Wynwood Horizon by Imtiaz in Meydan Horizon construction updates cover image featuring a project rendering of a residential tower above a landscaped podium and water feature in Dubai - Presented by Tohid Fetrat

Imtiaz · Meydan Horizon

Wynwood Horizon Construction Updates

A Lagoon-Side Tower Record, Read From the Foundations Up

Wynwood Horizon by Imtiaz read 9.59% in the DLD register on 16 September 2026, a first dated figure setting the groundwork baseline for this Meydan Horizon tower.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

9.59%Construction Progress
16 September 2026Latest RERA Inspection
159 residential unitsTotal Units
Project 4133DLD Registration

Construction Snapshot

Wynwood Horizon at a Glance

Wynwood Horizon by Imtiaz is one G+4P+18+R tower of 159 residences on a lagoon-side plot in Meydan Horizon, entered in the DLD register as project 4133 on 31 October 2025 and started on 15 November 2025. Ten months after that start, the register read 9.59% on 16 September 2026, so this record opens at the foundations rather than partway up the tower. The six register anchors below are what every later Wynwood Horizon reading will be measured against.

DLD Project Number

4133

Project Status

Active

Construction Start

15 November 2025

Total Units

159 residential units

Total Built-Up Area

17,687.61 sq m

Registered Completion Date

30 October 2028 (DLD)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

Wynwood Horizon Construction Update Timeline

The Wynwood Horizon record holds a single dated reading so far: 9.59% on 16 September 2026, the same day as the RERA progress monitoring report that listed mobilisation, enabling, foundation and substructure works on the plot. The register's inspection card also carries an earlier figure of 6.68% with no date attached, so it appears on the track below as an undated dot and stays out of the table. The one table row links the full September 2026 update.

Inspection MonthConstruction ProgressInspection DateFull Update
September 20269.59%16 September 2026View the September 2026 update

Pace Analysis

How Fast Wynwood Horizon Has Been Built

Pace between inspections usually tells buyers more than any single percentage, but Wynwood Horizon has one dated reading so far, 9.59% on 16 September 2026. Until a second dated reading posts, the record supports two figures, both arithmetic, not a forecast:

  • 15 Nov 2025 to 16 Sep 2026: mobilisation, enabling and substructure, construction start to 9.59% over 305 daysAbout 0.94 points per month
  • 16 Sep 2026 to the 30 Oct 2028 registered completion date: the remaining 90.41 points over 775 daysAbout 3.50 points per month

This record is too young to have a curve. Its only dated point is 9.59% on 16 September 2026, and the 6.68% before it carries no date, so nothing here is a measured rate between two inspections. What the arithmetic does show is the shape of the job ahead. The 0.94 points per month since the 15 November 2025 start covers mobilisation, enabling, foundation and substructure works, packages that typically move a whole-building percentage less than the floors built on top of them. The 3.50 points per month that would carry the register to 100% by 30 October 2028 has to come mostly from the four podium levels, the eighteen upper floors and the fit-out of 159 apartments. For an end user, the next two or three readings are the ones to watch, because they are where the frame of the tower should start to register; for an investor, they supply the first dated pair from which a real Wynwood Horizon pace can be measured.

Get the Next Inspection Figure First

Tell me you are tracking Wynwood Horizon and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About Wynwood Horizon at Meydan Horizon

A 9.59% reading on 16 September 2026 only means something next to what is being built. The project guide covers the tower this record is tracking toward:

Wynwood Horizon by Imtiaz in Meydan Horizon project rendering showing a residential tower beside a turquoise waterfront lagoon with surrounding greenery in Dubai - Presented by Tohid Fetrat

Wynwood Horizon: An Imtiaz Tower Beside Crystal Lagoons

Wynwood Horizon by Imtiaz is a Meydan Horizon tower of 159 apartments over eighteen floors, with retail at its base.

View the Wynwood Horizon Project Guide

Considering an Early-Stage Entry?

Wynwood Horizon is still at the groundwork stage, and the units on offer shift as the tower rises and each release is taken up. If the record on this page is what brought you here, ask me for current availability before the next dated instalment on 15 February 2027.

Ask About Remaining Availability on WhatsApp

Stage Record

Wynwood Horizon Build Stages, Mapped to the Inspections

Each stage below is pinned to what the Wynwood Horizon record actually holds: two register dates, one dated reading and the developer's Q2 2028 handover target. Stages the inspections have not reached carry no dates, because none have been recorded for this tower yet.

31 Oct 2025 to 15 Nov 2025

Registration and Construction Start

Project 4133 entered the DLD register on 31 October 2025, and construction start followed on 15 November 2025, opening the record this page tracks.

Current PhaseNov 2025 onward, 9.59% on 16 Sep 2026

Mobilisation, Enabling and Substructure

The RERA report of 16 September 2026 listed mobilisation still under way, with enabling, foundation and substructure works in progress, on the day the register read 9.59%.

Next stage, not yet recorded

Podium Levels and Tower Floors

The four podium levels, the eighteen upper floors and the roof level of the G+4P+18+R frame; no reading has recorded this stage yet.

Later stage, not yet recorded

Facade, Services and Fit-Out

Enclosure, building services and interior fit-out across the 159 one, two and three bedroom apartments and the retail units, where much of the 90.41 points left after the 16 September 2026 reading will be recorded.

Handover targeted for Q2 2028

Finishing, Commissioning and Handover

Final finishes, systems commissioning and handover, targeted by the developer for Q2 2028; the registered completion date in the DLD record is 30 October 2028.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Wynwood Horizon's own record.

Buyer Position

Tracking Your Position at Wynwood Horizon

This page is one of four project resources that together cover a Wynwood Horizon purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Wynwood Horizon by Imtiaz in Meydan Horizon construction updates cover image featuring a project rendering of a residential tower above a landscaped podium and water feature in Dubai - Presented by Tohid Fetrat
You Are Here

Wynwood Horizon Construction Updates

This page: the dated DLD register record for Wynwood Horizon from its November 2025 start.

Wynwood Horizon by Imtiaz in Meydan Horizon Golden Visa concept graphic with a gold card above a rendering of a palm-lined residential tower in Dubai - Presented by Tohid Fetrat

Wynwood Horizon by Imtiaz Golden Visa: A Meydan Horizon Tower

Wynwood Horizon is Imtiaz's 159-residence freehold tower in Meydan Horizon, apartments and retail units, open to all nationalities.

Read the Wynwood Horizon Golden Visa Guide
Wynwood Horizon by Imtiaz in Meydan Horizon escrow account concept graphic with a shield and padlock beside a rendered residential tower in Dubai - Presented by Tohid Fetrat

Wynwood Horizon Escrow: Imtiaz at Meydan Horizon With Ajman Bank

Imtiaz's Wynwood Horizon at Meydan Horizon is DLD project 4133, 165 units in Ajman Bank escrow, 9.59% certified September 2026.

Verify the Wynwood Horizon Escrow Account

Approaching Handover

Between 9.59% and Handover: What Wynwood Horizon Buyers Should Do Now

Wynwood Horizon's 60/40 plan follows calendar dates rather than build stages: 40% of the price had fallen due by the 16 September 2026 reading of 9.59%, 45% by 24 October 2026, and the next 5% is dated 15 February 2027, with 40% held to completion. That February date is the natural checkpoint, so the three steps below belong before it, not after the next reading posts.

First, confirm where each payment lands: the Wynwood Horizon escrow account guide covers the Ajman Bank account registered to project 4133, the only destination for every dated instalment.

Second, if residency is part of the plan, settle it while the payment calendar still runs to 2027: the Wynwood Horizon Golden Visa eligibility guide explains why the 2 and 3 bedroom apartments sit above the price threshold and the 1 bedroom does not.

Third, keep the purchase itself in view: the Wynwood Horizon by Imtiaz project guide holds the full dated schedule, the layouts and the Q2 2028 handover target that every later reading on this page is set against.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Meydan Horizon Structure

A groundwork-stage record reads differently once you see what surrounds it. These three pages set Wynwood Horizon's September 2026 reading against Meydan Horizon's listings, the community itself and the developer building the tower:

Street view of Meydan Horizon properties for sale in Dubai showing modern residential buildings, palm lined roads and urban community spaces, Presented by Tohid Fetrat

Meydan Horizon: The Symphony Apartments in a Lagoon District

Meydan Horizon, the Dubai Holding lagoon district beside Ras Al Khor Wildlife Sanctuary, has The Symphony apartments for sale.

See Meydan Horizon Properties for Sale
View of Meydan Horizon in Dubai showing modern high rise buildings, a central waterway and landscaped waterfront surroundings, Presented by Tohid Fetrat

Meydan Horizon: Four Crystal Lagoons Facing Ras Al Khor Wildlife Sanctuary

Meydan Horizon is a lagoon district planned for 72,000 residents, with towers by Ellington, Imtiaz and Dubai Investments.

Explore the Meydan Horizon Community
Exterior view of INARA by Imtiaz featuring a contemporary luxury residential tower with elegant balconies, refined façade design, and landscaped surroundings in Dubai, Presented by Tohid Fetrat

Imtiaz Developments: Fully Furnished Residences in Dubai Islands, JVC and Meydan

Imtiaz Developments, founded in 2011, has completed and under-construction design led residential projects in Meydan, JVC and Dubai Islands.

View the Imtiaz Developments Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

Wynwood Horizon Construction Updates Frequently Asked Questions

Wynwood Horizon by Imtiaz is an active DLD-registered project, number 4133, at the groundwork stage: the register read 9.59% on 16 September 2026, and the RERA report of that date listed mobilisation, enabling, foundation and substructure works in progress. Every dated reading is listed in the inspection timeline above.

The 16 September 2026 reading put Wynwood Horizon by Imtiaz at 9.59%, 2.91 points above the previous register figure of 6.68%, which the register shows without a date, so no monthly rate can be drawn from the pair. That reading is covered in full in the Wynwood Horizon September 2026 construction update.

Handover at Wynwood Horizon by Imtiaz is targeted for Q2 2028 by the developer, while the DLD register for project 4133 shows a registered completion date of 30 October 2028 as of the 16 September 2026 reading. The register date sits after the developer's target; it is the regulatory completion deadline in the record, not a forecast, and this page's record is updated as each new reading is recorded.

Wynwood Horizon by Imtiaz holds 159 residential units, all 1, 2 and 3 bedroom apartments in a single tower, alongside retail units. At the 9.59% reading of 16 September 2026, the RERA report recorded only groundwork, so the floors that will hold those 159 apartments were not yet part of the recorded works.

Wynwood Horizon by Imtiaz is a single residential tower configured G+4P+18+R: a ground level, four podium levels, eighteen upper floors and a roof level, described in the RERA report of 16 September 2026 as a G+4P+18+Roof, Residential Building. At the 9.59% reading of that date, the recorded work was still in the foundations and substructure beneath that frame.

Wynwood Horizon by Imtiaz averaged about 0.94 points per month over the 305 days from the 15 November 2025 construction start to the 9.59% reading of 16 September 2026. Reaching 100% by the 30 October 2028 registered completion date would take about 3.50 points per month over the remaining 775 days. Both figures are arithmetic, not a forecast, and the pace analysis above explains how the groundwork stage shapes the early average.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the Wynwood Horizon construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.