Imtiaz · Meydan Horizon · Construction Update

Wynwood Horizon Construction Update - September 2026

September 2026 DLD Register Reading Puts Wynwood Horizon at 9.59% Construction Progress in Meydan Horizon

Mobilisation, enabling works, foundations and substructure defined site activity at Wynwood Horizon, with the Dubai Land Department register showing 9.59% at the 16 September 2026 reading.

Direct advisor access. Every message answered personally, never by a call center.

9.59%DLD Register Reading
16 September 2026Inspection Date
Q2 2028Expected Handover
4133DLD Project Number

DLD Register Data

Wynwood Horizon Construction Snapshot

A rise of 2.91 points on the previous DLD register reading of 6.68%, which the register shows without a date, leaves Wynwood Horizon at 9.59% and in the enabling and foundations stage, where buyers on a date-based plan use each reading to see that the site is moving.

Project Name

Wynwood Horizon by Imtiaz

Project Number

4133

Project Status

Active

Construction Progress

9.59%

Inspection Date

16 September 2026

Construction Start

15 November 2025

Total Units

159 residential units

Total Built Area

17,687.61 sq m

Expected Completion

30 October 2028

Data source: the Dubai Land Department project register for project 4133, reading dated 16 September 2026, and the RERA progress monitoring report of the same date. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: September 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Wynwood Horizon Construction Progress Summary

Ten months after construction started on 15 November 2025, the RERA report of 16 September 2026 found Wynwood Horizon still in mobilisation, with enabling, foundation and substructure works running in parallel under a main contract it marks as progressing. Every item it records is groundwork for the tower; no superstructure activity appears in the report yet.

Recorded Milestones
  • Project registered with the Dubai Land Department on 31 October 2025
  • Construction start recorded on 15 November 2025
  • Main contract in place, marked progressing by RERA
In Progress at 9.59%
  • Site mobilisation, still under way at the 16 September 2026 inspection
  • Enabling works preparing the lagoon-side site
  • Foundation works for the residential tower
  • Substructure works beneath the ground level and podium
Ahead of Handover
  • Superstructure: four podium levels, eighteen residential floors and the roof level
  • Facade, MEP systems and interior finishing across 159 residences
  • Remaining RERA inspection cycles toward 100%, then handover targeted for Q2 2028
Next inspectionNo date is announced in advance; the next reading appears in the DLD project register for project 4133 after the next RERA site visit.
Completion targetHandover targeted for Q2 2028 by the developer; the registered completion date in the DLD record is 30 October 2028, the regulatory completion deadline rather than a forecast, and it sits after that target.
Remaining distance90.41 percentage points separate the 16 September 2026 reading from 100%.
Pace arithmetic9.59 points over the 305 days since the 15 November 2025 start averages about 0.94 points per month; reaching 100% by 30 October 2028 needs about 3.50 points per month over the remaining 775 days. Arithmetic, not a forecast.

Payment Linked Progress

What 9.59% Progress Means for Wynwood Horizon Buyers

Wynwood Horizon runs on a date-based 60/40 plan, so instalments fall due on the calendar rather than at construction milestones: at the 16 September 2026 reading, 40% of the price had been called against 9.59% registered progress, and by 24 October 2026 the 15 October instalment had taken that to 45%. A further 15% falls due across three dated instalments to 15 November 2027, with 40% on completion. At this stage, four actions matter most.

Before the Next Instalment

Verify the escrow account

Every instalment should go only to the DLD regulated escrow account registered for project 4133 at Ajman Bank. Wynwood Horizon escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before 15 February 2027

Reread your SPA payment schedule

Check how your sale and purchase agreement dates each instalment and defines completion, then map the next 5% on 15 February 2027 and the 40% on completion against the Q2 2028 handover. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

After Booking

Confirm your Oqood registration

An off-plan unit is recorded with the Dubai Land Department through Oqood, the interim register entry that stands in for a title deed until the building is delivered. With the tower still at the groundwork stage, check that your Wynwood Horizon Oqood entry is issued and matches the unit and price in your SPA.

Every Cycle

Track the remaining cycles

With 90.41 points still to record before 100%, the coming inspection cycles are where the tower's floors start to register. Wynwood Horizon construction updates gathers each dated reading as it publishes.

General framework, not legal advice: instalment dates, completion definitions, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 9.59%?

Entering at the enabling and foundations stage trades a visible structure for runway: the tower is still groundwork, handover is targeted for Q2 2028, and the largest payment, 40% on completion, sits furthest away. Every payment goes to the DLD-registered escrow account for project 4133, released against verified construction progress.

Entering Now at 9.59%
  • Groundwork on record: enabling, foundation and substructure works at 16 September 2026
  • Instalments already due are settled at signing, per the developer's current terms
  • 40% held to completion, with handover targeted for Q2 2028
Typical Late Stage Entry
  • Structure standing and visible before the purchase
  • A shorter wait between signing and keys
  • Most construction-period payments due at once, usually at later release prices
AED 1.69M ≈ USD 460KStarting Price
60/40 Plan40% Due on Completion
Q2 2028Expected Handover
Ask What Is Available at Wynwood Horizon

15 Units Available on the project page as of this update; availability shifts between cycles.

About the Development

Wynwood Horizon Project Details

Wynwood Horizon by Imtiaz in Meydan Horizon project rendering showing a residential tower beside a turquoise waterfront lagoon with surrounding greenery in Dubai - Presented by Tohid Fetrat
Meydan Horizon · Imtiaz

With substructure works recorded at 9.59%, Wynwood Horizon is still a groundwork-stage site for one G+4P+18+R tower of 159 one, two and three bedroom apartments, plus retail units, beside a Meydan Horizon lagoon. Starting prices: AED 1.69M ≈ USD 460K.

For buyers entering now, the trade off is a longer wait against keeping the 40% completion payment furthest away, with handover targeted for Q2 2028 by the developer.

Wynwood Horizon by Imtiaz Project Guide

Site Context This Cycle

Explore Wynwood Horizon Location on Dubai Map

The developer's location map pins Wynwood Horizon on a lagoon-side plot toward the western side of Meydan Horizon, between Ras Al Khor Road to the north and the Al Ain-Dubai Road interchange to the west. In this cycle that position matters mostly below ground: the September 2026 report records enabling, foundation and substructure works, the packages that prepare a waterside plot for a tower and its four podium levels.

Meydan Horizon is still filling in around its lagoons, promenades and plazas, so the tower is rising into a district under construction rather than a finished one, and the developer's map shows an upcoming metro station rather than an operating line. For buyers, the Q2 2028 handover and the surrounding community will mature side by side. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Wynwood Horizon by Imtiaz on Dubai Map

Buyer Resources for This Project

Investing in Wynwood Horizon During Early Construction Progress

The enabling and foundations stage is when payment protection and residency planning get settled, long before any handover preparation. Each resource below is matched to where Wynwood Horizon stands at the September 2026 reading.

Wynwood Horizon by Imtiaz in Meydan Horizon construction updates cover image featuring a project rendering of a residential tower above a landscaped podium and water feature in Dubai - Presented by Tohid Fetrat
You Are Here

Wynwood Horizon Construction Updates

This page: the September 2026 register reading for Wynwood Horizon, recorded at the groundwork stage.

Wynwood Horizon by Imtiaz in Meydan Horizon Golden Visa concept graphic with a gold card above a rendering of a palm-lined residential tower in Dubai - Presented by Tohid Fetrat

Wynwood Horizon by Imtiaz Golden Visa: A Meydan Horizon Tower

Wynwood Horizon is Imtiaz's 159-residence freehold tower in Meydan Horizon, apartments and retail units, open to all nationalities.

Read Wynwood Horizon Golden Visa Guide
Wynwood Horizon by Imtiaz in Meydan Horizon escrow account concept graphic with a shield and padlock beside a rendered residential tower in Dubai - Presented by Tohid Fetrat

Wynwood Horizon Escrow: Imtiaz at Meydan Horizon With Ajman Bank

Imtiaz's Wynwood Horizon at Meydan Horizon is DLD project 4133, 165 units in Ajman Bank escrow, 9.59% certified September 2026.

Verify Wynwood Horizon Escrow Account

Update Timeline

Other Wynwood Horizon Construction Updates

September 2026 opens the monthly record for Wynwood Horizon; each later reading joins the construction updates hub as its cycle publishes.

All Wynwood Horizon Construction Updates

FAQs

Wynwood Horizon Construction Progress in September 2026: Frequently Asked Questions

Wynwood Horizon stood at 9.59% in the Dubai Land Department project register at the 16 September 2026 reading, under project number 4133. The RERA progress monitoring report of the same date lists the main contract as progressing, with mobilisation still under way and enabling, foundation and substructure works ongoing at the time of inspection.

The register's inspection card for 16 September 2026 lists 6.68% as the previous inspection but does not show when that earlier reading was taken. Without a date, no monthly pace can be measured between the two figures, so this record uses the 15 November 2025 construction start as its only dated reference point for the 9.59% reading.

The September 2026 record does not change the timing: handover remains targeted for Q2 2028 by the developer, and the registered completion date in the DLD record reads 30 October 2028 as of the 16 September 2026 reading. Either date can be revised in a later cycle, and each new reading is set against both on the Wynwood Horizon construction updates hub.

The report describes a site still in mobilisation, with enabling works, foundation works and substructure works all in progress for what it lists as a G+4P+18+Roof, Residential Building. It records no superstructure activity yet, and it carries inspection photographs as part of the regulatory record.

The DLD register shows Wynwood Horizon registered on 31 October 2025 and construction started on 15 November 2025, 15 days later. By the 16 September 2026 reading, construction had run for 305 days and recorded 9.59%, an average of about 0.94 points per month. That figure is arithmetic, not a forecast.

No. The image heading this update is a developer rendering of the planned tower and its pool podium, used to illustrate the project, and it is not evidence of physical progress. The site as inspected on 16 September 2026 is documented in the RERA report's own inspection photographs, which form part of the regulatory record and are not reproduced here.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the September 2026 inspection record for Wynwood Horizon correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts