Sobha Realty · Sobha Hartland 2
360 Riverside Crescent Construction Updates
The Dated Register Record of a 66-Floor Sobha Hartland 2 Tower
360 Riverside Crescent read 50.67% in the DLD register on 16 September 2026, with foundations recorded as completed and its 66-floor frame still climbing toward Q4 2027.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
360 Riverside Crescent at a Glance
360 Riverside Crescent is Sobha Realty's tower of 891 residences in Sobha Hartland 2, registered with the Dubai Land Department as a project of its own, number 3079, so every register figure on this page describes this one building. The register dates its construction start to 10 May 2024, nineteen days before the project's registration on 29 May 2024, and twenty-eight months after that start it recorded 50.67% on 16 September 2026 for a frame the RERA progress report describes as 2B+G+5P+66F+Roof.
3079
Active
10 May 2024
891 residences
71,796.14 sq m
Q4 2027 (developer handover)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
360 Riverside Crescent Construction Update Timeline
The 360 Riverside Crescent record holds one dated reading so far: 50.67% on 16 September 2026, the first cycle published on this site, twenty-eight months after the May 2024 start. The register also lists a previous inspection at 42.85% without a date, so it sits on the track as an undated dot and has no table row. The table links the full September 2026 update, whose header image is a developer rendering of the project rather than a site photograph; the same holds for every image on this page.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| September 2026 | 50.67% | 16 September 2026 | View the September 2026 update |
Pace Analysis
How Fast 360 Riverside Crescent Has Been Built
With a single dated reading, the 360 Riverside Crescent pace can only be read as arithmetic from the recorded start, not as a measured curve between inspections. Two figures frame it:
- May 2024 to Sep 2026: whole-build average from the 10 May 2024 start, 50.67 points over 859 daysAbout 1.77 points per month
- Sep 2026 to Dec 2027: rate that 100% by 31 December 2027 would need, 49.33 points over 471 daysAbout 3.14 points per month
Neither figure is a forecast. The first folds the enabling and foundation period, which the September 2026 report records as completed, into one twenty-eight-month average; the second assumes Q4 2027 closes on 31 December 2027, and both use 30-day months. The undated 42.85% reading would show the recent climb, but without its date no measured pace exists yet: the next dated reading will be the first that can be set against 16 September 2026. For an end user planning a move and an investor weighing the construction 40% in the SPA, the useful step is to confirm the current handover timetable with Sobha Realty and compare it with that next DLD figure.
Get the Next Inspection Figure First
Tell me you are tracking 360 Riverside Crescent and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About 360 Riverside Crescent at Sobha Hartland 2
A register percentage only means something next to what is being built. The project guide covers the tower this record follows:

360 Riverside Crescent: 891 Sobha Apartments in Sobha Hartland 2
360 Riverside Crescent by Sobha Realty features 891 residences in Sobha Hartland 2, offering 1 to 2.5 bedroom apartments.
View the 360 Riverside Crescent Project GuideConsidering a Mid-Construction Entry?
Availability at 360 Riverside Crescent shifts from one register cycle to the next while the tower is mid-build. If this record is what brought you here, ask me for current availability before you settle on a unit type.
Ask About Remaining Availability on WhatsAppStage Record
360 Riverside Crescent Build Stages, Mapped to the Inspections
Each stage below is pinned to the dates and the single reading in 360 Riverside Crescent's own record, so the two May 2024 register anchors and the 50.67% of September 2026 show where the tower sits in its sequence.
Construction Start and DLD Registration
The register records construction starting on 10 May 2024 and project 3079 registered on 29 May 2024, the two dated anchors before any tracked reading.
Enabling and Foundation Works
The RERA report of 16 September 2026 lists the enabling and foundation works as completed, the only package it closes out for this tower; the record does not date their completion.
Superstructure, Envelope and MEP Under Way
At 50.67%, the report shows superstructure and substructure, external envelope and MEP works advancing in parallel on the 2B+G+5P+66F+Roof frame, each at its own stage, while mobilization continues.
Internal Works and Finishes
Internal works and finishes already show as progressing in September 2026; carrying them through the residences is part of the 49.33 points the register still has to record.
Completion and Handover
Handover of the 891 residences is stated for Q4 2027; the closing register readings and completion procedures come first, and this record will carry each of them.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on 360 Riverside Crescent's own record.
Buyer Position
Tracking Your Position at 360 Riverside Crescent
This page is one of four project resources that together cover a 360 Riverside Crescent purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

360 Riverside Crescent Construction Updates
This page: the dated DLD register record for 360 Riverside Crescent since its May 2024 start.

360 Riverside Crescent Golden Visa: From 1.5 Bedroom Apartments
360 Riverside Crescent by Sobha Realty in Sobha Hartland 2 meets the Golden Visa threshold from 1.5 bedroom apartments upward.
Read the 360 Riverside Crescent Golden Visa Guide
360 Riverside Crescent Escrow at Emirates NBD, DLD Project 3079
360 Riverside Crescent's 891 residences use Emirates NBD escrow under DLD project 3079, with 50.67% progress recorded in September 2026.
Verify the 360 Riverside Crescent Escrow AccountApproaching Handover
Between 50.67% and Handover: What 360 Riverside Crescent Buyers Should Do Now
At 50.67% on 16 September 2026, 360 Riverside Crescent is inside the construction 40% of its 60/40 plan, and each buyer's SPA, not the register, decides when those payments fall due. A payment notice can therefore arrive between two published readings, so the three checks below belong before it rather than after it.
First, confirm that every construction-stage payment is going to the Emirates NBD escrow account registered for project 3079; the 360 Riverside Crescent escrow account page shows how to check it against the DLD record.
Second, if residency is part of the plan, settle it before choosing a unit type: the 360 Riverside Crescent Golden Visa guide sets out which types reach the threshold and why the purchase value registered with the DLD decides eligibility.
Third, read each new register figure against this record; the 360 Riverside Crescent September 2026 construction update holds the full report notes behind the 50.67% of 16 September 2026, and later months join the timeline above as they publish.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Sobha Hartland 2 Structure
A build record is only half the picture; the other half is what surrounds it. These three pages set the 360 Riverside Crescent register record in its market, community and developer context:

Sobha Hartland 2 Properties for Sale: Riverside Crescent and Skyscape Apartments
Explore Sobha Hartland 2 properties for sale, comparing Riverside Crescent and Skyscape apartments, payment plans, handover dates and availability.
See Sobha Hartland 2 Properties for Sale
Sobha Hartland 2: A Swimmable Lagoon Master Community in Bukadra
Sobha Hartland 2 is Sobha Realty's second MBR City master community, with 15 named projects around a swimmable lagoon.
Explore the Sobha Hartland 2 Community
Sobha Realty: In-House Construction, From High-Grade Materials to the Façade Panels
Sobha Realty controls every stage of construction itself, from producing high-grade materials to the marble flooring and façade panels.
View the Sobha Realty Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
360 Riverside Crescent Construction Updates Frequently Asked Questions
360 Riverside Crescent is an active DLD-registered project, number 3079, recorded at 50.67% in the Dubai Land Department register on 16 September 2026. The RERA progress report of that date gives the status as Main Contract, Progressing, with enabling and foundation works completed and the superstructure, envelope and MEP progressing; the full record is in the inspection timeline above.
The DLD register reading dated 16 September 2026 put 360 Riverside Crescent at 50.67%, 7.82 points above the previous register reading of 42.85%, which the record shows without a date. Because that earlier reading is undated, the gain cannot be spread over a period; the detail behind the figure is in the 360 Riverside Crescent September 2026 inspection notes.
Completion of 360 Riverside Crescent is stated for Q4 2027, and the register record reviewed here shows no completion date of its own. From the 10 May 2024 start, 50.67 points over 859 days averages about 1.77 points per month; reaching 100% by 31 December 2027, taken as the end of Q4 2027, needs 49.33 points over 471 days, about 3.14 points per month. Both figures are arithmetic, not a forecast, and buyers should confirm the current timetable with Sobha Realty; the workings are in the pace analysis above.
360 Riverside Crescent holds 891 residences in 1, 1.5, 2 and 2.5 bedroom apartment types. The RERA progress report of 16 September 2026 describes the configuration as 2B+G+5P+66F+Roof: two basements, a ground floor, five podium levels, 66 floors and a roof, the frame that the 50.67% register reading of that date measures.
The Dubai Land Department register records construction at 360 Riverside Crescent as started on 10 May 2024 and the project as registered on 29 May 2024, nineteen days later. The first reading tracked on this site, 50.67% on 16 September 2026, came 859 days after that start.
Each figure for 360 Riverside Crescent comes from the Dubai Land Department register for project 3079, read in the Dubai REST app, alongside the RERA progress report for the same inspection date. That report prints no percentage of its own, so 50.67% on 16 September 2026 is the register figure, and this page adds a row each time a new dated reading is published. The general method is set out in the Dubai Construction Updates methodology.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the 360 Riverside Crescent construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.