Emaar · Dubai Hills Estate
Vida Residences Club Point at Dubai Hills Estate Construction Updates
One Verified Reading, Two Towers, and the Road to Q1 2029
Vida Residences Club Point recorded 36.5% construction at its 22 April 2026 RERA inspection, with both nineteen storey towers now rising above completed foundations toward Q1 2029.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Vida Residences Club Point at Dubai Hills Estate at a Glance
Vida Residences Club Point puts Emaar's Vida brand into Dubai Hills Estate as 672 residences in two nineteen storey buildings, raised on plot 5367 over a podium the pair shares with a basement and two parking levels. Seventeen months separate the 05 November 2024 construction start from the 36.5% logged in April 2026, and every number in the grid below is drawn from the project's own registration file. The unusual part of this record is what surrounds it: the golf club, the mall, the park and the hospital were all trading before these towers left the ground, so the open question here is the building, not the district it lands in.
3309
Active
05 November 2024
672 residential units
61,115.19 sq m
28 February 2029 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Vida Residences Club Point at Dubai Hills Estate Construction Update Timeline
This record currently holds one dated reading: 36.5%, verified on 22 April 2026. The register also carries an earlier figure of 22.9% with no published inspection date attached, so it is described here rather than plotted, and the 13.6 point gain between the two cannot be tied to a measured window. The track below therefore shows a single verified dot, and the table row links the full April 2026 report behind it.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| April 2026 | 36.5% | 22 April 2026 | View the April 2026 update |
Pace Analysis
How Fast Vida Residences Club Point at Dubai Hills Estate Has Been Built
With one dated inspection on the record, there is no measured window between two verified readings to report yet. Two figures can still be stated honestly, and both are derived rather than recorded:
- Nov 2024 to Apr 2026: whole-build average, site start to 36.5%About 2.1 points per month
- Apr 2026 to Feb 2029: schedule-implied pace, 36.5% to 100%About 1.9 points per month
The first divides the 36.5% reading by the seventeen and a half months since 05 November 2024. The second divides the remaining 63.5 points by the thirty four months to the 28 February 2029 registered date. The comparison between them is the useful part: Club Point has so far averaged marginally more per month than its own remaining schedule asks of it, and it arrives at that comparison exactly where the arithmetic of a build normally gets easier, with piling and foundations closed out and repeating floor plates now carrying the percentage. The undated 22.9% figure sitting behind the April reading is the single gap in this record. Until a second dated inspection publishes, no phase velocity for this project can be defended, and this page will not invent one.
Get the Next Inspection Figure First
Tell me you are tracking Vida Residences Club Point at Dubai Hills Estate and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Vida Residences Club Point at Dubai Hills Estate
A reading from the register only means something set against what it is producing. The project guide holds the detail behind the percentage on this page:

Vida Residences Club Point at Dubai Hills Estate, Golf-Side Vida Towers
Vida Residences Club Point at Dubai Hills Estate brings the Vida brand to 672 apartments across two 19 storey towers.
View the Vida Residences Club Point at Dubai Hills Estate Project GuideConsidering an Entry at 36.5%?
Availability at Vida Residences Club Point is limited right now, and it moves between inspection cycles as the buildings gain floors. If you arrived here through the register rather than a brochure, tell me what you are after before the next threshold is certified.
Ask About Remaining Availability on WhatsAppStage Record
Vida Residences Club Point at Dubai Hills Estate Build Stages, Mapped to the Inspections
Every stage below is pinned to the window this project actually spent in it, read off the register instead of a textbook sequence, so the 36.5% of April 2026 has somewhere to sit.
Registration and Site Activation
Project 3309 entered the DLD register on 27 September 2024, and construction was recorded as started on 05 November 2024, with enabling works opening plot 5367.
Piling and Foundations
Piles driven under both buildings and the slab between them, then the foundations themselves. Enabling, piling and foundation works were all logged complete by the 22 April 2026 inspection.
Superstructure Across Both Towers
Concrete frames climbing Block A and Block B, nineteen residential floors apiece over the two podium levels beneath them, and the package carrying most of the movement in the current reading.
Envelope, MEP and First Finishes
Facade packages, MEP first fix, internal works and internal finishes were each logged as progressing at the same 36.5% inspection, running alongside the frame instead of waiting for it to top out.
Podium Amenities, Certification and Handover
Pools, gardens and the amenity deck across the podium, then completion certification: 63.5 points of programme sit between the April 2026 figure and a building that can be handed over.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Vida Residences Club Point at Dubai Hills Estate's own record.
Buyer Position
Tracking Your Position at Vida Residences Club Point at Dubai Hills Estate
This page is one of four project resources that together cover a Vida Residences Club Point at Dubai Hills Estate purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Vida Residences Club Point at Dubai Hills Estate Construction Updates
This page: the full inspection record for Vida Residences Club Point, kept current after every reading.

Vida Residences Club Point at Dubai Hills Estate Golden Visa: 672 Apartments
Two and three bedroom apartments at Vida Residences Club Point at Dubai Hills Estate qualify individually; the one bedroom needs combination.
Read the Vida Residences Club Point at Dubai Hills Estate Golden Visa Guide
Vida Residences Club Point at Dubai Hills Estate: Its Escrow File
Vida Residences Club Point at Dubai Hills Estate escrows 672 units at First Abu Dhabi Bank, 36.5% certified April 2026.
Verify the Vida Residences Club Point at Dubai Hills Estate Escrow AccountApproaching Handover
Between 36.5% and Handover: What Vida Residences Club Point at Dubai Hills Estate Buyers Should Do Now
At 36.5% the work that moves the percentage is repeating structure, the fastest arithmetic in any build programme. The register crosses the next certified threshold quietly, and the payment demand tied to it tends to arrive once the crossing has already happened, so the three steps below belong to this cycle rather than the next one.
First, confirm that every remaining installment is routed to the account the project is legally required to use; the Vida Residences Club Point escrow account page covers the registered account for project 3309 and how certified progress releases funds held in it.
Second, if the purchase value may support residency, settle eligibility now rather than near handover; the Vida Residences Club Point Golden Visa guide sets out how an off plan position is treated while the title deed is still years away.
Third, read each figure as it publishes instead of waiting for handover: the Vida Residences Club Point April 2026 construction update carries the full site report behind the 36.5% reading, and every later cycle is added to the timeline on this page.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Dubai Hills Estate Structure
Numbers from a register read differently when you know what is already finished nearby. These three pages set the 36.5% figure beside its market, its community and its developer:

Dubai Hills Estate Properties for Sale
Compare the Emaar projects for sale in this community, with current prices, payment plans and handover dates.
See Dubai Hills Estate Properties for Sale
Dubai Hills Estate Community Overview
Read the Dubai Hills Estate guide: 2,700 acres of parks, an 18-hole championship golf course and Dubai Hills Mall.
Explore the Dubai Hills Estate Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Vida Residences Club Point at Dubai Hills Estate Construction Updates Frequently Asked Questions
Project 3309 is listed as Active in the DLD register and sits in its superstructure phase, with 36.5% progress verified at the RERA inspection of 22 April 2026. Every reading held for this project is laid out in the inspection timeline above.
The 22 April 2026 inspection recorded 36.5% construction progress, 13.6 points above the register's previous reading of 22.9%. That earlier figure carries no published inspection date, so the gain cannot be tied to a measured period. The site report behind it is the April 2026 inspection report for Vida Residences Club Point.
Across the seventeen and a half months from the 05 November 2024 construction start to the 22 April 2026 reading, the project has averaged about 2.1 percentage points per month. Reaching 100% by the registered date of 28 February 2029 requires about 1.9 points per month from that figure. Both numbers are derived from dates and percentages rather than measured between two dated inspections, as set out in the pace analysis above.
The register carries 28 February 2029 as the completion date for project 3309, which places handover inside the Q1 2029 window, measured against the 36.5% verified on 22 April 2026. Anticipated dates are revised between inspection cycles, so this record is rebuilt each time a new reading publishes.
DLD registration records show 672 residential units across one, two and three bedroom apartments, a total built-up area of 61,115.19 sq m, divided between two nineteen storey buildings and the podium they stand on.
Project 3309 entered the DLD register on 27 September 2024, and construction was recorded as started on 05 November 2024. The first dated reading held on this page, from 22 April 2026, recorded 36.5% progress.
At the 22 April 2026 inspection, enabling works, piling and foundations were recorded complete. Structure, external envelope, MEP, internal works and internal finishes were all recorded as progressing, so several trades are running in parallel rather than in sequence.
The development occupies plot 5367 in Hadaeq Sheikh Mohammed Bin Rashid, both nineteen storey buildings turned to face the golf course and the low rise plots past it. Layouts and the wider investment case are covered in the Vida Residences Club Point project guide.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Vida Residences Club Point at Dubai Hills Estate construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.