Address Residences at Dubai Creek Harbour Construction Updates
The Register Record of an Address Tower Rising Across the Channel from Central Park
Address Residences stood at 26.44% on the 4 May 2026 DLD register reading, its frame climbing above completed foundations toward the expected Q1 2029 handover.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Address Residences at Dubai Creek Harbour at a Glance
Address Residences at Dubai Creek Harbour is Emaar's Address-branded tower of 324 residential units on the eastern side of the masterplan, facing Central Park across the inner channel. The DLD registered the project on 20 August 2024, construction started on 11 December 2024, and the register reading of 4 May 2026 put it at 26.44%, with handover expected in Q1 2029. One detail sets this record apart: the register's own completion date, 31 January 2029, falls inside that expected quarter and in the same month Emaar's schedule gives the final 20% instalment, so the official dates and the buyer's payment calendar point at the same finish line.
3229
Active
11 December 2024
324 Residential
33,616.39 sq m
31 January 2029 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Address Residences at Dubai Creek Harbour Construction Update Timeline
The Address Residences record holds one dated reading so far: 26.44% on 4 May 2026, entered in the DLD register 509 days after the 11 December 2024 construction start. The register also lists a previous inspection at 16.82% but attaches no date to it, so that reading appears on the track below as a dot without a month and stays out of the table, whose single row links the full May 2026 update.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| May 2026 | 26.44% | 4 May 2026 | View the May 2026 update |
Pace Analysis
How Fast Address Residences at Dubai Creek Harbour Has Been Built
With only one dated reading on file, Address Residences has no measured pace between inspections yet. What the record does support is arithmetic across the registered build window, set out below and labelled as such:
- 11 Dec 2024 to 4 May 2026: foundations and early frame, from the registered start to 26.44% over 509 daysAbout 1.56 points per 30 days (arithmetic)
- 4 May 2026 to 31 Jan 2029: remaining frame, envelope, MEP and finishes, 73.56 points over 1,003 days to the registered completionAbout 2.20 points per 30 days needed (arithmetic)
- Undated previous inspection to 4 May 2026: 16.82% to 26.44%+9.62 points, no pace without a date
Read together, the two averages describe the shape the next readings need to take rather than a verdict on the first one. The 509 days to May 2026 absorbed enabling, piling and foundation works, which the RERA report of 4 May 2026 lists as complete, and work below ground moves a register percentage slowly. The 2.20 points per 30 days implied for the rest of the window would come from floors, envelope and fit-out, trades that the same report already shows running together on the lower levels while the frame climbs toward its 35 floors. Neither figure is a forecast, and neither signals a delay or an early finish. For an end user, the test is whether the next dated readings climb faster than 1.56 points per 30 days as the frame rises; for an investor, those same readings decide when the plan's 40% construction milestone, and the 10% instalment tied to it, falls due.
Get the Next Inspection Figure First
Tell me you are tracking Address Residences at Dubai Creek Harbour and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Address Residences at Dubai Creek Harbour
A register percentage means little without the building behind it. The project guide covers what each Address Residences reading is tracking toward:

Address Residences at Dubai Creek Harbour: An Address-Branded Emaar Tower
Address Residences at Dubai Creek Harbour is an Emaar tower of 324 apartments and three bedroom townhouses carrying the Address name.
View the Address Residences at Dubai Creek Harbour Project GuideConsidering a Mid-Construction Entry?
Limited units are available at Address Residences, and the cost of entering shifts as construction-linked instalments fall due behind the rising frame. If the record on this page is what brought you here, ask me for current availability and where a unit would sit against the payment schedule today.
Ask About Remaining Availability on WhatsAppStage Record
Address Residences at Dubai Creek Harbour Build Stages, Mapped to the Inspections
Each stage below is pinned to the register dates and RERA notes that place it in the Address Residences record, so the windows are this tower's own, from a 20 August 2024 registration to a 26.44% reading on 4 May 2026 and onward to Q1 2029.
Registration and Site Mobilization
DLD registration of project 3229 on 20 August 2024, on plot 285 in Al Khairan First, then the registered construction start of 11 December 2024, 113 days later.
Enabling, Piling and Foundations
The below-ground stage beneath the tower: enabling, piling and foundation works, every one of them listed as complete when RERA inspected on 4 May 2026.
Structure Rising Above the Podium
The frame was climbing toward the "B + G + 2P + 35 Floors + Mechanical Roof" configuration in the IPMR when the register read 26.44%, with the report's photographs showing climbing screens near its upper floors.
Envelope, MEP and Interiors
Already started on the lower levels by 4 May 2026, these trades carry the build through the plan's 40%, 60% and 80% construction milestones, which Emaar estimated for Jan 2027 to Mar 2028.
Completion and Handover
Final works and handover, expected in Q1 2029 against a registered completion date of 31 January 2029, when the plan's last 20% instalment falls due at 100% completion.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Address Residences at Dubai Creek Harbour's own record.
Buyer Position
Tracking Your Position at Address Residences at Dubai Creek Harbour
This page is one of four project resources that together cover a Address Residences at Dubai Creek Harbour purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Address Residences at Dubai Creek Harbour Construction Updates
This page: the DLD register record for Address Residences, from the December 2024 start to handover.

Address Residences at Dubai Creek Harbour Golden Visa: Exactly on the Line
Emaar's Address Residences at Dubai Creek Harbour, 324 units, qualifies at every type, the 1 bedroom exactly at the threshold.
Read the Address Residences at Dubai Creek Harbour Golden Visa Guide
Address Residences at Dubai Creek Harbour Escrow, Held at Emirates NBD
Emirates NBD holds Address Residences at Dubai Creek Harbour escrow, DLD project 3229, 326 units, certified 26.44% in May 2026.
Verify the Address Residences at Dubai Creek Harbour Escrow AccountApproaching Handover
Between 26.44% and Handover: What Address Residences at Dubai Creek Harbour Buyers Should Do Now
The 4 May 2026 reading places Address Residences past the plan's 20% construction milestone and short of its 40% one, so this stretch is about the instalments still tied to the frame rather than handover logistics. In Emaar's schedule of record the next trigger is that 40% milestone, worth 10% of the price, and it falls due when the milestone is reached under your SPA rather than on its calendar estimate, so the three steps below belong before a reading crosses 40%.
First, check the payment instructions for that instalment against the Emirates NBD escrow account registered for project 3229; the Address Residences escrow account page explains how to confirm it on the DLD record.
Second, if residency is part of your plan, settle where your unit's registered price sits against the Golden Visa threshold now, while the purchase is held under Oqood; the Address Residences Golden Visa guide covers the 1 Bedroom's zero margin at AED 2.00M ≈ USD 545K.
Third, read each register reading in full as it publishes, starting with the Address Residences May 2026 construction update, so your SPA milestones are checked against recorded progress rather than calendar estimates.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Dubai Creek Harbour Structure
A single tower's record reads better in context. These three pages set Address Residences against its community, its developer's portfolio and the wider Dubai Creek Harbour market:

Dubai Creek Harbour Properties for Sale
Browse waterfront apartments, branded residences and penthouses for sale in Dubai Creek Harbour.
See Dubai Creek Harbour Properties for Sale
Dubai Creek Harbour: Emaar's Waterfront City With a Marina and Urban Beach
Dubai Creek Harbour is Emaar's waterfront city between Downtown Dubai and the Creek, planned for 48,500 homes with skyline views.
Explore the Dubai Creek Harbour Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Address Residences at Dubai Creek Harbour Construction Updates Frequently Asked Questions
Address Residences at Dubai Creek Harbour is under construction: DLD project 3229 is Active, and the register reading of 4 May 2026 recorded 26.44%, with foundations complete and the frame rising. Handover is expected in Q1 2029. Every reading on file is set out in the Address Residences inspection timeline above.
One. The DLD register reading of 4 May 2026 recorded Address Residences at 26.44%, 9.62 points above a previous inspection reading of 16.82% that the register shows without a date. Because only the May 2026 figure is dated, it is the record's single table row, and the inspection detail behind it is in the Address Residences May 2026 register reading page.
"Main Contract - Progressing" is the progress status that the RERA Independent Progress Monitoring Report of 4 May 2026 gives Address Residences: the label places the project in its main construction contract, past the enabling stage, with that contract active on the inspection date. It is a status, not a percentage; the 26.44% figure for the same date comes from the DLD register.
As of the RERA report of 4 May 2026, enabling, piling and foundation works at Address Residences were complete. Still under way on that date were the tower's structure, at different levels, together with internal works, the external envelope, MEP services and internal finishes, while site mobilization was listed as ongoing. The DLD register put overall progress at 26.44% on the same day.
"Address Residences l Dubai Creek Harbour" is how the DLD register records Address Residences at Dubai Creek Harbour, project 3229; the "l" is the register's separator between the brand and the community name. Searching Dubai REST by project number 3229 finds it reliably, with status Active and a reading of 26.44% dated 4 May 2026.
Yes. The DLD register gives Address Residences a completion date of 31 January 2029, which falls inside the Q1 2029 quarter in which handover is expected and matches the Jan 2029 estimate in Emaar's schedule for the final 20% instalment. On 4 May 2026, when the register read 26.44%, that date was 1,003 days away and had not lapsed.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Address Residences at Dubai Creek Harbour construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.