Imtiaz · Meydan Horizon
Wynwood Horizon Construction Updates
A Lagoon-Side Tower Record, Read From the Foundations Up
Wynwood Horizon by Imtiaz read 9.59% in the DLD register on 16 September 2026, a first dated figure setting the groundwork baseline for this Meydan Horizon tower.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Wynwood Horizon at a Glance
Wynwood Horizon by Imtiaz is one G+4P+18+R tower of 159 residences on a lagoon-side plot in Meydan Horizon, entered in the DLD register as project 4133 on 31 October 2025 and started on 15 November 2025. Ten months after that start, the register read 9.59% on 16 September 2026, so this record opens at the foundations rather than partway up the tower. The six register anchors below are what every later Wynwood Horizon reading will be measured against.
4133
Active
15 November 2025
159 residential units
17,687.61 sq m
30 October 2028 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Wynwood Horizon Construction Update Timeline
The Wynwood Horizon record holds a single dated reading so far: 9.59% on 16 September 2026, the same day as the RERA progress monitoring report that listed mobilisation, enabling, foundation and substructure works on the plot. The register's inspection card also carries an earlier figure of 6.68% with no date attached, so it appears on the track below as an undated dot and stays out of the table. The one table row links the full September 2026 update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| September 2026 | 9.59% | 16 September 2026 | View the September 2026 update |
Pace Analysis
How Fast Wynwood Horizon Has Been Built
Pace between inspections usually tells buyers more than any single percentage, but Wynwood Horizon has one dated reading so far, 9.59% on 16 September 2026. Until a second dated reading posts, the record supports two figures, both arithmetic, not a forecast:
- 15 Nov 2025 to 16 Sep 2026: mobilisation, enabling and substructure, construction start to 9.59% over 305 daysAbout 0.94 points per month
- 16 Sep 2026 to the 30 Oct 2028 registered completion date: the remaining 90.41 points over 775 daysAbout 3.50 points per month
This record is too young to have a curve. Its only dated point is 9.59% on 16 September 2026, and the 6.68% before it carries no date, so nothing here is a measured rate between two inspections. What the arithmetic does show is the shape of the job ahead. The 0.94 points per month since the 15 November 2025 start covers mobilisation, enabling, foundation and substructure works, packages that typically move a whole-building percentage less than the floors built on top of them. The 3.50 points per month that would carry the register to 100% by 30 October 2028 has to come mostly from the four podium levels, the eighteen upper floors and the fit-out of 159 apartments. For an end user, the next two or three readings are the ones to watch, because they are where the frame of the tower should start to register; for an investor, they supply the first dated pair from which a real Wynwood Horizon pace can be measured.
Get the Next Inspection Figure First
Tell me you are tracking Wynwood Horizon and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Wynwood Horizon at Meydan Horizon
A 9.59% reading on 16 September 2026 only means something next to what is being built. The project guide covers the tower this record is tracking toward:

Wynwood Horizon: An Imtiaz Tower Beside Crystal Lagoons
Wynwood Horizon by Imtiaz is a Meydan Horizon tower of 159 apartments over eighteen floors, with retail at its base.
View the Wynwood Horizon Project GuideConsidering an Early-Stage Entry?
Wynwood Horizon is still at the groundwork stage, and the units on offer shift as the tower rises and each release is taken up. If the record on this page is what brought you here, ask me for current availability before the next dated instalment on 15 February 2027.
Ask About Remaining Availability on WhatsAppStage Record
Wynwood Horizon Build Stages, Mapped to the Inspections
Each stage below is pinned to what the Wynwood Horizon record actually holds: two register dates, one dated reading and the developer's Q2 2028 handover target. Stages the inspections have not reached carry no dates, because none have been recorded for this tower yet.
Registration and Construction Start
Project 4133 entered the DLD register on 31 October 2025, and construction start followed on 15 November 2025, opening the record this page tracks.
Mobilisation, Enabling and Substructure
The RERA report of 16 September 2026 listed mobilisation still under way, with enabling, foundation and substructure works in progress, on the day the register read 9.59%.
Podium Levels and Tower Floors
The four podium levels, the eighteen upper floors and the roof level of the G+4P+18+R frame; no reading has recorded this stage yet.
Facade, Services and Fit-Out
Enclosure, building services and interior fit-out across the 159 one, two and three bedroom apartments and the retail units, where much of the 90.41 points left after the 16 September 2026 reading will be recorded.
Finishing, Commissioning and Handover
Final finishes, systems commissioning and handover, targeted by the developer for Q2 2028; the registered completion date in the DLD record is 30 October 2028.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Wynwood Horizon's own record.
Buyer Position
Tracking Your Position at Wynwood Horizon
This page is one of four project resources that together cover a Wynwood Horizon purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Wynwood Horizon Construction Updates
This page: the dated DLD register record for Wynwood Horizon from its November 2025 start.

Wynwood Horizon by Imtiaz Golden Visa: A Meydan Horizon Tower
Wynwood Horizon is Imtiaz's 159-residence freehold tower in Meydan Horizon, apartments and retail units, open to all nationalities.
Read the Wynwood Horizon Golden Visa Guide
Wynwood Horizon Escrow: Imtiaz at Meydan Horizon With Ajman Bank
Imtiaz's Wynwood Horizon at Meydan Horizon is DLD project 4133, 165 units in Ajman Bank escrow, 9.59% certified September 2026.
Verify the Wynwood Horizon Escrow AccountApproaching Handover
Between 9.59% and Handover: What Wynwood Horizon Buyers Should Do Now
Wynwood Horizon's 60/40 plan follows calendar dates rather than build stages: 40% of the price had fallen due by the 16 September 2026 reading of 9.59%, 45% by 24 October 2026, and the next 5% is dated 15 February 2027, with 40% held to completion. That February date is the natural checkpoint, so the three steps below belong before it, not after the next reading posts.
First, confirm where each payment lands: the Wynwood Horizon escrow account guide covers the Ajman Bank account registered to project 4133, the only destination for every dated instalment.
Second, if residency is part of the plan, settle it while the payment calendar still runs to 2027: the Wynwood Horizon Golden Visa eligibility guide explains why the 2 and 3 bedroom apartments sit above the price threshold and the 1 bedroom does not.
Third, keep the purchase itself in view: the Wynwood Horizon by Imtiaz project guide holds the full dated schedule, the layouts and the Q2 2028 handover target that every later reading on this page is set against.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Meydan Horizon Structure
A groundwork-stage record reads differently once you see what surrounds it. These three pages set Wynwood Horizon's September 2026 reading against Meydan Horizon's listings, the community itself and the developer building the tower:

Meydan Horizon: The Symphony Apartments in a Lagoon District
Meydan Horizon, the Dubai Holding lagoon district beside Ras Al Khor Wildlife Sanctuary, has The Symphony apartments for sale.
See Meydan Horizon Properties for Sale
Meydan Horizon: Four Crystal Lagoons Facing Ras Al Khor Wildlife Sanctuary
Meydan Horizon is a lagoon district planned for 72,000 residents, with towers by Ellington, Imtiaz and Dubai Investments.
Explore the Meydan Horizon Community
Imtiaz Developments: Fully Furnished Residences in Dubai Islands, JVC and Meydan
Imtiaz Developments, founded in 2011, has completed and under-construction design led residential projects in Meydan, JVC and Dubai Islands.
View the Imtiaz Developments Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Wynwood Horizon Construction Updates Frequently Asked Questions
Wynwood Horizon by Imtiaz is an active DLD-registered project, number 4133, at the groundwork stage: the register read 9.59% on 16 September 2026, and the RERA report of that date listed mobilisation, enabling, foundation and substructure works in progress. Every dated reading is listed in the inspection timeline above.
The 16 September 2026 reading put Wynwood Horizon by Imtiaz at 9.59%, 2.91 points above the previous register figure of 6.68%, which the register shows without a date, so no monthly rate can be drawn from the pair. That reading is covered in full in the Wynwood Horizon September 2026 construction update.
Handover at Wynwood Horizon by Imtiaz is targeted for Q2 2028 by the developer, while the DLD register for project 4133 shows a registered completion date of 30 October 2028 as of the 16 September 2026 reading. The register date sits after the developer's target; it is the regulatory completion deadline in the record, not a forecast, and this page's record is updated as each new reading is recorded.
Wynwood Horizon by Imtiaz holds 159 residential units, all 1, 2 and 3 bedroom apartments in a single tower, alongside retail units. At the 9.59% reading of 16 September 2026, the RERA report recorded only groundwork, so the floors that will hold those 159 apartments were not yet part of the recorded works.
Wynwood Horizon by Imtiaz is a single residential tower configured G+4P+18+R: a ground level, four podium levels, eighteen upper floors and a roof level, described in the RERA report of 16 September 2026 as a G+4P+18+Roof, Residential Building. At the 9.59% reading of that date, the recorded work was still in the foundations and substructure beneath that frame.
Wynwood Horizon by Imtiaz averaged about 0.94 points per month over the 305 days from the 15 November 2025 construction start to the 9.59% reading of 16 September 2026. Reaching 100% by the 30 October 2028 registered completion date would take about 3.50 points per month over the remaining 775 days. Both figures are arithmetic, not a forecast, and the pace analysis above explains how the groundwork stage shapes the early average.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Wynwood Horizon construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.