The Portman Construction Updates

The Dated Register Record for Ellington's 173-Residence JVC Building

The Portman's DLD register read 78.67% on 7 August 2026, when RERA recorded its structure complete, leaving MEP, envelope and finishes before handover in JVC.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

78.67%Construction Progress
7 August 2026Latest RERA Inspection
173 residencesTotal Units
Project 2537DLD Registration

Construction Snapshot

The Portman at a Glance

The Portman is Ellington's 173-residence apartment building in Jumeirah Village Circle, described in the RERA report as G+3P+16+R: a ground floor, three podium levels and 16 residential floors under a roof level. Construction started on 12 December 2022, the DLD registered the project on 10 January 2023, and the register read 78.67% on 7 August 2026. What sets this record apart is that both scheduled dates already sat in the past at that reading, so the original handover schedule and the registered completion date are shown side by side below rather than as a single target.

DLD Project Number

2537

Project Status

Active

Construction Start

12 December 2022

Total Units

173 residences

Total Built-Up Area

12,320.20 sq m

Registered Completion Date

30 September 2025

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

The Portman Construction Update Timeline

The Portman's public record holds one dated reading so far: 78.67% on the DLD register on 7 August 2026, the inspection whose RERA report lists the main contract as progressing. The register also carries a previous inspection at 56.66% without a date, so it appears on the track as a dot with no month and has no table row. The track runs from the 12 December 2022 construction start, and the single table row links the August 2026 update that documents the inspection in full.

Inspection MonthConstruction ProgressInspection DateFull Update
August 202678.67%7 August 2026View the August 2026 update
!

Reading the dates: the DLD registered completion date for project 2537 is 30 September 2025, and it has passed, while the register read 78.67% at the 7 August 2026 inspection; Ellington's original Q3 2025 handover schedule has passed as well. The register showed no revised date at that reading. Confirm the current completion date with Ellington in writing and check the completion clause in your SPA.

Pace Analysis

How Fast The Portman Has Been Built

With a single dated reading on the register, The Portman's pace can only be read as one whole-build average rather than as phases between inspections:

  • Dec 2022 to Aug 2026: construction start to the 7 August 2026 reading, 78.67 points over 1,334 daysAbout 1.77 points per month
  • After 7 August 2026: distance still to record on the DLD register, 78.67% to 100%21.33 points remain

That average is arithmetic, not a forecast: it spreads 78.67 points evenly across 1,334 days on a 30-day month, while the RERA report of 7 August 2026 shows the work itself changing character, with enabling, foundation and structural works recorded complete and MEP, the external envelope, internal works and internal finishes progressing. A second dated reading will turn the single average into a measured pace between two inspections; until then the record cannot show whether the finishing packages move more or fewer points per month than the frame did. For an end user, the practical reading is that the 21.33 points left sit inside the building and on its outer skin rather than in new floors. For an investor, both the original Q3 2025 schedule and the 30 September 2025 registered completion date have passed, so the next register figure, not a calendar date, is the measure to follow until Ellington confirms a current completion date in writing.

Get the Next Inspection Figure First

Tell me you are tracking The Portman and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About The Portman at JVC

A register percentage means more next to the building it measures. The full project guide covers what Portman buyers are tracking toward on this page:

The Portman by Ellington in Jumeirah Village Circle project rendering of a residential tower with balconies, a podium entrance, palm trees and planted frontage in Dubai - Presented by Tohid Fetrat

The Portman by Ellington: 173 Apartments in Jumeirah Village Circle

The Portman by Ellington Properties features 173 studio, 1 and 2 bedroom apartments in JVC, with a dedicated amenity floor.

View the The Portman Project Guide

Considering a Finishing-Stage Entry?

Availability at The Portman keeps shifting while the building works through its MEP, envelope and finishing packages. If the record on this page is what brought you here, ask me for current availability before remaining inventory narrows further.

Ask About Remaining Availability on WhatsApp

Stage Record

The Portman Build Stages, Mapped to the Inspections

Each stage below is pinned to the dates The Portman's record actually carries: the 12 December 2022 start, the 10 January 2023 registration and the 7 August 2026 RERA inspection at 78.67%. Where the record gives a stage no date of its own, none is invented here.

Dec 2022 to Jan 2023

Construction Start and DLD Registration

Works began on 12 December 2022 and project 2537 was registered with the DLD on 10 January 2023; the register lists Abu Dhabi Commercial Bank as its trust account bank.

Recorded complete by 7 Aug 2026

Enabling Works and Foundations

The RERA report of 7 August 2026 lists enabling and foundation works at The Portman as completed; the register carries no earlier dated reading for this stage.

Recorded complete by 7 Aug 2026

G+3P+16+R Structure

Ground floor, three podium levels, 16 residential floors and the roof level: structural works on this frame are recorded as completed in the same 7 August 2026 report.

Current Phase7 Aug 2026 at 78.67%

MEP, Envelope and Internal Finishes

At the 7 August 2026 inspection, MEP, the external envelope, internal works and internal finishes were all under way, with the register reading 78.67%.

From Ellington's handover notice

Snagging, Completion Payment and Keys

Still ahead: 21.33 points on the register, then Ellington's handover notice, the pre-handover snagging inspection, the 30% due on completion and key collection.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on The Portman's own record.

Buyer Position

Tracking Your Position at The Portman

This page is one of four project resources that together cover a The Portman purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

The Portman by Ellington in Jumeirah Village Circle construction updates cover image featuring a project rendering of the tower entrance and a taller elevation in a split layout in Dubai - Presented by Tohid Fetrat
You Are Here

The Portman Construction Updates

This page: the dated DLD register record for The Portman, from December 2022 to handover.

The Portman by Ellington in Jumeirah Village Circle Golden Visa concept graphic with a gold card above a landscaped outdoor terrace with seated people in Dubai - Presented by Tohid Fetrat

The Portman Golden Visa: Apartment Eligibility and Property Threshold

The Portman by Ellington in JVC offers studios to 2 bedroom apartments, all below the Golden Visa threshold at starting prices.

Read the The Portman Golden Visa Guide
The Portman by Ellington in Jumeirah Village Circle escrow account concept graphic with a shield and padlock over a rendered building entrance in Dubai - Presented by Tohid Fetrat

The Portman Escrow Account at ADCB, DLD Project 2537

The Portman, DLD project 2537, escrows 173 residences at Abu Dhabi Commercial Bank for Ellington, recorded at 78.67% in August 2026.

Verify the The Portman Escrow Account
The Portman by Ellington in Jumeirah Village Circle snagging inspection concept graphic showing a modern kitchen with a small inspection symbol in the corner in Dubai - Presented by Tohid Fetrat

The Portman Snagging: Balconies, Full-Height Windows and Kitchen Finishes

The Portman snagging checks Ellington's JVC apartments, from balcony drainage and full-height windows to kitchen cabinetry, bathroom waterproofing and AC.

Book The Portman Snagging

Approaching Handover

Between 78.67% and Handover: What The Portman Buyers Should Do Now

The 21.33 points still to be recorded at The Portman are MEP, envelope and finishing work around a frame that RERA recorded complete on 7 August 2026, so the remaining progress is in building systems and surfaces rather than new floors, and this is the stretch where buyer preparation counts most. A handover notice usually leaves only a short window to complete the appointment, so the three steps below are worth doing now rather than once Ellington's notice arrives.

First, plan independent snagging so defects in your apartment are documented before you accept it; no window is open yet, and The Portman snagging page explains what is checked once Ellington's notice opens it.

Second, confirm that the 30% due on completion goes only to the Abu Dhabi Commercial Bank escrow account registered for project 2537, using The Portman escrow verification page, so the last payment follows recorded progress, not a request.

Third, if residency is part of your plan, read The Portman Golden Visa threshold guide before handover: it sets each unit type's starting price against the property threshold, and title deed timing shapes the application path.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore JVC Structure

A build record reads differently once you see what surrounds it. These three pages set The Portman's 78.67% reading against JVC listings, the community around the plot and Ellington's own record:

Aerial view of Jumeirah Village Circle properties for sale in Dubai showing residential homes, landscaped greenery and the circular community layout, Presented by Tohid Fetrat

Jumeirah Village Circle: Five Imtiaz and Binghatti Towers in New Dubai

Jumeirah Village Circle, Nakheel's freehold ring of ten districts in New Dubai, lists apartments in five Imtiaz and Binghatti towers.

See JVC Properties for Sale
Aerial view of Jumeirah Village Circle (JVC) in Dubai showcasing circular urban planning residential villas green spaces and high-rise buildings with the Dubai skyline in the background. Presented by Tohid Fetrat.

JVC Community Overview

Read the Jumeirah Village Circle guide: Nakheel's freehold community of apartments, townhouses and villas with strong rental yields.

Explore the JVC Community
Exterior view of Ocean House by Ellington featuring sculptural architecture, curved balconies, lush landscaping, and luxury waterfront residences in Dubai. Presented by Tohid Fetrat.

Ellington Properties: Design-Led Boutique Residences With Curated Interiors

Ellington Properties, founded in 2014, is a design-led developer of apartments, villas and waterfront homes, with 30 developments launched and delivered.

View the Ellington Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

The Portman Construction Updates Frequently Asked Questions

The Portman, DLD project 2537, is listed as Active and read 78.67% on the DLD register on 7 August 2026. The RERA report from that inspection lists the enabling, foundation and structural packages as completed, while MEP, envelope, internal works and finishes were still in progress and the main contract was marked as progressing. The dated record is in the inspection timeline above.

The 7 August 2026 inspection put The Portman at 78.67% on the DLD register, 22.01 points above the previous inspection reading of 56.66%. The register shows that earlier figure without a date, so the rise cannot be converted into a monthly rate; the inspection notes are set out in The Portman August 2026 construction update.

Two dates are on record for The Portman and both have passed: Ellington's original Q3 2025 handover schedule and the DLD registered completion date of 30 September 2025. At the 7 August 2026 inspection the register read 78.67% and showed no revised date. Buyers confirm the current completion date with Ellington in writing and check the completion clause in their SPA, and this page's record is updated when the next reading is recorded.

The Portman has 173 residences, a mix of studio, 1 bedroom and 2 bedroom apartments. The RERA report of 7 August 2026 describes the building as G+3P+16+R, matching the developer's configuration of a ground floor, three podium levels and 16 residential floors, with a roof level above.

Across the whole build, The Portman averaged about 1.77 points per month: 78.67 points over 1,334 days from the 12 December 2022 construction start to the 7 August 2026 reading, on a 30-day month. That figure is arithmetic, not a forecast, and with only one dated reading on the register no phase-by-phase pace can be measured yet; the working is in the pace analysis above.

The DLD register records the construction start at The Portman on 12 December 2022 and the project's registration on 10 January 2023, and both dates are shown on this page as recorded. The first dated reading tracked here is 78.67% on 7 August 2026, which the stage record maps against those two dates.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the The Portman construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.