

A 7% reading only means something against the tower it is measuring. The project guide covers what this record is tracking toward:

The Highgrove by Ellington in Meydan Horizon project rendering of the slender residential tower beside landscaped waterways with the city skyline beyond in Dubai - Presented by Tohid Fetrat

The Highgrove: Lagoon-Side Ellington Tower With a Sky Villa and Penthouse

The Highgrove is an Ellington tower of 291 residences in Meydan Horizon, with apartments, duplexes, a sky villa and a penthouse.

View the The Highgrove Project Guide

Considering an Early-Stage Entry?

The project page lists The Highgrove as Limited Units Available, and the mix on offer shifts as the build moves through its early stages. If the record on this page is what brought you here, ask me for current availability before the remaining choice narrows further.

Ask About Remaining Availability on WhatsApp

Stage Record

The Highgrove Build Stages, Mapped to the Inspections

Only the first two stages below carry dates in The Highgrove's record; the other three are mapped to the parts of the G + 4P + 31F + R + UR description that the register had not reached by its 7% entry on 6 August 2026, so each new inspection can be placed against them as it posts.

September 2025

Construction Start and Registration

The register records construction starting on 1 September 2025 and project 4037 registered on 12 September 2025, both shown as recorded.

Current PhaseSep 2025 to Aug 2026, 7% at last reading

Enabling, Piling and Foundations

Enabling, piling and foundation works were the recorded activity at the 6 August 2026 RERA visit, with the register at 7% and an undated previous figure of 4.31%.

Not yet recorded at 6 Aug 2026

Ground Floor and Four Podium Levels

The G and 4P of the register description: the lobby level and the four podium levels that carry the cinema and clubhouse access in the developer's plans.

Not yet recorded at 6 Aug 2026

31 Residential Floors, Roof and Upper Roof

The 31F, R and UR of the description, including the 19th and 20th floor wellness level and the 34th and 35th floor sky dining in the developer's plans.

Toward the Q4 2028 handover

Finishing, Commissioning and Handover

Apartment finishing and building systems before handover, expected in Q4 2028; the register lists a registered completion date of 31-12-2028.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on The Highgrove's own record.

Buyer Position

Tracking Your Position at The Highgrove

This page is one of four project resources that together cover a The Highgrove purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

The Highgrove by Ellington in Meydan Horizon construction updates cover image featuring a project rendering of the tall residential tower beside landscaped waterways in Dubai - Presented by Tohid Fetrat
You Are Here

The Highgrove Construction Updates

This page: the dated register record for The Highgrove from its September 2025 start to handover.

The Highgrove by Ellington in Meydan Horizon Golden Visa concept graphic with a gold visa card above a rendering of the residential tower and landscaped waterfront in Dubai - Presented by Tohid Fetrat

The Highgrove Golden Visa: From the 2 Bedroom Tier Upward

The Highgrove, Ellington's lagoon-side tower in Meydan Horizon, reaches the AED 2M Golden Visa threshold from the 2 bedroom tier upward.

Read the The Highgrove Golden Visa Guide
The Highgrove by Ellington in Meydan Horizon escrow concept graphic with shield and padlock icons above the rendered residential tower and Dubai skyline in Dubai - Presented by Tohid Fetrat

The Highgrove Escrow Account at First Abu Dhabi Bank, Project 4037

The Highgrove, DLD project 4037, escrows 291 residences at First Abu Dhabi Bank for Ellington, certified at 7% in August 2026.

Verify the The Highgrove Escrow Account

Approaching Handover

Between 7% and Handover: What The Highgrove Buyers Should Do Now

At 7% on the register, recorded on 6 August 2026, almost the whole of The Highgrove's tower is still to be built, which makes this the stretch where buyers protect their payments and their plans rather than prepare for keys. Reservation-date instalments at 60, 120, 240 and 360 days run on each buyer's own calendar whatever the register shows, so the three steps below belong before the next one falls due.

First, before any transfer, check that each reservation-date instalment is paid into the escrow account registered with the DLD for project 4037 at First Abu Dhabi Bank (FAB); The Highgrove escrow account page shows how to verify that account against the official record.

Second, if residency is part of the purchase, settle the eligibility question early through The Highgrove Golden Visa eligibility guide, because the unit type you choose decides whether its starting price reaches the threshold.

Third, follow the register rather than the skyline: the first construction-linked instalment falls due at 20% construction, so each new dated reading added to this page matters more than any change visible from the road, and The Highgrove August 2026 inspection record shows how the current figure was read.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Meydan Horizon Structure

A tower in groundworks is one site among many in Meydan Horizon. These three pages set The Highgrove's record against the market, the lagoon community and the developer around it:

Street view of Meydan Horizon properties for sale in Dubai showing modern residential buildings, palm lined roads and urban community spaces, Presented by Tohid Fetrat

Meydan Horizon: The Symphony Apartments in a Lagoon District

Meydan Horizon, the Dubai Holding lagoon district beside Ras Al Khor Wildlife Sanctuary, has The Symphony apartments for sale.

See Meydan Horizon Properties for Sale
View of Meydan Horizon in Dubai showing modern high rise buildings, a central waterway and landscaped waterfront surroundings, Presented by Tohid Fetrat

Meydan Horizon: Four Crystal Lagoons Facing Ras Al Khor Wildlife Sanctuary

Meydan Horizon is a lagoon district planned for 72,000 residents, with towers by Ellington, Imtiaz and Dubai Investments.

Explore the Meydan Horizon Community
Exterior view of Ocean House by Ellington featuring sculptural architecture, curved balconies, lush landscaping, and luxury waterfront residences in Dubai. Presented by Tohid Fetrat.

Ellington Properties: Design-Led Boutique Residences With Curated Interiors

Ellington Properties, founded in 2014, is a design-led developer of apartments, villas and waterfront homes, with 30 developments launched and delivered.

View the Ellington Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

The Highgrove Construction Updates Frequently Asked Questions

The Highgrove is an active project on the DLD register (project 4037), with its main contract recorded as progressing and a register reading of 7% recorded on 6 August 2026, when the RERA report found enabling, piling and foundation works under way. Readings posted after that date are added to the inspection timeline above.

Progress at The Highgrove is tracked on the DLD project register for project 4037, where each RERA inspection posts a percentage, read alongside the RERA Independent Progress Monitoring Report for the same visit. The report for 6 August 2026 prints no percentage of its own, so the 7% shown here is the register's figure for that date; the register's earlier 4.31% carries no date and appears on the track as a dot only.

At the 6 August 2026 reading, the DLD register carries a registered completion date of 31-12-2028 for The Highgrove, which sits inside Q4 2028, the quarter in which handover is expected. A registered completion date is an entry on the project record that can be amended as the build moves on, and the register stood at 7% on that date, so buyers should confirm the current construction timetable with the developer in writing.

The Highgrove has 291 residences in one tower that the DLD register describes as G + 4P + 31F + R + UR: a ground floor, four podium levels, 31 residential floors, a roof and an upper roof. Unit types, sizes and starting prices are set out in The Highgrove project guide.

Across the 339 days from the 1 September 2025 construction start to the 6 August 2026 reading of 7%, The Highgrove averaged about 0.62 points per month on 30-day months; that figure is arithmetic, not a forecast. The earlier 4.31% reading has no date, so no pace between two inspections can be measured yet, and the pace analysis above shows the working.

The DLD register records construction at The Highgrove as starting on 1 September 2025 and the project as registered on 12 September 2025; both dates are shown here exactly as recorded. The first dated reading in the record, 7% on 6 August 2026, is covered in The Highgrove August 2026 construction update.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the The Highgrove construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status