Imtiaz Developments · Island A, Dubai Islands
Wynwood Construction Updates
The Register Record of One Furnished Residential Building Rising on Island A
Wynwood by Imtiaz read 16% in the DLD register on 9 July 2026, an opening record for one G+2P+14+R building on Island A with foundations complete.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Wynwood at a Glance
Wynwood by Imtiaz is a single G+2P+14+R residential building of 146 fully furnished residences on Island A at Dubai Islands, registered with the Dubai Land Department as project 3784. Its record is short and recent: construction started on 15 June 2025, the project was registered on 1 July 2025, and the 9 July 2026 reading placed it at 16%, so this page tracks Wynwood from near the start of the build rather than reconstructing a long history. With one building under one main contract and handover expected in Q3 2027, every figure below describes the same frame, with no towers or phases to separate.
3784
Active
15 June 2025
146 residences
17,623.11 sq m
30 September 2027 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Wynwood Construction Update Timeline
Wynwood's record holds one dated reading so far: 16% in the DLD register on 9 July 2026, from the same inspection whose RERA report lists enabling works, piling and foundation as completed. The register entry also carries a previous reading of 8.45% but shows no date for it, so that figure sits on the track below as an undated dot and has no row in the table. Each later reading for project 3784 joins both once it posts, and the July 2026 row links the full monthly update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| July 2026 | 16% | 9 July 2026 | View the July 2026 update |
Pace Analysis
How Fast Wynwood Has Been Built
With a single dated reading, Wynwood's pace can only be framed as arithmetic between fixed register dates. Two figures bracket the build, and both are labelled arithmetic, not a forecast:
- 15 Jun 2025 to 9 Jul 2026: enabling works, piling and foundations, 16 points over 389 days to the 16% reading (arithmetic, not a forecast)About 1.23 points per month
- 9 Jul 2026 to 30 Sep 2027: frame, finishes and furnishing, 84 points over 448 days to the registered completion date (arithmetic, not a forecast)About 5.63 points per month
There is no curve to read yet, only a starting point and a deadline. The first figure spreads the 16% recorded on 9 July 2026 across the whole span since the 15 June 2025 start, a period the RERA report of the same date shows went into enabling works, piling and foundations. The second is the average that the remaining 84 points would need over the 448 days to the registered completion date of 30 September 2027, which falls on the last day of the Q3 2027 handover quarter. Neither figure predicts anything, and the undated 8.45% previous reading cannot anchor a measured pace, so Wynwood's first true velocity figure arrives with its second dated reading. For an end user, that reading shows how far the frame has climbed through the two podium levels and 14 residential floors; for an investor, the useful comparison is that reading against the 5.63-point line rather than the 1.23-point average.
Get the Next Inspection Figure First
Tell me you are tracking Wynwood and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Wynwood at Island A
A 16% reading in July 2026 only means something next to the building it measures. The full project guide covers what Wynwood buyers are tracking toward on this page:

Wynwood by Imtiaz: A 14-Floor Furnished Building on Island A
Wynwood by Imtiaz is a building on Island A with 146 furnished residences, from one bedroom apartments to four bedroom duplexes.
View the Wynwood Project GuideConsidering an Early-Stage Entry?
Limited units are available at Wynwood, and the choice narrows as layouts are taken while the frame is still rising. If the record on this page is what brought you here, ask me for current availability before choosing a floor you cannot yet see on site.
Ask About Remaining Availability on WhatsAppStage Record
Wynwood Build Stages, Mapped to the Inspections
Each stage below is anchored to the register dates and the 9 July 2026 inspection rather than a generic construction sequence, so you can see where Wynwood's single building stood when its 16% was recorded and what still separates it from handover.
Site Start and Registration
Construction started on 15 June 2025 and project 3784 was registered on 1 July 2025; site mobilisation was still recorded as ongoing at the 9 July 2026 inspection.
Enabling Works, Piling and Foundations
Recorded as completed by the 9 July 2026 RERA inspection and sitting beneath the 16% reading; the 8.45% previous reading belongs to an earlier inspection the register does not date.
Concrete Frame of the G+2P+14+R Building
Structure works were ongoing on 9 July 2026, with the frame still to rise through the ground floor, two podium levels, 14 residential floors and the roof.
Block Work, Finishes and Furnishing
Block walls, internal and external finishes, and the furnishing of all 146 residences follow the frame; no reading for this stage had been recorded by July 2026.
Podium, Rooftop and Handover
The first-floor pool deck, the gym on the second podium level and the rooftop infinity pool complete the building, against a registered completion date of 30 September 2027.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Wynwood's own record.
Buyer Position
Tracking Your Position at Wynwood
This page is one of four project resources that together cover a Wynwood purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Wynwood Construction Updates
This page: the DLD register record for Wynwood, from its June 2025 start to handover.

Wynwood by Imtiaz Golden Visa: 146 Furnished Residences
Imtiaz's Wynwood on Island A clears the threshold at every layout, from the 1 bedroom apartment to the 4 bedroom duplex.
Read the Wynwood Golden Visa Guide
Wynwood by Imtiaz Escrow: The Ajman Bank Account on Island A
Imtiaz Developments' Wynwood escrows 146 units with Ajman Bank as DLD project 3784, certified 16% in July 2026.
Verify the Wynwood Escrow AccountApproaching Handover
Between 16% and Handover: What Wynwood Buyers Should Do Now
Under the developer's current plan, Wynwood instalments fall due on calendar dates rather than construction milestones, so the stretch between 16% and a finished frame is measured in payments as much as in floors. At the 9 July 2026 reading, 40% of the price had been called through the booking share and the February and May 2026 instalments against 16% registered progress; the 15 August 2026 instalment took that to 50%, and the next 5% falls due on 15 November 2026. Dated instalments arrive whether or not a new reading has posted, so the three checks below belong before the next due date, not after it.
First, confirm that every remaining instalment goes only to the Ajman Bank trust account registered for project 3784; the Wynwood by Imtiaz escrow account page shows how to check it against the DLD record.
Second, if residency is part of your plan, settle eligibility early through the Wynwood by Imtiaz Golden Visa guide, since the qualifying value and timing of an off-plan purchase are worth confirming well before the Q3 2027 handover.
Third, place the unit you are tracking within the building through the Wynwood by Imtiaz project guide, where the 1 to 3 bedroom apartments and the 4 bedroom duplexes are set out, so each new reading can be read against the floors your residence depends on.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Island A Structure
A build record is only half the picture; the other half is what is rising around it. These three pages put Wynwood's July 2026 reading in its island, community, and developer context:

Island A: Four Imtiaz Projects, From Furnished Apartments to Marina-Front Penthouses
Island A is the urban waterfront core of Dubai Islands, with furnished apartments, duplexes and penthouses across four Imtiaz projects.
See Island A Properties for Sale
Island A Community Overview
Read the full Island A guide: the island's role in the Dubai Islands masterplan, property types, connectivity and pricing.
Explore the Island A Community
Imtiaz Developments: Fully Furnished Residences in Dubai Islands, JVC and Meydan
Imtiaz Developments, founded in 2011, has completed and under-construction design led residential projects in Meydan, JVC and Dubai Islands.
View the Imtiaz Developments Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Wynwood Construction Updates Frequently Asked Questions
Wynwood by Imtiaz, an active DLD-registered project (number 3784), was in its structural stage at the inspection of 9 July 2026, recorded at 16% in the Dubai Land Department register with enabling works, piling and foundation completed and structure works ongoing. The full record is in the inspection timeline above.
The latest DLD register reading, dated 9 July 2026, placed Wynwood by Imtiaz at 16%, 7.55 points above the previous reading of 8.45%. The register shows that earlier reading without a date, so the rise cannot be expressed as a monthly pace. The full record of that inspection is in the July 2026 Wynwood by Imtiaz construction update.
The two line up: handover for Wynwood by Imtiaz is expected in Q3 2027, and the DLD record for project 3784 lists 30 September 2027, the last day of that quarter, as the registered completion date. As of the 9 July 2026 reading of 16%, 448 days separated the reading from that date, and this page's record is updated as each later reading is recorded.
Wynwood by Imtiaz is being built with 146 residences, the same total shown in the DLD register for project 3784, all delivered fully furnished and ranging from 1 bedroom apartments to 4 bedroom duplexes within a single residential building on Island A at Dubai Islands.
The Wynwood by Imtiaz timeline runs from a construction start of 15 June 2025 and DLD registration on 1 July 2025, through the 16% register reading of 9 July 2026, to a registered completion date of 30 September 2027, with handover expected in Q3 2027. Each date is shown as the register recorded it.
Reaching 100% by 30 September 2027 would take Wynwood by Imtiaz about 5.63 points per month over the 448 days after the 9 July 2026 reading of 16%, compared with a whole-build average of about 1.23 points per month across the 389 days since the 15 June 2025 start. Both figures are arithmetic, not a forecast; the working is in the pace analysis above.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Wynwood construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.