Wynwood by Imtiaz Construction Update - July 2026
July 2026 Inspection Places Wynwood by Imtiaz at 16% in the DLD Register on Island A
Structure works were under way at Wynwood after enabling works, piling and foundations completed, with the DLD register recording 16 percent at the 9 July 2026 inspection.
Direct advisor access. Every message answered personally, never by a call center.
DLD Register Inspection Data
Wynwood by Imtiaz Construction Snapshot
A 7.55 point rise on the previous DLD register reading of 8.45%, a reading the register shows without a date, brings Wynwood to 16% and places it in the enabling and foundations band, where escrow and registration checks count for more than any handover timeline.
Wynwood Residences By Imtiaz
3784
Active
16%
9 July 2026
15 June 2025
146 residences
17,623.11 sq m
Q3 2027
Data source: the Dubai Land Department project register for project 3784, read from the inspection record dated 9 July 2026, alongside the RERA Independent Progress Monitoring Report of the same date, which records progress status and prints no percentage. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. The image at the top of this page is a developer rendering of the planned building, not a photograph of the site. This page records the 9 July 2026 reading; later readings are tracked in the Wynwood by Imtiaz construction updates guide. Last updated: July 2026.
Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp
This Inspection Cycle
Wynwood by Imtiaz Construction Progress Summary
The RERA Independent Progress Monitoring Report dated 9 July 2026 describes a site past its groundwork: enabling works, piling and foundation were completed, mobilisation was still ongoing, and structure works had started on the concrete frame of the G+2P+14+R residential building. RERA lists the main contract as progressing, and the report carries inspection photographs.
- Enabling works across the site
- Piling works for the residential building
- Foundation works beneath the concrete frame
- Structure works on the concrete frame
- Site mobilisation, recorded as ongoing
- Main contract, listed by RERA as progressing
- Completion of the frame through the ground, two podium levels, 14 residential floors and roof
- Block work with internal and external finishes
- Furnishing of all 146 residences
- Handover expected in Q3 2027
Payment Linked Progress
What 16% Progress Means for Wynwood by Imtiaz Buyers
Wynwood's current developer plan calls instalments on calendar dates rather than construction milestones, so the 16% reading triggers no payment; it shows how far the building had moved against money already called. At 9 July 2026, 40% of the price had been called through the booking share and the February and May 2026 instalments, and the 15 August 2026 instalment brought that to 50%. At this stage of Wynwood, four actions matter most.
Verify the escrow account
Every instalment still ahead, from the 5% due on 15 November 2026 onward, should go only to the DLD regulated escrow account registered for project 3784 with Ajman Bank. Wynwood by Imtiaz escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.
Reread your SPA payment schedule
Check how your sale and purchase agreement dates each instalment, what it requires for instalments already past due at signing, and how it defines the handover notice ahead of Q3 2027. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the register readings.
Confirm your Oqood registration
At 16%, a Wynwood purchase is registered off plan through Oqood with the Dubai Land Department until completion. Once the booking payment clears, confirm the unit appears under project 3784 and keep that record with your SPA.
Track the next readings
With 84 points still to be recorded, many inspection cycles lie ahead before Q3 2027. Wynwood by Imtiaz construction updates logs each new register reading as it posts.
General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.
Buying at 16%?
Entering at the foundations stage means buying a building that is still mostly on paper: the frame had only begun to rise at the July 2026 reading, and handover is expected in Q3 2027. Buyers entering now settle the instalments already due at signing, per the developer's current terms; confirm the schedule with the developer. Every payment goes to the DLD-registered escrow account for project 3784, released against construction progress recorded in the DLD register.
- Enabling works, piling and foundation recorded complete on 9 July 2026
- Handover expected in Q3 2027
- 40% of the 60/40 plan due on completion
- Frame and facade largely visible before purchase
- A shorter wait between signing and keys
- Fewer units left to choose from
Limited units available on the project page as of this update; availability shifts between cycles.
About the Development
Wynwood by Imtiaz Project Details

With piling and foundations recorded complete and structure works under way at 16%, Wynwood is an early stage build of 146 fully furnished residences, from 1 bedroom apartments to 4 bedroom duplexes, on Island A at Dubai Islands. Starting prices: AED 2.20M ≈ USD 599K.
For buyers entering at this stage, the trade off is choosing a unit before its floor and view can be seen on site, with handover expected in Q3 2027 and the dated plan already partly called.
Wynwood by Imtiaz Project GuideSite Context This Cycle
Explore Wynwood by Imtiaz Location on Dubai Map
The developer's location map places Wynwood at the southern edge of a residential block on Island A, beside the island's main road and a short distance from the water, and at the July 2026 reading that plot was still a working site: one building moving from completed piling and foundations into its concrete frame, with mobilisation recorded as ongoing.
Dubai Islands is a young waterfront masterplan whose districts are still being built out, so Wynwood is rising into an emerging neighbourhood rather than a finished one; the developer's fact sheet puts Dubai Islands Marina and the beach about five minutes away and Dubai International Airport about fifteen, and buyers planning to live in or let the unit after Q3 2027 should weigh how much of the district will be complete by then. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Buyer Resources for This Project
Investing in Wynwood by Imtiaz During Early Construction Progress
At the foundations stage, the questions that matter are payment protection and residency eligibility rather than handover logistics. Each resource below is matched to where Wynwood stood at the 9 July 2026 reading.

Wynwood by Imtiaz Construction Updates
This page: the 9 July 2026 register reading for Wynwood at 16%, with structure works ongoing.

Wynwood by Imtiaz Golden Visa: 146 Furnished Residences
Imtiaz's Wynwood on Island A clears the threshold at every layout, from the 1 bedroom apartment to the 4 bedroom duplex.
Read Wynwood by Imtiaz Golden Visa Guide
Wynwood by Imtiaz Escrow: The Ajman Bank Account on Island A
Imtiaz Developments' Wynwood escrows 146 units with Ajman Bank as DLD project 3784, certified 16% in July 2026.
Verify Wynwood by Imtiaz Escrow AccountUpdate Timeline
Other Wynwood by Imtiaz Construction Updates
July 2026 is the first monthly record for Wynwood on this site; each later reading joins the timeline once it posts in the DLD register.
Where This Update Fits
Explore Wynwood by Imtiaz Structure
This monthly record is one part of the wider picture: the island listings competing with Wynwood, the community taking shape around the site, and the developer delivering it.

Island A: Four Imtiaz Projects, From Furnished Apartments to Marina-Front Penthouses
Island A is the urban waterfront core of Dubai Islands, with furnished apartments, duplexes and penthouses across four Imtiaz projects.
See Island A Properties for Sale
Island A Community Overview
Read the full Island A guide: the island's role in the Dubai Islands masterplan, property types, connectivity and pricing.
Explore the Island A Community
Imtiaz Developments: Fully Furnished Residences in Dubai Islands, JVC and Meydan
Imtiaz Developments, founded in 2011, has completed and under-construction design led residential projects in Meydan, JVC and Dubai Islands.
View the Imtiaz Developments Developer ProfileFAQs
Wynwood by Imtiaz Construction Progress in July 2026: Frequently Asked Questions
The Dubai Land Department project register shows Wynwood by Imtiaz, registered as project 3784, at 16% construction progress following the inspection dated 9 July 2026. The RERA monitoring report of the same date lists the main contract as progressing but prints no percentage, so 16% is the register reading rather than a figure taken from the report itself.
No change is shown: as of the 9 July 2026 reading, handover is expected in Q3 2027, and the DLD record lists 30 September 2027 as the registered completion date. Registered completion dates can be revised between inspection cycles, so the date is worth rechecking in the register before any payment decision. How readings lead to completion is explained in the Wynwood by Imtiaz construction updates guide.
The inspection card dated 9 July 2026 in the DLD app lists 8.45% as the previous inspection beside the 16% current figure, but it does not display when that earlier inspection took place. Without that date, this page does not work out a monthly pace from the two readings. The date of the earlier inspection can be checked in the inspection history for project 3784 in the DLD app.
The Independent Progress Monitoring Report dated 9 July 2026 notes that enabling works, piling and foundation were completed, that structure works were ongoing and that site mobilisation was still in progress. It describes the project as a G+2P+14+R residential building with a concrete structure and block walls carrying internal and external finishes, and it includes inspection photographs.
The DLD record lists 15 June 2025 as the construction start and 1 July 2025 as the registration date, so the recorded start falls 16 days before registration. Both dates are shown here exactly as the register gave them at the 9 July 2026 reading.
No. It is a developer rendering of the planned building, used to illustrate this update, and it does not show the site as it stood on 9 July 2026. The inspection photographs in the RERA report form part of the official record and are not reproduced on this page.
A Question the FAQ Can Not Answer?

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is helping you read the July 2026 inspection record for Wynwood correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.