Emaar Properties · Emaar Beachfront
Beach Vista at Emaar Beachfront Construction Updates
The Closed Build Record for Two Delivered Towers on Emaar Beachfront
Beach Vista reached 100% construction at its 26 December 2021 RERA inspection, the reading that closed the Dubai Harbour record with snagging the only work still running.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Beach Vista at Emaar Beachfront at a Glance
Beach Vista is Emaar Properties' pair of residential towers on plot 3650 in Marsa Dubai, 466 apartments on the Emaar Beachfront peninsula inside Dubai Harbour. Three years and nine months separate the 19 March 2018 construction start from the 100% certified on 26 December 2021, and the anchors below are the DLD register entries behind that span. What makes this record unusual is how short it is: one dated inspection closes it, because by the time the file was written the register was already carrying project 2015 as Finished.
2015
Finished
19 March 2018
466 residential units
55,406.02 sq m
06 January 2022 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Beach Vista at Emaar Beachfront Construction Update Timeline
One dated inspection carries this record: 26 December 2021, when RERA certified Beach Vista at 100% and project 2015 was left standing as Finished on the DLD register. The same file names a previous reading of 98.33%, but no date is attached to it anywhere, so the track below plots the closing reading alone. The row underneath links the full December 2021 report.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| December 2021 | 100% | 26 December 2021 | View the December 2021 update |
Reading the dates: the DLD-registered completion date for project 2015 is 06 January 2022, and the inspection of 26 December 2021 had already recorded 100% eleven days before it. That date is an administrative anchor set at registration rather than a delivery promise, and it has since lapsed with the register reading Finished and a RERA Progress Status of Completed.
Pace Analysis
How Fast Beach Vista at Emaar Beachfront Has Been Built
Pace is usually the most useful thing an inspection record hands a buyer. On Beach Vista it is the one thing the record withholds, and the reason is worth knowing before anyone quotes a rate of progress for project 2015:
- Previous reading to the closing inspection: 98.33% to 100%Plus 1.67 points, earlier date not recorded
- Construction start 19 Mar 2018 to certification 26 Dec 2021Three years and nine months on the register
Two progress figures sit in the December 2021 file and only one of them carries a date. The 1.67 points between 98.33% and the certified 100% is a documented gain, but with no date against the earlier reading there is no interval to divide it by, so no honest monthly rate for Beach Vista exists to be published. What the record does show is the shape at the end. Dubai Civil Defence clearance was obtained on 19 September 2021 and the building completion certificate came from DDA on 28 September 2021, three months ahead of the inspection that closed the file. Certificates in hand while the last points were being worked off is the sequence a buyer wants, because it means the approvals were not being chased after the building was already being handed over. For anyone reading this in 2026 that matters more than velocity: the open question at Beach Vista is no longer how quickly it was built, but what condition a specific finished apartment is in.
Get the Next Inspection Figure First
Tell me you are tracking Beach Vista at Emaar Beachfront and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Beach Vista at Emaar Beachfront
A closed build record only means something next to what was actually delivered. The project guide covers the apartments behind the 100% on this page:

Beach Vista at Emaar Beachfront, a Twin-Tower Dubai Harbour Address
Beach Vista at Emaar Beachfront holds 466 Emaar apartments of one to four bedrooms in two towers above a pool podium.
View the Beach Vista at Emaar Beachfront Project GuideConsidering a Completed Beachfront Apartment?
Beach Vista has been carried as Finished since December 2021, so what is left is remaining stock rather than a launch list, and availability shifts between cycles. If the record on this page is what brought you here, ask for what is open before the better placed apartments go.
Ask About Remaining Availability on WhatsAppStage Record
Beach Vista at Emaar Beachfront Build Stages, Mapped to the Inspections
Every stage below is tied to a date the record actually carries for project 2015 rather than to a generic construction sequence, so the Beach Vista history reads as the register and the December 2021 inspection wrote it.
Registration and Construction Start
The Dubai Land Department registered project 2015 on 10 January 2018, and construction was recorded as started on 19 March 2018 on plot 3650 in Marsa Dubai.
Two Towers Above a Shared Podium
The inspection file describes Tower 1 as ground, mezzanine, five podium levels, 33 floors and two roof levels, Tower 2 the same to 26 floors, plus apartments across podium levels P1 to P4.
Civil Defence and Completion Clearances
Dubai Civil Defence clearance was obtained on 19 September 2021 and the building completion certificate from DDA on 28 September 2021, with DEWA meters installed and connected.
The Previous 98.33% Reading
The December 2021 file names a previous inspection figure of 98.33%. No date is attached to it in the report or in the DLD project record, so it cannot be placed in sequence against the dates above.
Closing Inspection, Snagging and Deep Cleaning
RERA recorded all building construction activities substantially completed and certified 100%, with snagging and deep cleaning the only works still progressing at site on that date.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Beach Vista at Emaar Beachfront's own record.
Buyer Position
Tracking Your Position at Beach Vista at Emaar Beachfront
This page is one of four project resources that together cover a Beach Vista at Emaar Beachfront purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Beach Vista at Emaar Beachfront Construction Updates
This page: the closed inspection record for Beach Vista, certified at 100% on 26 December 2021.

Beach Vista at Emaar Beachfront Golden Visa: 466 Apartments on Title Deed
All four apartment tiers at Beach Vista at Emaar Beachfront, Emaar Properties' island development in Dubai Harbour, clear the threshold individually.
Read the Beach Vista at Emaar Beachfront Golden Visa Guide
Beach Vista at Emaar Beachfront: An Emirates NBD Escrow Certified in Full
Emirates NBD held Beach Vista at Emaar Beachfront escrow, DLD project 2015, 466 units, 100% certified December 2021.
Verify the Beach Vista at Emaar Beachfront Escrow Account
Beach Vista at Emaar Beachfront Snagging on the Dubai Harbour Island
Beach Vista at Emaar Beachfront is an Emaar Properties development of 466 freehold apartments in two towers over a shared podium.
Book Beach Vista at Emaar Beachfront SnaggingApproaching Handover
Between 100% and Handover: What Beach Vista at Emaar Beachfront Buyers Should Do Now
The construction question at Beach Vista was answered on 26 December 2021, which changes what due diligence looks like here. Nothing on this page has to be waited for: the three checks below all belong to the stretch between choosing an apartment and signing for it, and on a building that is already standing that stretch is usually short.
First, arrange independent defect documentation before you accept the apartment. The Beach Vista snagging inspection page sets out what gets inspected and why the rectification window on this building runs from its 2021 completion rather than from the day you move in.
Second, confirm where the money goes against the DLD record. The Beach Vista escrow account page names the Emirates NBD trust account registered to project 2015 and how the entry is checked before any transfer is made.
Third, if residency is part of the purchase, settle eligibility early through the Beach Vista Golden Visa guide, because a completed property follows a different application path from an off plan one and the title deed timing sits at the centre of it.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Emaar Beachfront Structure
A build record is only half the picture; the other half is the island it was built on. These three pages put the Beach Vista inspection file into its community, market and developer context:

Emaar Beachfront Properties for Sale
Browse apartments and penthouses for sale in Emaar Beachfront, Dubai's private beach community in Dubai Harbour.
See Emaar Beachfront Properties for Sale
Emaar Beachfront: A Private-Beach Island Community Inside Dubai Harbour
Emaar Beachfront holds 27 residential towers and around 10,000 homes along a private beachfront, with two marinas, retail and dining.
Explore the Emaar Beachfront Community
Emaar Properties: Burj Khalifa, Downtown Dubai and Twenty Master Communities
Emaar, founded in 1997, built Burj Khalifa and Downtown Dubai and has delivered over 85,000 homes across twenty master communities.
View the Emaar Properties Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Beach Vista at Emaar Beachfront Construction Updates Frequently Asked Questions
Beach Vista at Emaar Beachfront is carried as Finished on the Dubai Land Department register for project 2015, with construction certified at 100% by the RERA inspection of 26 December 2021 and a RERA Progress Status of Completed. That single dated reading is the whole of the progress record, and it is set out in the inspection timeline above.
The inspection of 26 December 2021 certified 100%, a rise of 1.67 points on the previous recorded reading of 98.33%. The record attaches no date to that earlier figure, so the gain is documented but the period it covers is not. The underlying report is published in the December 2021 construction update for Beach Vista.
No. A points per month figure needs two dated readings, and project 2015 carries only one: 100% on 26 December 2021. The 98.33% previous inspection appears without a date in the inspection file and in the DLD project record, so any rate of progress quoted for Beach Vista would be invented rather than computed. The reasoning is set out in the pace analysis above.
The registered completion date for project 2015 is 06 January 2022, and the inspection of 26 December 2021 had already recorded 100% eleven days before it. Because the register now reads Finished with a RERA Progress Status of Completed, that date is a closed administrative anchor rather than an outstanding target, and no revised completion date exists anywhere in the record.
The DLD project register records 466 units for project 2015, released as one, two, three and four bedroom apartments across two delivered towers on plot 3650 in Marsa Dubai. The same total is carried on the Beach Vista at Emaar Beachfront project guide, so the registered figure and the marketed figure agree.
The Dubai Land Department registered project 2015 on 10 January 2018 and recorded the construction start on 19 March 2018. Three years and nine months later, on 26 December 2021, the RERA inspection certified the build at 100%. No dated progress reading exists between those two dates.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Beach Vista at Emaar Beachfront construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.