Sobha Realty · Sobha Hartland 2
340 Riverside Crescent Construction Updates
The Dated Register Record of a 52-Floor Riverside Crescent Tower
340 Riverside Crescent read 55.02% in the DLD register on 18 August 2026, a climb from the May 2024 start that puts the tower past halfway.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
340 Riverside Crescent at a Glance
340 Riverside Crescent is one of the six towers Sobha Realty arranges as a tapered crescent in Sobha Hartland 2, registered with the Dubai Land Department as project 3082 and planned for 760 residences. Construction started on 10 May 2024, and the one dated reading so far is 55.02% on 18 August 2026. Because the RERA report describes one building, 52 floors over three podiums, a ground floor and two basements, every figure below tracks one tall frame rather than a cluster of low-rise buildings averaged together.
3082
Active
10 May 2024
760 residential units
58,059.57 sq m
Q4 2027 (developer handover)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
340 Riverside Crescent Construction Update Timeline
This record holds one dated reading for 340 Riverside Crescent: 55.02%, entered in the Dubai Land Department register for the 18 August 2026 inspection. The same inspection card shows a previous reading of 42.95% without a date, 12.07 points lower, so it sits on the track below as a dot with no row of its own. Two dated milestones open the record, the construction start on 10 May 2024 and the registration on 29 May 2024, while the far end of the track is the handover Sobha Realty schedules for Q4 2027.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| August 2026 | 55.02% | 18 August 2026 | View the August 2026 update |
Pace Analysis
How Fast 340 Riverside Crescent Has Been Built
A measured pace needs two dated inspections, and 340 Riverside Crescent has one: the previous 42.95% reading carries no date. The register's own dates still support two figures, both arithmetic, not a forecast:
- 10 May 2024 to 18 Aug 2026: whole-build average, construction start to 55.02%About 1.99 points per month
- 18 Aug 2026 to 31 Dec 2027: rate that would reach 100% by the end of Q4 2027About 2.70 points per month
Set side by side, the two figures describe a gap rather than a verdict. Spread over the 830 days between the 10 May 2024 start and the August reading, 55.02 points work out at about 1.99 per 30-day month; the 44.98 points still to record would need about 2.70 per month to land inside the 500 days left before 31 December 2027. Both are arithmetic, not a forecast. The DLD register logs readings and sets no timetable; a 52-floor tower seldom climbs in a straight line, because the envelope, MEP, finishes and fit-out that dominate its later stages move the percentage at their own rate; and only Sobha Realty can confirm the Q4 2027 handover date. The 18 August 2026 RERA report already shows five packages running at once on this tower, from superstructure to internal finishes, so no single monthly rate yet describes its curve. For an end user, the figure worth waiting for is the next dated reading, which gives this record its first measured pace; for an investor, the distance between 1.99 and 2.70 is the question to put to Sobha Realty before relying on Q4 2027.
Get the Next Inspection Figure First
Tell me you are tracking 340 Riverside Crescent and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About 340 Riverside Crescent at Sobha Hartland 2
A 55.02% reading from 18 August 2026 only means something against what is being delivered: 760 residences in four layout types inside a 52-floor tower. The full project guide covers what buyers on this page are tracking toward:

340 Riverside Crescent by Sobha Realty: Apartments in Sobha Hartland 2
Explore 340 Riverside Crescent apartments by Sobha Realty in Sobha Hartland 2, including prices, floor plans, payment plan and availability.
View the 340 Riverside Crescent Project GuideConsidering a Mid-Construction Entry?
Availability at 340 Riverside Crescent shifts from one inspection cycle to the next. If the record on this page is what brought you here, ask me what is currently available and how an entry at today's stage fits the 60/40 plan.
Ask About Remaining Availability on WhatsAppStage Record
340 Riverside Crescent Build Stages, Mapped to the Inspections
Each stage below is anchored to what the DLD register and the 18 August 2026 RERA report actually record for 340 Riverside Crescent, so the windows run from the May 2024 start through the 55.02% reading to the Q4 2027 handover.
Construction Start and Registration
The register dates the start of construction to 10 May 2024 and the registration of project 3082 to 29 May 2024.
Enabling, Foundation and Substructure
By the 18 August 2026 inspection the RERA report lists enabling, foundation and substructure works as completed for the two-basement base of the tower.
Superstructure and External Envelope
Superstructure works and the external envelope were both progressing on 18 August 2026, when the register read 55.02% against an undated previous 42.95%.
MEP, Internal Works and Finishes
MEP, internal works and internal finishes were already recorded as progressing in August 2026, alongside the frame of the 52 floors and three podium levels.
Completion and Handover of 760 Residences
The remaining 44.98 points to 100% close this stage; Sobha Realty schedules handover for Q4 2027, a date that is the developer's to confirm.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on 340 Riverside Crescent's own record.
Buyer Position
Tracking Your Position at 340 Riverside Crescent
This page is one of four project resources that together cover a 340 Riverside Crescent purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

340 Riverside Crescent Construction Updates
This page: the dated DLD register record for 340 Riverside Crescent, from May 2024 to handover.

340 Riverside Crescent Golden Visa: Eligible Apartments and Residency Requirements
Explore 340 Riverside Crescent Golden Visa eligibility, qualifying apartment layouts, off-plan application timing, Oqood registration and complimentary VIP processing.
Read the 340 Riverside Crescent Golden Visa Guide
340 Riverside Crescent Escrow Account: DLD and Bank Verification
Verify 340 Riverside Crescent escrow account details, Emirates NBD banking information and DLD registration before making off-plan property payments.
Verify the 340 Riverside Crescent Escrow AccountApproaching Handover
Between 55.02% and Handover: What 340 Riverside Crescent Buyers Should Do Now
At 55.02% on 18 August 2026, 340 Riverside Crescent is in the construction period of its 60/40 plan, with the superstructure and envelope still progressing and 44.98 points left to record. How much of the construction 40% is already due at today's stage is set in each SPA, so the three steps below belong before your next instalment, not after the next reading arrives.
First, check that every payment toward the construction 40% goes to the Emirates NBD escrow account registered for project 3082; the 340 Riverside Crescent escrow account page sets out how to confirm it.
Second, map your SPA payment schedule against the dated record: the August 2026 inspection report for 340 Riverside Crescent lists what was completed and what was progressing when the register read 55.02%.
Third, if you hold or are weighing a 2 or 2.5 bedroom unit, settle residency questions while the tower is still being built through the Golden Visa eligibility guide for 340 Riverside Crescent, since eligibility turns on the purchase price recorded for your unit.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Sobha Hartland 2 Structure
One tower's reading is easier to judge beside what surrounds it. These three pages set the 55.02% recorded at 340 Riverside Crescent on 18 August 2026 against the Sobha Hartland 2 market, its community and the developer building it:

Sobha Hartland 2 Properties for Sale: Riverside Crescent and Skyscape Apartments
Explore Sobha Hartland 2 properties for sale, comparing Riverside Crescent and Skyscape apartments, payment plans, handover dates and availability.
See Sobha Hartland 2 Properties for Sale
Sobha Hartland 2: A Swimmable Lagoon Master Community in Bukadra
Sobha Hartland 2 is Sobha Realty's second MBR City master community, with 15 named projects around a swimmable lagoon.
Explore the Sobha Hartland 2 Community
Sobha Realty: In-House Construction, From High-Grade Materials to the Façade Panels
Sobha Realty controls every stage of construction itself, from producing high-grade materials to the marble flooring and façade panels.
View the Sobha Realty Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
340 Riverside Crescent Construction Updates Frequently Asked Questions
340 Riverside Crescent is an active Dubai Land Department project, number 3082, recorded at 55.02% in the DLD register at the inspection of 18 August 2026. The RERA progress report of that date lists the main contract as progressing, with superstructure works, external envelope, MEP and internal finishes underway; the dated record is in the inspection timeline above.
One so far. The record for 340 Riverside Crescent holds a single dated DLD register reading, 55.02% on 18 August 2026, plus a previous reading of 42.95% that the inspection card shows without a date, so that figure sits on the progress track as a dot and has no table row. The full report for the dated inspection is the August 2026 construction update for 340 Riverside Crescent, and each later dated reading joins this page as its own row.
The Dubai Land Department register dates the construction start at 340 Riverside Crescent to 10 May 2024 and the registration of project 3082 to 29 May 2024, 19 days later; both dates are shown here exactly as recorded. The first dated reading in this record came 830 days after the start, at 55.02% on 18 August 2026.
Between the 10 May 2024 start and the 55.02% reading of 18 August 2026, a span of 830 days, 340 Riverside Crescent has averaged about 1.99 percentage points per 30-day month in the DLD register. No reading-to-reading pace can be measured yet because the previous 42.95% reading is undated; the arithmetic, which is not a forecast, is set out in the pace analysis above.
Sobha Realty schedules handover of 340 Riverside Crescent for Q4 2027, and this record quotes no registered completion date. Reaching 100% by 31 December 2027 from 55.02% on 18 August 2026 would take about 2.70 points per month over 500 days, against a whole-build average of about 1.99. Treat both as arithmetic, not a forecast: the register logs readings without setting a timetable, a tower's later finishing and fit-out work seldom moves the percentage at the pace of its frame, and confirming the handover date rests with Sobha Realty.
340 Riverside Crescent is planned for 760 residences in 1, 1.5, 2 and 2.5 bedroom layouts. The RERA progress report of 18 August 2026 records a configuration of two basement levels, a ground floor, three podiums, 52 floors and a roof (2B+G+3P+52F+Roof), and the DLD register read 55.02% on that date. Layouts and prices sit in 340 Riverside Crescent's project guide.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the 340 Riverside Crescent construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.