Meraas · City Walk · Construction Update
Verve City Walk Construction Update - August 2026
DLD Register Reads 13.71% for Verve City Walk by Meraas After the 04 August 2026 Inspection
Enabling, foundation, substructure and superstructure works were all progressing at Verve City Walk when RERA inspected on 04 August 2026, the register reading 13.71 percent.
Direct advisor access. Every message answered personally, never by a call center.
Verified DLD Inspection Data
Verve City Walk Construction Snapshot
A 2.97 point rise over the previous inspection keeps Verve City Walk in the early band of construction, where register readings follow work buyers rarely see from the street: groundworks, foundations and the base of the two towers.
Verve City Walk by Meraas
3152
Active
13.71%
04 August 2026
15 November 2024
436 residential units
52,621.79 sq m
Q3 2028
Data source: Dubai Land Department project register reading dated 04 August 2026, read with the RERA inspection report from the same visit, which records the works in progress and prints no percentage of its own. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. The hero image is a developer rendering, not a photograph of the site. Last updated: August 2026.
Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp
This Inspection Cycle
Verve City Walk Construction Progress Summary
The DLD register moved Verve City Walk from 10.74% at the previous inspection to 13.71% on 04 August 2026, a 2.97 point step. The register screen does not date the earlier reading, so this pair gives no measured monthly pace, and the RERA report for the same visit lists the main contract as progressing without a percentage, which is why every figure here is a register reading.
- Project registration with the DLD on 03 July 2024
- Construction start recorded on 15 November 2024
- Previous register reading of 10.74%
- Enabling works across the site
- Foundation works for both towers
- Substructure works
- Superstructure works under the main contract
- Tower A structure to 2B + G + 36 floors and Tower B to 2B + G + 28 floors
- Shared podium with ground-floor retail
- Envelope, MEP and interior works for the 436 residential units
- Handover expected in Q3 2028
Payment Linked Progress
What 13.71% Progress Means for Verve City Walk Buyers
The Verve City Walk launch plan ties its instalments to calendar dates rather than construction readings, so 13.71% does not trigger a payment by itself; it shows how much of the build still stands between today and the 25% due on handover. At this stage, four actions matter most.
Verify the escrow account
Every instalment still ahead, including the 10% dated November 2026 on the launch schedule, should go only to the DLD regulated escrow account registered for project 3152 with Abu Dhabi Commercial Bank. Verve City Walk escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.
Reread your SPA payment schedule
Five of the six dated construction instalments on the launch schedule, November 2024 to June 2026, fell due before this reading, so check how your sale and purchase agreement sets the amount due at booking, the November 2026 instalment and the 25% due on handover against the Q3 2028 estimate. Not sure how your schedule lines up with this reading? Send me your SPA schedule and I will map it against the DLD register readings.
Confirm your Oqood registration
Off-plan units at Verve City Walk are recorded in the Dubai Land Department's Oqood register while the towers are under construction. Check that your unit appears there under project 3152 before your next instalment, because that registration is what ties your purchase to the project record.
Track the next readings
With 86.29 points still to go, the coming register readings show whether the pace rises as the structure goes up. Verve City Walk construction updates keep every reading in one record.
General framework, not legal advice: payment dates, booking amounts, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.
Buying at 13.71%?
Entering Verve while the structure is still going up trades part of the launch-era instalment runway for a clearer picture: the project is active in the register, the main contract is progressing, and handover is expected in Q3 2028. Every payment goes to the DLD-registered escrow account for project 3152, released against verified construction progress.
- Works on record: enabling, foundation, substructure and superstructure progressing
- Five dated launch instalments already past, so Meraas sets the booking amount
- About two years to the Q3 2028 handover estimate, with 25% due on handover
- Construction risk carried from an empty plot
- Full instalment runway from the first payment
- Longest wait to handover, priced at launch levels
Limited Units Available, per the project page as of this update; availability shifts between cycles.
About the Development
Verve City Walk Project Details

With foundation and superstructure works progressing, Verve City Walk is an early-stage build of 436 residential units in two high-rise towers (Tower A and Tower B) on a shared podium with ground-floor retail, from 1 bedroom apartments to 5 bedroom penthouses. Starting prices: AED 2.12M ≈ USD 577K.
For buyers entering at this stage, the trade off is a wait of roughly two years against a booking amount that has to absorb the dated instalments already past, with handover expected in Q3 2028.
Verve City Walk by Meraas Project GuideSite Context This Cycle
Explore Verve City Walk Location on Dubai Map
Verve City Walk takes the north-east corner of City Walk along Al Safa Street, directly beside Coca-Cola Arena and with Sheikh Zayed Road just to the east, so this cycle's foundation, substructure and superstructure works are running on a corner plot hemmed in by an operating arena and busy roads rather than on open land.
Because City Walk is an established district, with City Walk Mall, Central Park and The Green Planet already open to the west and south-west, Verve is being built into a finished neighbourhood; for buyers at 13.71% the open question is not what the area will become but when the towers will be ready against the Q3 2028 estimate. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Buyer Resources for This Project
Investing in Verve City Walk During Early Construction
At the foundations stage, the questions that matter most are where your instalments are held and whether the purchase supports residency. Each resource below is matched to where Verve City Walk stands right now.

Verve City Walk Construction Updates
This page: the August 2026 DLD register reading and RERA works record for Verve City Walk.

Verve City Walk Golden Visa: From the Entry 1 Bedroom
Verve City Walk, Meraas's 436 residences in two high-rise towers, qualifies at all five tiers, the 1 bedroom included.
Read Verve City Walk Golden Visa Guide
Verve City Walk Escrow: Meraas's Abu Dhabi Commercial Bank Account
Meraas's Verve City Walk, DLD project 3152, escrows 440 units at Abu Dhabi Commercial Bank, 13.71% certified August 2026.
Verify Verve City Walk Escrow AccountUpdate Timeline
Other Verve City Walk Construction Updates
August 2026 opens the monthly record for Verve City Walk on this site, so there is no earlier monthly page to compare; each new reading joins the record here as later cycles publish.
Where This Update Fits
Explore Verve City Walk Structure
A reading of 13.71% is easier to judge in context: the City Walk homes already on the market, the community the towers will join, and the developer responsible for delivering them.

City Walk: Crestlane Apartments in the Meraas Lifestyle District Facing Downtown Dubai
City Walk is the Meraas lifestyle district in Al Wasl facing Downtown Dubai, with Crestlane apartments on a 75/25 payment plan.
See City Walk Properties for Sale
City Walk: Meraas's Urban Quarter With Coca-Cola Arena and Central Park
City Walk is an urban district in Al Wasl with low and mid-rise residences, 236 retail outlets and Burj Khalifa views.
Explore the City Walk Community
Meraas: Lifestyle Destinations From City Walk to Port de La Mer
Meraas is the name behind City Walk, Bluewaters Island and Madinat Jumeirah Living, from beachfront communities to luxury mixed-use districts.
View the Meraas Developer ProfileFAQs
Verve City Walk Construction Progress in August 2026: Frequently Asked Questions
As of the inspection dated 04 August 2026, Verve City Walk stands at 13.71% in the Dubai Land Department project register, 2.97 points above the previous inspection reading of 10.74%. The RERA inspection report for the same visit records the works in progress but prints no percentage of its own, so 13.71% is the register figure.
The register reading rose from 10.74% at the previous inspection to 13.71% at the inspection dated 04 August 2026, a gain of 2.97 points. The register screen for this cycle does not show when the 10.74% inspection took place, so the gain cannot be converted into a monthly pace; a measured pace becomes possible once two dated readings are on record.
One reading cannot settle that. As arithmetic, not a forecast: the build has averaged about 0.66 points per 30-day month since the recorded construction start on 15 November 2024, while the remaining 86.29 points would need about 3.35 points per month to reach 100% by the registered completion date of 15 September 2028. Structural phases usually add percentage points faster than enabling works, so the next few register readings will say far more than this one. How readings relate to handover is explained on the Verve City Walk construction updates page.
Yes. Q3 2028 is an estimate, and the registered completion date of 15 September 2028 in the DLD project register can be revised between inspection cycles; as of the 04 August 2026 record the two fall in the same quarter. Any revision would appear in the register first and in a later monthly update, and your SPA sets what happens to your obligations if handover moves.
At the RERA inspection on 04 August 2026, the inspector recorded that enabling, foundation, substructure, and superstructure works were progressing at the site, with the main contract listed as progressing. These works serve both Tower A and Tower B, which are planned to share a podium with ground-floor retail.
No. The image at the top of this page is a developer rendering of the planned Verve City Walk towers, used to identify the project. The condition of the site in August 2026 comes from the RERA inspection notes and the DLD register reading; the RERA inspection photographs belong to the official record and are not reproduced on this site.
A Question the FAQ Can Not Answer?

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is helping you read the August 2026 inspection record for Verve City Walk correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.