310 Riverside Crescent by Sobha Realty in Sobha Hartland 2 project rendering used for the September 2026 construction update showing a landscaped pedestrian walkway, mature trees and surrounding residential buildings in Dubai - Presented by Tohid Fetrat

Sobha Realty · Sobha Hartland 2 · Construction Update

310 Riverside Crescent Construction Update - September 2026

DLD Register Records 310 Riverside Crescent at 50.23% Construction Progress After the September 2026 Inspection

Superstructure works, the external envelope, MEP and internal finishes are progressing at different stages at 310 Riverside Crescent, recorded at 50.23 percent on 09 September 2026.

Direct advisor access. Every message answered personally, never by a call center.

50.23%DLD Register Reading
09 September 2026Inspection Date
Q4 2027Expected Completion
3067DLD Project Number

DLD Register Data

310 Riverside Crescent Construction Snapshot

A 50.23% DLD register reading at the 09 September 2026 inspection places 310 Riverside Crescent in the envelope and MEP band, though here the superstructure is still rising alongside those trades rather than finished ahead of them.

Project Name

310 Riverside Crescent by Sobha Realty

Project Number

3067

Project Status

Active

Construction Progress

50.23%

Inspection Date

09 September 2026

Construction Start

10 May 2024

Total Units

894 residences

Total Built Area

72,440.62 sq m

Expected Completion

Q4 2027

Data source: the DLD project register for project 3067 (inspection report card dated 09 September 2026; registered developer SOBHA L.L.C, developer number 966; project registered 29 May 2024, construction start recorded as 10 May 2024) and the RERA Independent Progress Monitoring Report of the same date, which lists Progress Status as Main Contract, Progressing and prints no percentage. The 50.23% figure is the register reading; the register extract on file shows no completion date, and Q4 2027 is the expected handover. Monthly tracking of construction against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. The image at the top of this page is a developer rendering, not a site photograph. Last updated: September 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

310 Riverside Crescent Construction Progress Summary

The DLD register put 310 Riverside Crescent at 50.23% on 09 September 2026, 5.72 points above a previous inspection figure of 44.51% that the register shows without a date, so no monthly pace can be measured from that pair. The RERA report of the same day finds enabling, foundation and substructure works completed, with superstructure, external envelope, MEP, internal works and internal finishes progressing at different stages.

Completed
  • Enabling works
  • Foundation works
  • Substructure works, per the 09 September 2026 RERA report
In Progress at 50.23%
  • Superstructure works on the 2B+G+5P+66F+Roof tower
  • External envelope works
  • MEP systems: mechanical, electrical, and plumbing
  • Internal works and internal finishes, at different stages
Ahead of Handover
  • Superstructure carried through to roof level
  • Remaining RERA inspection cycles toward 100%
  • Completion paperwork and handover of the 894 residences, expected Q4 2027
Next inspectionPublished in the DLD project register after the next RERA site visit; the record sets no date for it, and this cluster adds each new reading as it appears.
Completion targetQ4 2027 expected handover; the register extract on file carries no completion date, so confirm the current timetable with Sobha Realty.
Remaining distance49.77 percentage points separate the 09 September 2026 reading from 100%.
Pace arithmeticAbout 1.77 points per month since the recorded start (50.23 points over 852 days from 10 May 2024, 30-day months). Reaching 100% by 31 December 2027, taken here as the end of Q4 2027, would need about 3.12 points per month over the remaining 478 days. Arithmetic, not a forecast: watch the next DLD reading.

Payment Linked Progress

What 50.23% Progress Means for 310 Riverside Crescent Buyers

On the 60/40 plan, 20% is paid at booking, 40% during construction and 40% on handover, so a 50.23% register reading falls inside the construction stretch of the plan. The reading does not by itself say which part of that 40% has fallen due: each SPA sets it. At this stage of 310 Riverside Crescent, four actions matter most.

Before Your Next Installment

Verify the escrow account

Every construction-stage payment should go only to the DLD regulated escrow account registered for project 3067, held with Emirates NBD. 310 Riverside Crescent escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before the Next Payment Request

Reread your SPA payment schedule

Check how your sale and purchase agreement times the 40% construction share, by calendar dates or by construction stages, and set it against the 50.23% reading and the Q4 2027 handover. Not sure how your installments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

Before Any Resale or Residency Step

Confirm your Oqood registration

Off-plan purchases are recorded on the DLD interim register, Oqood, long before a title deed exists. Mid-build is when resale, assignment and residency questions begin to surface, and each starts from that record in your name; the 310 Riverside Crescent Golden Visa guide sets out which unit types meet the residency threshold.

Every Cycle

Track the remaining cycles

With 49.77 points still to record, further inspection readings remain before handover. The 310 Riverside Crescent construction updates hub lists each one as it is published.

General framework, not legal advice: milestone definitions, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 50.23%?

Entering at the midpoint of the build trades part of the launch-stage payment runway for a project whose below-ground works are recorded as completed, while the tower above is still rising. Every payment goes to the DLD-registered escrow account for project 3067, released against construction progress recorded by RERA inspections.

Entering Now at 50.23%
  • Enabling, foundation and substructure works recorded as completed
  • Handover expected in Q4 2027
  • 40% of the 60/40 plan due on handover; construction-stage timing set in your SPA
Typical Launch Entry
  • Construction risk carried from excavation to handover
  • Two to four years of waiting is the usual delivery horizon
  • Longest installment runway, priced at launch levels
AED 1.36M ≈ USD 370KStarting Price
60/40 Plan40% Due on Handover
Q4 2027Expected Handover
Ask What Is Available at 310 Riverside Crescent

Unit availability is published on the project page rather than in this update, because availability shifts between cycles.

About the Development

310 Riverside Crescent Project Details

310 Riverside Crescent by Sobha Realty in Sobha Hartland 2 project rendering of several residential towers overlooking a landscaped lagoon, with a green arrow pointing to one tower in Dubai - Presented by Tohid Fetrat
Sobha Hartland 2 · Sobha Realty

With substructure works recorded as completed and the superstructure still rising at the 09 September 2026 inspection, 310 Riverside Crescent is a mid-build tower of 894 residences in 1, 1.5, 2 and 2.5 bedroom layouts. Starting prices: AED 1.36M ≈ USD 370K.

For buyers entering at this stage, the trade off is a shorter wait than at launch against less of the construction-stage runway remaining, with 40% of the 60/40 plan due at the expected Q4 2027 handover.

310 Riverside Crescent by Sobha Realty Project Guide

Site Context This Cycle

Explore 310 Riverside Crescent Location on Dubai Map

310 Riverside Crescent rises within Sobha Hartland 2, where the developer's floor plans label unit outlooks toward the community lagoons and the wider community, and the brochure cites views of the Dubai skyline and Meydan Racecourse. For a tower registered as two basements, ground, five podium levels and 66 floors, this cycle's works are spread vertically: the RERA report places superstructure, envelope, MEP and finishing works at different stages rather than in one sequence.

The developer plans Sobha Hartland 2 as a master community of about 8 million sq ft with an international school, offices, a mall, clubhouses and retail, so buyers at the midpoint of the build should check which of those facilities will be operating by the Q4 2027 handover rather than assume the full plan is in place. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view 310 Riverside Crescent by Sobha Realty in Sobha Hartland 2 on Dubai Map

Buyer Resources for This Project

Investing in 310 Riverside Crescent at the Mid-Build Stage

Mid-build is where payment verification, residency planning, and the construction-stage installments meet. Each resource below is matched to where 310 Riverside Crescent stands at 50.23%.

310 Riverside Crescent by Sobha Realty in Sobha Hartland 2 construction updates cover image featuring a project rendering of residential towers beside a landscaped lagoon in Dubai - Presented by Tohid Fetrat
You Are Here

310 Riverside Crescent Construction Updates

This page: the 09 September 2026 register reading for 310 Riverside Crescent, superstructure still rising.

310 Riverside Crescent by Sobha Realty in Sobha Hartland 2 Golden Visa concept graphic with a gold card above a rendering of residential towers and a landscaped lagoon in Dubai - Presented by Tohid Fetrat

310 Riverside Crescent Golden Visa: Eligible Apartments and Off-Plan Requirements

Explore 310 Riverside Crescent Golden Visa eligibility, qualifying apartment types, off-plan application requirements and complimentary VIP processing assistance.

Read 310 Riverside Crescent Golden Visa Guide
310 Riverside Crescent by Sobha Realty in Sobha Hartland 2 escrow account concept graphic showing a shield and padlock over landscaped waterfront terraces and a swimming pool in Dubai - Presented by Tohid Fetrat

310 Riverside Crescent Escrow Account: Emirates NBD and DLD Verification Copy

Verify 310 Riverside Crescent escrow account details at Emirates NBD, check DLD registration and learn how to safeguard buyer payments. Copy

Verify 310 Riverside Crescent Escrow Account

Update Timeline

Other 310 Riverside Crescent Construction Updates

New readings for 310 Riverside Crescent are added to the construction updates hub as each RERA inspection reaches the DLD register, so the record can be followed reading by reading.

All 310 Riverside Crescent Construction Updates

FAQs

310 Riverside Crescent Construction Progress in September 2026: Frequently Asked Questions

The DLD project register records 310 Riverside Crescent (project 3067) at 50.23% construction progress following the inspection of 09 September 2026. The RERA progress report of the same date prints no percentage and lists the main contract as progressing, so 50.23% is the register reading for this cycle.

Yes. Expected handover dates can be revised between inspection cycles, and a single reading neither fixes nor moves one. Q4 2027 is the expected handover for 310 Riverside Crescent as of September 2026, and the register extract on file shows no completion date, so the current timetable should be confirmed directly with Sobha Realty and against your SPA. How successive readings build toward handover is covered on the 310 Riverside Crescent construction updates hub.

Alongside the current 50.23% figure, the DLD app lists 44.51% as the previous inspection for 310 Riverside Crescent but shows no date for it. Without that date the gap between the two readings cannot be turned into a monthly pace, so this page treats 44.51% only as an earlier point on the record.

The RERA report dated 09 September 2026 found enabling, foundation and substructure works completed at 310 Riverside Crescent. Superstructure works, the external envelope, MEP, internal works and internal finishes were all progressing at different stages, so the tower was still rising at the time of that inspection.

No. The image at the top of this September 2026 page is a developer rendering of landscaped community space, not a photograph of the construction site. The DLD register record for project 3067 carries inspection photographs of its own; they are not reproduced on this page.

On the 60/40 plan for 310 Riverside Crescent, 20% is paid at booking, 40% during construction and 40% on handover. A register reading of 50.23% shows how far the building has progressed, but it does not by itself show which part of the construction 40% has fallen due, because each SPA sets those installments.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the September 2026 inspection record for 310 Riverside Crescent correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts