Ellington · Dubai South Residential District
Windsor House Construction Updates
The Dated Register Record for Tower A and Tower B in Dubai South
Windsor House read 3.08% on the DLD register on 17 June 2026, the first dated entry for two Dubai South buildings, recorded at enabling works and piling.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Windsor House at a Glance
Windsor House puts 414 residences into two 2B+G+10 buildings, Tower A and Tower B, held under a single DLD registration, project 4035, which the register shows as Active. Its record opens with a construction start of 01 December 2025 and, so far, one dated reading: 3.08% on 17 June 2026. Ellington describes Windsor House as its first project in Dubai South, so this record is also the developer's first build history in the district, with no earlier Ellington phase nearby to read it against.
4035
Active
01 December 2025
414 residential units
39,084.64 sq m
31 July 2029 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Windsor House Construction Update Timeline
One dated reading anchors the Windsor House record so far: 3.08% on 17 June 2026, taken 198 days after the construction start the register dates to 01 December 2025. The register entered the project as number 4035 on 16 December 2025, fifteen days after that start, and both dates are shown here as the register holds them. The same inspection card lists a previous reading of 0% without a date, so it sits on the track as an undated baseline dot rather than a table row, and the single row below links the full June 2026 update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| June 2026 | 3.08% | 17 June 2026 | View the June 2026 update |
Pace Analysis
How Fast Windsor House Has Been Built
With a single dated reading, Windsor House has no inspection to inspection pace yet. What its record does support is a whole-build average from the recorded start, set out below as arithmetic, not a forecast:
- 01 Dec 2025 start to 17 Jun 2026: enabling works and piling, 3.08 points over 198 daysAbout 0.47 points per month
- Undated 0% baseline to 17 Jun 2026: no dated pair on the register yetNot measurable yet
There is no curve to read at Windsor House yet, only a starting point. The 0.47 figure divides the 3.08 points recorded on 17 June 2026 by the 198 days since the 01 December 2025 start, on a 30-day month, and it says nothing about the months ahead: the register shows readings, not a schedule, and build pace is rarely linear. A plot still at enabling works and piling, with two basement levels planned under each of its two buildings, has not reached the floors above ground that later readings would record. For an investor weighing timing or an end user planning a move, the useful next step is the second dated reading, which will give Windsor House its first measurable pace; the Q3 2028 handover date remains the developer's to confirm.
Get the Next Inspection Figure First
Tell me you are tracking Windsor House and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Windsor House at Dubai South Residential District
A register reading of 3.08% on 17 June 2026 only means something next to what the site is building toward. The project guide sets out what buyers are tracking on this page:

Windsor House by Ellington: 414 Apartments in Dubai South
Windsor House by Ellington features 414 studio to 3 bedroom residences across two mid-rise buildings surrounding a landscaped courtyard.
View the Windsor House Project GuideConsidering an Early-Stage Entry?
Windsor House is being sold while its plot is at enabling works and piling, so the unit mix and terms on offer can change between release cycles. If the record on this page is what brought you here, ask me what is currently available and which payment terms apply at signing.
Ask About Remaining Availability on WhatsAppStage Record
Windsor House Build Stages, Mapped to the Inspections
Only the first two stages below carry dates from the Windsor House record; the other three are the stages its 2B+G+10 description still has ahead, marked as not yet recorded so this page never runs ahead of the register.
Construction Start and DLD Registration
The register dates the construction start to 01 December 2025 and the registration of project 4035 to 16 December 2025, with the trust account held at Sharjah Islamic Bank.
Enabling Works and Piling
The RERA report of 17 June 2026 found enabling works and piling ongoing for Tower A and Tower B, with the register at 3.08% on the same date.
Two Basement Levels and Ground Floor
Each building's 2B+G+10 description begins with two basements and a ground floor; no Windsor House inspection to date records work at this level.
Ten Residential Floors per Building
Tower A and Tower B are each planned with 10 residential floors above the ground floor, home to the 414 residences; no register reading covers them yet.
Interiors, Courtyard Amenities and Handover
Interiors, the courtyard amenities and handover close the record. Ellington plans handover for Q3 2028; the registered completion date on the DLD record for project 4035 is 31 July 2029.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Windsor House's own record.
Buyer Position
Tracking Your Position at Windsor House
This page is one of four project resources that together cover a Windsor House purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Windsor House Construction Updates
This page: each dated DLD register reading for Windsor House, from its December 2025 start onward.

Windsor House Golden Visa: Only 3 Bedroom Apartments Qualify
At Windsor House by Ellington in Dubai South, only 3 bedroom apartments start above the Golden Visa property threshold.
Read the Windsor House Golden Visa Guide
Windsor House Escrow Account at Sharjah Islamic Bank, DLD Project 4035
Windsor House, DLD project 4035, escrows 414 residences at Sharjah Islamic Bank and read 3.08% in June 2026.
Verify the Windsor House Escrow AccountApproaching Handover
Between 3.08% and Handover: What Windsor House Buyers Should Do Now
The Windsor House schedule splits two ways: 20% at booking plus five reservation-date instalments, 50% in all within 360 days of each buyer's own reservation, and four 5% instalments the developer links to 20%, 30%, 40% and 50% construction. The register stood at 3.08% on 17 June 2026, below the first of those construction points, so none of the four had been triggered at that reading. Reservation-date instalments run on the calendar, not on the register, so the three checks below belong before your next transfer rather than after the next reading.
First, confirm before each transfer that the payment is going to the escrow account registered for project 4035 at Sharjah Islamic Bank; the Windsor House escrow account guide explains how to match it against the DLD record.
Second, if residency is part of the plan, settle the unit type before reserving: only the 3 bedroom, from AED 2.24M ≈ USD 610K, is priced at or above the threshold, and the Windsor House Golden Visa eligibility guide sets out the off-plan route.
Third, read the record by dated entries rather than by the calendar: the Windsor House June 2026 register record holds the first entry, and every later reading joins the timeline on this page.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Dubai South Residential District Structure
A register reading covers one plot, and the district around it is growing too. These three pages place the Windsor House record in its listings, community and developer context:

Dubai South Residential District: Inara Residence in the Freehold Core
Dubai South Residential District, the established freehold core of Dubai South, lists Inara Residence apartments on a 60/40 payment plan.
See Dubai South Residential District Properties for Sale
Dubai South Residential District: A Freehold Zone Beside Expo City Dubai
Dubai South Residential District has gated villa, townhouse and apartment communities, a lagoon beachfront and freehold title for all nationalities.
Explore the Dubai South Residential District Community
Ellington Properties: Design-Led Boutique Residences With Curated Interiors
Ellington Properties, founded in 2014, is a design-led developer of apartments, villas and waterfront homes, with 30 developments launched and delivered.
View the Ellington Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Windsor House Construction Updates Frequently Asked Questions
Windsor House, DLD project 4035, is Active on the register at the enabling works and piling stage, with a DLD register reading of 3.08% recorded on 17 June 2026. A newer reading may already be listed on the register, and every dated entry so far is in the inspection timeline above.
The most recent dated reading for Windsor House is 3.08% on the DLD register, recorded on 17 June 2026, up 3.08 points from a previous reading of 0% that carries no date on the inspection card. Because the earlier figure is undated, it works as a baseline rather than a measurable step; the full record of that inspection is in the Windsor House June 2026 construction update.
As arithmetic, not a forecast, Windsor House has averaged about 0.47 points per month on the DLD register: 3.08 points over the 198 days between the 01 December 2025 start and the 17 June 2026 reading, on a 30-day month. No inspection to inspection pace exists yet because the only earlier reading, 0%, is undated, and a single average says little about later phases. The working is in the pace analysis above.
Ellington gives Q3 2028 as the Windsor House handover, and the registered completion date held for project 4035 on the DLD register is 31 July 2029; neither date has arrived yet. With the register at 3.08% on 17 June 2026, buyers should confirm the handover timetable with the developer in writing, and this page's record is updated as new inspections are recorded.
Windsor House includes 414 residences, studio to 3 bedroom apartments, divided between Tower A and Tower B under one DLD registration, project 4035. The developer's plans place F&B and retail shops at ground level beside them, and the residences fill the 10 residential floors of each building.
Windsor House is two separate 2B+G+10 buildings, Tower A and Tower B, per the RERA report of 17 June 2026, which means each sits on two basements with a ground floor and ten residential floors stacked above. Ellington presents the pair as L-shaped buildings set around a central courtyard, and at that inspection the site was at enabling works and piling.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Windsor House construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.