Sobha Realty · Sobha Hartland 2
310 Riverside Crescent Construction Updates
Following a 66-Floor Sobha Hartland 2 Tower Through Its Mid-Build Climb
310 Riverside Crescent reached 50.23% on the DLD register on 09 September 2026, climbing from a May 2024 start with its 66-floor superstructure still rising.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
310 Riverside Crescent at a Glance
310 Riverside Crescent is Sobha Realty's 894-residence tower in Sobha Hartland 2, registered with the Dubai Land Department as project 3067 and described in its RERA report as two basements, ground, five podium levels, 66 floors and a roof. Construction was recorded as starting on 10 May 2024, the project was registered on 29 May 2024, and the 09 September 2026 inspection put it at 50.23%. What marks this record is that the halfway reading arrived while the superstructure was still rising, with envelope, MEP and finishing trades progressing alongside it rather than after it.
3067
Active
10 May 2024
894 residences
72,440.62 sq m
Q4 2027 (developer handover)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
310 Riverside Crescent Construction Update Timeline
The register gives 310 Riverside Crescent one dated reading so far: 50.23% at the inspection of 09 September 2026, logged against a construction start of 10 May 2024 and a registration date of 29 May 2024. The DLD app also lists 44.51% as the previous inspection without a date, so it sits on the track below as an earlier point rather than as a table row. The single row links the September 2026 update, whose header image is a developer rendering, not a site photograph.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| September 2026 | 50.23% | 09 September 2026 | View the September 2026 update |
Pace Analysis
How Fast 310 Riverside Crescent Has Been Built
With a single dated reading, the pace of 310 Riverside Crescent can only be read as arithmetic: from the recorded start to 50.23%, and from 50.23% to the Q4 2027 handover. Two figures frame it:
- May 2024 to Sep 2026: whole-build average, 0% at the recorded start to 50.23% over 852 daysAbout 1.77 points per month
- Sep 2026 to Dec 2027: rate needed for 100% by 31 December 2027, 49.77 points over 478 daysAbout 3.12 points per month
Both figures use 30-day months and are arithmetic, not a forecast. The first folds the enabling, foundation and substructure works, recorded as completed in September 2026, into one line with a superstructure that was still climbing toward its 66th floor; the second simply spreads the remaining 49.77 points across the days left to 31 December 2027, a date taken here as the end of Q4 2027. The DLD app also lists an earlier 44.51% without a date, which places a second point on the track but cannot yield a measured rate. For an end user planning a move, and for an investor sizing the construction-stage share of the 60/40 plan, the useful signal is the next dated DLD reading, which will turn this single point into the record's first measurable pair; until then, the current handover timetable is a question for Sobha Realty.
Get the Next Inspection Figure First
Tell me you are tracking 310 Riverside Crescent and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About 310 Riverside Crescent at Sobha Hartland 2
A register percentage means more next to what is being built. The full project guide covers what 310 Riverside Crescent buyers are waiting for:

310 Riverside Crescent by Sobha Realty: Apartments in Sobha Hartland 2
Explore 310 Riverside Crescent by Sobha Realty, featuring apartment prices, floor plans, payment options, amenities and availability in Sobha Hartland 2.
View the 310 Riverside Crescent Project GuideConsidering a Mid-Construction Entry?
Availability at 310 Riverside Crescent moves as the tower rises toward its Q4 2027 handover. If the record on this page is what brought you here, ask me for current availability before choosing a layout.
Ask About Remaining Availability on WhatsAppStage Record
310 Riverside Crescent Build Stages, Mapped to the Inspections
With one dated reading so far, each stage below is anchored to what the register and the 09 September 2026 RERA report actually record for 310 Riverside Crescent: the May 2024 start, the works listed as completed, and the trades still progressing at 50.23%.
Site Activation and Enabling Works
Construction was recorded as starting on 10 May 2024, and the September 2026 RERA report lists the enabling works for the 2B+G+5P+66F+Roof tower among those completed.
Foundations and Substructure
The 09 September 2026 RERA report records foundation and substructure works as completed, closing the below-ground phase of a tower that begins with two basement levels.
Superstructure: Podium and 66 Floors
The phase this record sits in: superstructure works were still progressing at the 09 September 2026 inspection, when the DLD register put the tower at 50.23%.
Envelope, MEP, and Interior Works
External envelope, MEP, internal works and internal finishes were progressing at different stages alongside the superstructure in September 2026, rather than waiting for the frame to finish.
Commissioning and Handover
Testing of building systems, completion paperwork and the handover of 894 residences, with 49.77 points still to be recorded after the 50.23% reading of 09 September 2026.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on 310 Riverside Crescent's own record.
Buyer Position
Tracking Your Position at 310 Riverside Crescent
This page is one of four project resources that together cover a 310 Riverside Crescent purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

310 Riverside Crescent Construction Updates
This page: the DLD register record for project 3067, from the May 2024 start to handover.

310 Riverside Crescent Golden Visa: Eligible Apartments and Off-Plan Requirements
Explore 310 Riverside Crescent Golden Visa eligibility, qualifying apartment types, off-plan application requirements and complimentary VIP processing assistance.
Read the 310 Riverside Crescent Golden Visa Guide
310 Riverside Crescent Escrow Account: Emirates NBD and DLD Verification Copy
Verify 310 Riverside Crescent escrow account details at Emirates NBD, check DLD registration and learn how to safeguard buyer payments. Copy
Verify the 310 Riverside Crescent Escrow AccountApproaching Handover
Between 50.23% and Handover: What 310 Riverside Crescent Buyers Should Do Now
At 50.23%, 310 Riverside Crescent sits inside the construction stretch of its 60/40 plan, where 40% of the price is paid while the tower rises and the timing of each installment is set in the SPA. Those construction-stage payments fall due before the building is finished, so the three checks below belong before the next payment request rather than after it.
First, confirm that every construction-stage installment goes to the Emirates NBD escrow account registered for project 3067; the 310 Riverside Crescent escrow account page shows how to check it against the DLD record.
Second, if residency matters to your purchase, settle the question while construction continues; the 310 Riverside Crescent Golden Visa guide explains which unit types sit above the price threshold, from the 1.5 bedroom upward.
Third, set each new DLD reading against the construction-stage schedule in your SPA; the 310 Riverside Crescent September 2026 inspection report holds the latest detail, and later readings join the timeline above.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Sobha Hartland 2 Structure
A tower at 50.23% is easier to judge alongside what surrounds it. These three pages set the 310 Riverside Crescent record against its community, its listings, and the developer building it:

Sobha Hartland 2 Properties for Sale: Riverside Crescent and Skyscape Apartments
Explore Sobha Hartland 2 properties for sale, comparing Riverside Crescent and Skyscape apartments, payment plans, handover dates and availability.
See Sobha Hartland 2 Properties for Sale
Sobha Hartland 2: A Swimmable Lagoon Master Community in Bukadra
Sobha Hartland 2 is Sobha Realty's second MBR City master community, with 15 named projects around a swimmable lagoon.
Explore the Sobha Hartland 2 Community
Sobha Realty: In-House Construction, From High-Grade Materials to the Façade Panels
Sobha Realty controls every stage of construction itself, from producing high-grade materials to the marble flooring and façade panels.
View the Sobha Realty Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
310 Riverside Crescent Construction Updates Frequently Asked Questions
310 Riverside Crescent is an active DLD-registered project (number 3067) recorded at 50.23% construction progress at the inspection of 09 September 2026. The RERA report of that date lists enabling, foundation and substructure works as completed and the superstructure, external envelope, MEP and internal finishes as progressing, so the tower was still rising at that reading. The dated record is in the inspection timeline above.
The 09 September 2026 inspection put 310 Riverside Crescent at 50.23%, 5.72 points above the 44.51% that the DLD app lists as the previous inspection. The register shows no date for that earlier figure, so the gap cannot be read as a monthly pace. The full September reading is set out in the 310 Riverside Crescent September 2026 construction update.
Q4 2027 is the expected handover for 310 Riverside Crescent, and the register extract on file for project 3067 shows no completion date of its own. At the 50.23% reading of 09 September 2026, 49.77 percentage points remained to 100%. Handover timing is confirmed by Sobha Realty, and this page's record is updated as each new DLD reading is posted.
From the recorded start on 10 May 2024 to the 50.23% reading of 09 September 2026, 310 Riverside Crescent averaged about 1.77 percentage points per month over 852 days, using 30-day months. Reaching 100% by 31 December 2027, taken as the end of Q4 2027, would need about 3.12 points per month over the remaining 478 days. Both figures are arithmetic, not a forecast, and the pace analysis above sets them side by side.
The RERA report of 09 September 2026 describes 310 Riverside Crescent as two basements, ground, five podium levels, 66 floors and a roof (2B+G+5P+66F+Roof). The tower holds 894 residences across 1, 1.5, 2 and 2.5 bedroom layouts, and at that inspection its superstructure was still progressing toward the full 66 floors.
The DLD register records the construction start of 310 Riverside Crescent as 10 May 2024 and the project's registration as 29 May 2024. The first dated reading on this page followed on 09 September 2026 at 50.23%, about 28 months after that recorded start.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the 310 Riverside Crescent construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.