
Sobha Realty · Sobha Hartland 2 · Construction Update
340 Riverside Crescent Construction Update - August 2026
August 2026 Inspection Puts 340 Riverside Crescent at 55.02% Construction Progress in Sobha Hartland 2
Superstructure, external envelope, MEP and internal finishes are progressing at 340 Riverside Crescent, recorded at 55.02 percent in the DLD register after the 18 August 2026 inspection.
Direct advisor access. Every message answered personally, never by a call center.
DLD Register Inspection Data
340 Riverside Crescent Construction Snapshot
A 12.07 point rise over the previous DLD reading, which the record leaves undated, carries 340 Riverside Crescent past the halfway mark and into the envelope and MEP band, the stage where buyers check what they have paid against what the register records.
340 Riverside Crescent by Sobha Realty
3082
Active
55.02%
18 August 2026
10 May 2024
760 residential units
58,059.57 sq m
Q4 2027
Data source: Dubai Land Department register reading for the inspection dated 18 August 2026 (project 3082, registered 29 May 2024, trust account bank Emirates NBD) and the RERA progress report of the same date, which records the main contract as progressing and prints no percentage. Tower configuration as described in that report. Handover quarter as stated by Sobha Realty. The hero image is a Sobha Realty rendering of the planned entrance, not a site photograph. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: August 2026.
Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp
This Inspection Cycle
340 Riverside Crescent Construction Progress Summary
The RERA report for the 18 August 2026 inspection describes a tower with its groundwork finished and five packages running in parallel: enabling, foundation and substructure works are completed, while superstructure, internal works, external envelope, MEP and internal finishes progress together. In the DLD register that combination reads 55.02%, up from a previous reading of 42.95% that carries no date.
- Enabling works on the plot
- Foundation works for the tower
- Substructure works, as recorded in the RERA report
- Superstructure works on the 2B+G+3P+52F+Roof tower
- Internal works inside the tower
- External envelope around the frame
- MEP: mechanical, electrical, and plumbing systems
- Internal finishes, recorded as progressing in August 2026
- Completion of the superstructure, envelope, MEP and finishes packages
- Further RERA inspection cycles toward a 100% register reading
- Handover of the 760 residences, scheduled by Sobha Realty for Q4 2027
Payment Linked Progress
What 55.02% Progress Means for 340 Riverside Crescent Buyers
On the 60/40 plan, 40% of the price falls due during construction and 40% on handover, so a 55.02% register reading is not just a status update: it frames how much of the construction 40% your SPA may already call for. At this stage of 340 Riverside Crescent, four actions matter most.
Verify the escrow account
Any payment toward the construction 40% should go only to the DLD regulated escrow account with Emirates NBD registered for project 3082. 340 Riverside Crescent escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.
Reread your SPA payment schedule
Check how your sale and purchase agreement times the construction 40% of the 60/40 plan, and map those clauses against the 55.02% reading of 18 August 2026. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.
Confirm your Oqood registration
Off-plan units in project 3082 are registered with the Dubai Land Department through Oqood; check that the record shows your unit, 340 Riverside Crescent and the price in your SPA before further construction payments. If you are buying from an existing buyer mid-construction, the Oqood transfer is what moves the contract into your name.
Track the next readings
With 44.98 points still to record before 100%, each new DLD reading shows how the envelope, MEP and finishes packages are moving toward the Q4 2027 handover. 340 Riverside Crescent construction updates hub keeps every dated reading in one record.
General framework, not legal advice: payment timing, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.
Buying at 55.02%?
Entering a tower past the halfway mark of its register reading trades part of the payment-plan runway for a structure already on the record: enabling, foundation and substructure works are completed and the superstructure is progressing. Every payment goes to the DLD-registered escrow account for project 3082, released against construction progress recorded in the DLD register.
- Groundwork completed: the inspection record above is the risk picture
- Handover scheduled by Sobha Realty for Q4 2027
- 40% of the 60/40 plan due on handover; the construction share already due is set in your SPA
- Construction risk carried from enabling works to handover
- Two to four years of waiting is the usual delivery horizon
- Full instalment runway, priced at launch levels
4 units listed available on the project page as of this update; availability shifts between cycles.
About the Development
340 Riverside Crescent Project Details

With its substructure completed and the superstructure still progressing, 340 Riverside Crescent is a mid-construction tower of 760 residences in 1, 1.5, 2 and 2.5 bedroom layouts within Sobha Realty's Riverside Crescent cluster. Starting prices: AED 1.23M ≈ USD 334K.
For buyers entering at this stage, the trade off is a shorter wait than at launch against less of the construction 40% left to spread, with handover scheduled by Sobha Realty for Q4 2027.
340 Riverside Crescent by Sobha Realty Project GuideSite Context This Cycle
Explore 340 Riverside Crescent Location on Dubai Map
340 Riverside Crescent is one tower in the six-tower arrangement Sobha Realty describes as a tapered crescent inside Sobha Hartland 2, with unit plans labelling outlooks such as Park View, Meydan Golf Course and the community lagoons. With a 52-floor superstructure still progressing, the rising frame and the external envelope that wraps it are the works most visible from the surrounding community in this cycle.
Sobha Realty's brochure places Downtown Dubai and Meydan Racecourse about 10 minutes from Sobha Hartland 2 and Dubai International Airport about 12, so the tower is rising inside a planned community of schools, clubhouses and lagoons while staying within short reach of established city districts. For buyers at this mid-construction stage, that access already exists, while the tower itself still has its envelope and interiors to complete before the Q4 2027 handover. See the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Buyer Resources for This Project
Investing in 340 Riverside Crescent During Mid-Construction Progress
Past the halfway mark, payment protection and residency planning outweigh handover logistics. Each resource below is matched to where 340 Riverside Crescent stands at 55.02%.

340 Riverside Crescent Construction Updates
This page: the 18 August 2026 DLD reading for 340 Riverside Crescent and its RERA notes.

340 Riverside Crescent Golden Visa: Eligible Apartments and Residency Requirements
Explore 340 Riverside Crescent Golden Visa eligibility, qualifying apartment layouts, off-plan application timing, Oqood registration and complimentary VIP processing.
Read 340 Riverside Crescent Golden Visa Guide
340 Riverside Crescent Escrow Account: DLD and Bank Verification
Verify 340 Riverside Crescent escrow account details, Emirates NBD banking information and DLD registration before making off-plan property payments.
Verify 340 Riverside Crescent Escrow AccountUpdate Timeline
Other 340 Riverside Crescent Construction Updates
August 2026 is the first monthly report for 340 Riverside Crescent; each later inspection the DLD register records will join this timeline as its own dated update.
Where This Update Fits
Explore 340 Riverside Crescent Structure
This monthly report is one node in a wider record: the Sobha Hartland 2 community around the tower, Sobha Realty as the developer building it, and the listings competing with it.

Sobha Hartland 2 Properties for Sale: Riverside Crescent and Skyscape Apartments
Explore Sobha Hartland 2 properties for sale, comparing Riverside Crescent and Skyscape apartments, payment plans, handover dates and availability.
See Sobha Hartland 2 Properties for Sale
Sobha Hartland 2: A Swimmable Lagoon Master Community in Bukadra
Sobha Hartland 2 is Sobha Realty's second MBR City master community, with 15 named projects around a swimmable lagoon.
Explore the Sobha Hartland 2 Community
Sobha Realty: In-House Construction, From High-Grade Materials to the Façade Panels
Sobha Realty controls every stage of construction itself, from producing high-grade materials to the marble flooring and façade panels.
View the Sobha Realty Developer ProfileFAQs
340 Riverside Crescent Construction Progress in August 2026: Frequently Asked Questions
340 Riverside Crescent recorded 55.02% construction progress in the Dubai Land Department register at the inspection dated 18 August 2026, under DLD project number 3082 with the project status Active. The figure is a register reading: the RERA progress report for the same date describes the works but prints no percentage of its own.
Nothing in the August 2026 record moves it. Sobha Realty schedules handover for Q4 2027, the RERA report of 18 August 2026 lists the main contract as progressing without setting or revising any date, and this report quotes no registered completion date from the DLD record. A developer can still revise a handover date, so the quarter is Sobha Realty's to confirm. Successive readings toward handover are collected in one dated record at 340 Riverside Crescent construction updates.
The DLD app's inspection card for 18 August 2026 shows 42.95% as the previous inspection beside the current 55.02%, but it does not display when that earlier reading was taken. Without that date no monthly pace can be measured between the two figures, so this report limits its pace figures to whole-build arithmetic from the 10 May 2024 construction start.
The RERA progress report for 18 August 2026 records enabling, foundation and substructure works as completed, with superstructure works, internal works, external envelope, MEP and internal finishes progressing. It describes the building as two basements, ground, three podium levels, 52 floors and a roof, and the register record also carries inspection photographs, which are not reproduced on this page.
No. The image at the top of this page is a Sobha Realty rendering of the planned entrance marked 340 Riverside Crescent, used to identify the project, and it does not show the state of the site on 18 August 2026. The construction position on this page comes from the DLD register reading and the RERA progress report, not from any image.
On the 60/40 plan for 340 Riverside Crescent, buyers pay a 20% down payment, 40% during construction and 40% on handover, but how much of the construction 40% is already due at the 55.02% stage recorded on 18 August 2026 is set in each SPA. The plan card gives no instalment dates or milestone triggers, so ask Sobha Realty for the schedule that applies to your unit before signing.
A Question the FAQ Can Not Answer?

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is helping you read the August 2026 inspection record for 340 Riverside Crescent correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.