330 Riverside Crescent by Sobha Realty in Sobha Hartland 2 construction updates cover image featuring a project rendering of landscaped podium terraces beside a curved blue waterfront in Dubai - Presented by Tohid Fetrat

Sobha Realty · Sobha Hartland 2

330 Riverside Crescent Construction Updates

The Dated Register Record From a Completed Superstructure to a Q2 2027 Handover

330 Riverside Crescent read 67.81% in the DLD register on 12 October 2026, a climb that has completed its superstructure and moved on to envelope and finishes.

Construction tracking against RERA inspection data, updated after every recorded inspection.

Direct advisor access. Every message answered personally, never by a call center.

67.81%Construction Progress
12 October 2026Latest RERA Inspection
758 residencesTotal Units
Project 2788DLD Registration

Construction Snapshot

330 Riverside Crescent at a Glance

330 Riverside Crescent is Sobha Realty's 758-residence tower in Sobha Hartland 2, and because the Dubai Land Department holds it as a project of its own, number 2788, every register figure on this page belongs to this building alone. Its record opens with the start ahead of the registration: construction started on 12 October 2023, 83 days before the project was registered on 03 January 2024, and both dates are shown below exactly as the register records them.

DLD Project Number

2788

Project Status

Active

Construction Start

12 October 2023

Total Units

758 residences

Total Built-Up Area

58,020.13 sq m

Registered Completion Date

Q2 2027 (developer handover)

Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.

Inspection Record

330 Riverside Crescent Construction Update Timeline

The register record for 330 Riverside Crescent holds one dated reading so far: 67.81% on 12 October 2026, three years to the day after the 12 October 2023 start. The same register card lists a previous reading of 60.37% without showing when it was taken, so it sits on the track below as a marker with no month and has no table row. Each dated reading that follows becomes a new row linking its monthly update.

Inspection MonthConstruction ProgressInspection DateFull Update
October 202667.81%12 October 2026View the October 2026 update

Pace Analysis

How Fast 330 Riverside Crescent Has Been Built

With a single dated reading, this record cannot yet show a measured pace between two inspections. What it can show is arithmetic on the 12 October 2026 figure, labelled as such and not a forecast:

  • 12 Oct 2023 to 12 Oct 2026: whole-build average, start to 67.81% over 1,096 days (arithmetic, not a forecast)About 1.86 points per month
  • 12 Oct 2026 to 30 Jun 2027, taken as the end of Q2 2027: 67.81% to 100% over 261 days (arithmetic, not a forecast)About 3.70 points per month

The first figure spreads 67.81 points evenly across three years that included enabling works, the substructure and the full superstructure; the second is what the remaining 32.19 points would take if 100% were reached by 30 June 2027, an assumption about the quarter end rather than a date in the register. Neither describes how Sobha Realty has sequenced the envelope, MEP and finishing packages the October 2026 report lists as progressing, and the register record shows no completion date to test either number against. For an end user planning a move into one of the 758 residences, the Q2 2027 timetable is the figure to confirm with Sobha Realty; for an investor reading delivery pace, the next dated DLD reading is the first that will turn this arithmetic into a measured rate.

Get the Next Inspection Figure First

Tell me you are tracking 330 Riverside Crescent and I will send you the next recorded figure and site photos directly, ahead of the page update.

Get the Next Update on WhatsApp

Project Profile

About 330 Riverside Crescent at Sobha Hartland 2

A register percentage only means something next to what it measures. The full project guide covers the tower this record follows:

330 Riverside Crescent by Sobha Realty in Sobha Hartland 2 annotated aerial project rendering showing residential towers with a green arrow pointing toward the development in Dubai - Presented by Tohid Fetrat

330 Riverside Crescent by Sobha Realty in Sobha Hartland 2

Explore 330 Riverside Crescent apartments in Sobha Hartland 2, featuring waterfront amenities, floor plans, payment options and handover details.

View the 330 Riverside Crescent Project Guide

Considering a Late-Construction Entry?

Availability at 330 Riverside Crescent moves with each Sobha Realty release while the envelope and finishes are completed. If the register record on this page is what brought you here, ask me what is available now, before the next release cycle changes the list.

Ask About Remaining Availability on WhatsApp

Stage Record

330 Riverside Crescent Build Stages, Mapped to the Inspections

Each stage below is tied to what the register and the 12 October 2026 RERA report actually record for 330 Riverside Crescent; where the record carries no date for a stage, the window says so rather than estimating one.

12 Oct 2023 to 03 Jan 2024

Construction Start and DLD Registration

Construction started on 12 October 2023 and project 2788 was registered on 03 January 2024, 83 days later, both as the DLD register records them.

Completed by 12 Oct 2026

Enabling, Foundation, and Substructure

The 12 October 2026 report lists enabling, foundation and substructure works, including the two basement levels, as completed; no earlier dated reading shows when.

Completed by 12 Oct 2026

Superstructure to the Roof

Ground floor, three podium levels, 52 floors and roof: the same report records the superstructure works as completed, with the register at 67.81%.

Current PhaseOct 2026, 67.81% at last reading

Envelope, MEP, and Internal Finishes

The 12 October 2026 report places the external envelope, MEP, internal works and internal finishes in progress, each at its own stage, under a Main Contract, Progressing status.

Handover expected Q2 2027

Completion and Handover

The remaining 32.19 points to 100%, completion procedures and handover of the 758 residences, expected in Q2 2027.

What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on 330 Riverside Crescent's own record.

Buyer Position

Tracking Your Position at 330 Riverside Crescent

This page is one of four project resources that together cover a 330 Riverside Crescent purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

330 Riverside Crescent by Sobha Realty in Sobha Hartland 2 construction updates cover image featuring a project rendering of landscaped podium terraces beside a curved blue waterfront in Dubai - Presented by Tohid Fetrat
You Are Here

330 Riverside Crescent Construction Updates

This page: every dated DLD register reading for 330 Riverside Crescent from start to handover.

330 Riverside Crescent by Sobha Realty in Sobha Hartland 2 Golden Visa concept graphic showing a gold visa card over an aerial rendering of residential towers and a curved water feature in Dubai - Presented by Tohid Fetrat

330 Riverside Crescent Golden Visa: Eligible Apartments and Off-Plan Application Guide

Discover which 330 Riverside Crescent apartments meet Golden Visa requirements, with unit eligibility, Oqood registration, application timing and VIP assistance.

Read the 330 Riverside Crescent Golden Visa Guide
330 Riverside Crescent by Sobha Realty in Sobha Hartland 2 escrow account concept graphic showing a shield and padlock above a poolside terrace with sun loungers and landscaped planting in Dubai - Presented by Tohid Fetrat

330 Riverside Crescent Escrow Account: Bank Details and DLD Verification

Verify 330 Riverside Crescent escrow bank details, DLD registration and secure payment instructions through Dubai REST before transferring funds.

Verify the 330 Riverside Crescent Escrow Account
330 Riverside Crescent by Sobha Realty in Sobha Hartland 2 snagging inspection concept graphic placed over a furnished living room with floor-to-ceiling windows and a view of surrounding towers in Dubai - Presented by Tohid Fetrat

330 Riverside Crescent Snagging Inspection Before Apartment Handover

Book an independent snagging inspection at 330 Riverside Crescent, covering apartment defects, finishing quality, essential systems and pre-handover reporting.

Book 330 Riverside Crescent Snagging

Approaching Handover

Between 67.81% and Handover: What 330 Riverside Crescent Buyers Should Do Now

At 67.81% on 12 October 2026 the superstructure of 330 Riverside Crescent is recorded complete, while the envelope, MEP and internal finishes are still being worked through, and the construction 40% of Sobha Realty's 60/40 plan falls due on each SPA's own timetable during that work. With the other 40% due on handover in Q2 2027, the three steps below are far easier to settle months ahead than in the short window after a handover notice arrives.

First, confirm that every remaining construction instalment goes to the Emirates Islamic Bank account registered for project 2788; the 330 Riverside Crescent escrow account page shows how to check it before each transfer.

Second, read each new DLD register reading against your SPA schedule as it appears; the dated inspection timeline on this page gains a row for every one, and the next one will give this tower its first measured pace.

Third, line up an independent inspection of your apartment now rather than at notice; the 330 Riverside Crescent snagging page explains what gets checked and when to fix the date.

Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.

The Wider Picture

Explore Sobha Hartland 2 Structure

A tower's build record reads differently against what surrounds it. These three pages set the 330 Riverside Crescent readings in their market, community and developer context:

Aerial view of Sobha Hartland 2 properties for sale in Dubai showing modern residential towers, landscaped community areas and the Dubai skyline, Presented by Tohid Fetrat

Sobha Hartland 2 Properties for Sale: Riverside Crescent and Skyscape Apartments

Explore Sobha Hartland 2 properties for sale, comparing Riverside Crescent and Skyscape apartments, payment plans, handover dates and availability.

See Sobha Hartland 2 Properties for Sale
Aerial night view of Sobha Hartland 2 in Dubai showing illuminated residential towers, landscaped community areas and the Dubai skyline, Presented by Tohid Fetrat

Sobha Hartland 2: A Swimmable Lagoon Master Community in Bukadra

Sobha Hartland 2 is Sobha Realty's second MBR City master community, with 15 named projects around a swimmable lagoon.

Explore the Sobha Hartland 2 Community
Sobha Developer Dubai – luxury skyscraper with rooftop pool and skyline view of Burj Khalifa

Sobha Realty: In-House Construction, From High-Grade Materials to the Façade Panels

Sobha Realty controls every stage of construction itself, from producing high-grade materials to the marble flooring and façade panels.

View the Sobha Realty Developer Profile

Construction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.

FAQs

330 Riverside Crescent Construction Updates Frequently Asked Questions

330 Riverside Crescent, DLD project 2788 with Active status, stood at 67.81% in the register reading of 12 October 2026, with its enabling, foundation, substructure and superstructure works recorded as completed in the RERA report of the same date. The stage record above maps each of those stages to the register.

Progress at 330 Riverside Crescent is tracked through the Dubai Land Department project register for project 2788, read alongside the RERA monitoring report of the same date. The latest reading is 67.81% on 12 October 2026, 7.44 points above the previous register reading of 60.37%, which the register shows without a date. Each dated reading becomes a row in the inspection timeline, and the method is set out on the Dubai Construction Updates hub.

At the 12 October 2026 reading of 67.81%, 32.19 points remained before 330 Riverside Crescent reaches 100%, made up of the external envelope, MEP, internal works and internal finishes the RERA report lists as in progress. Handover is expected in Q2 2027, the register record reviewed for this page shows no separate completion date, and the current timetable is for Sobha Realty to confirm.

330 Riverside Crescent has 758 residences, all 1, 1.5 and 2 bedroom apartments. The RERA report of 12 October 2026 describes the building as two basements, a ground floor, three podium levels, 52 floors and a roof, written 2B+G+3P+52F+Roof. Layouts and sizes are in the 330 Riverside Crescent project guide.

Measured from the 12 October 2023 start, 330 Riverside Crescent averaged about 1.86 points per month to reach 67.81% on 12 October 2026, over 1,096 days. Reaching 100% by 30 June 2027, taken as the end of Q2 2027, would need about 3.70 points per month over 261 days. Both figures are arithmetic, not a forecast, and the pace analysis explains what each one leaves out.

The DLD register records the construction start of 330 Riverside Crescent as 12 October 2023, before the project's registration on 03 January 2024. The first dated reading in this record arrived three years later, 67.81% on 12 October 2026, documented in the October 2026 construction update for 330 Riverside Crescent.

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is keeping the 330 Riverside Crescent construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

WhatsApp +971543443597
Get the Latest Status