Imtiaz Developments · Island A, Dubai Islands
Beach Walk Grand Construction Updates
The DLD Register Record of One Furnished Building on Island A
Beach Walk Grand read 53.22% in the DLD register on 10 August 2026, a climb clearing every below-ground stage and moving into frame, finishes and MEP.
Construction tracking against RERA inspection data, updated after every recorded inspection.
Direct advisor access. Every message answered personally, never by a call center.
Construction Snapshot
Beach Walk Grand at a Glance
Beach Walk Grand is the single G+2P+12+R residential building of 112 furnished residences that Imtiaz Developments is building on Island A at Dubai Islands. Its register record is short and exact: construction started on 25 December 2024, DLD project 3367 was registered on 30 December 2024, and the one dated reading so far, 53.22% on 10 August 2026, arrived 593 days into the build. With one building rather than a cluster of phased towers, every reading on this page describes the whole project at once, not an average across separate blocks.
3367
Active
25 December 2024
112 residential units
13,314.49 sq m
25 December 2026 (DLD)
Figures from Dubai Land Department registration records, updated after each recorded inspection. How every project on this site is tracked is explained once on the Dubai Construction Updates hub.
Inspection Record
Beach Walk Grand Construction Update Timeline
This record holds a single dated reading: 53.22% in the Dubai Land Department project register on 10 August 2026. The same register entry lists a previous inspection at 44.65% with no date attached, so that figure appears on the track as an undated marker rather than as a table row. The two readings sit 8.57 points apart, a spread that cannot be placed in time because the earlier reading is undated. The table row opens the August 2026 update, where the notes from that inspection are set out in full.
| Inspection Month | Construction Progress | Inspection Date | Full Update |
|---|---|---|---|
| August 2026 | 53.22% | 10 August 2026 | View the August 2026 update |
Pace Analysis
How Fast Beach Walk Grand Has Been Built
With one dated reading and one undated, Beach Walk Grand has no measured pace between inspections yet. What the record does support is arithmetic between three register dates, shown here as averages, not as phases:
- 25 Dec 2024 to 10 Aug 2026: construction start to the dated reading of 53.22%, over 593 daysAbout 2.69 points per month (average)
- 10 Aug 2026 to 25 Dec 2026: 53.22% to 100% by the registered completion date, over 137 daysAbout 10.24 points per month (needed)
Neither number describes how the site is actually moving. The 2.69 figure spreads 53.22 points evenly across 593 days, yet the 10 August 2026 notes show the below-ground stages finished while the frame, internal works, finishes and MEP were running at the same time inside one building, so an even split by month is a convenience of the maths, not a picture of the work. The 10.24 figure is only what the remaining 46.78 points would require if spread across the 137 days to the 25 December 2026 registered completion date. Both are arithmetic, not a forecast, and neither replaces the Q4 2026 handover stated for the project. For an end user planning a move, the figure that matters is the next dated reading; for an investor, that same reading creates the first dated pair, and this section will then show a measured pace in place of these averages.
Get the Next Inspection Figure First
Tell me you are tracking Beach Walk Grand and I will send you the next recorded figure and site photos directly, ahead of the page update.
Get the Next Update on WhatsAppProject Profile
About Beach Walk Grand at Island A
A register reading of 53.22% on 10 August 2026 only means something next to what the building will hold. The project guide covers the 112 furnished residences this record is tracking toward:

Beach Walk Grand: Furnished Imtiaz Homes on Island A
Beach Walk Grand by Imtiaz is a building of 112 fully furnished apartments and penthouses on Island A at Dubai Islands.
View the Beach Walk Grand Project GuideConsidering a Mid-Construction Entry?
Beach Walk Grand is listed with Limited Units Available, and with the frame still in progress, the entry terms change from one cycle to the next. If the record on this page is what brought you here, ask me for current availability and the amount due at signing before you decide.
Ask About Remaining Availability on WhatsAppStage Record
Beach Walk Grand Build Stages, Mapped to the Inspections
With a single dated reading, the windows below are bounded by three register dates rather than a run of inspections: the 25 December 2024 start, the 53.22% reading of 10 August 2026, and the 25 December 2026 registered completion date. Each stage shows where Beach Walk Grand stood against them.
Construction Start and DLD Registration
The register records construction starting on 25 December 2024 and project 3367 being registered on 30 December 2024, the two dates that open this record.
Enabling, Piling and Foundations
Enabling, piling and foundation works are all listed as completed in the 10 August 2026 inspection notes for the Island A plot.
Substructure Complete, Superstructure in Progress
With the substructure recorded complete, the superstructure of the ground floor, two podium parking levels, 12 residential floors and roof was progressing at the 53.22% reading.
Internal Works, Finishes and MEP
Internal works, internal finishes and MEP works were also progressing in the same 10 August 2026 inspection, running in parallel with the frame rather than after it.
Furnished Fit-Out and Handover
Furnishing and handover of all 112 residences remain ahead, with handover expected in Q4 2026 and a registered completion date of 25 December 2026.
What each construction stage involves in general is covered once in the guides on the Dubai Construction Updates hub, so this page stays focused on Beach Walk Grand's own record.
Buyer Position
Tracking Your Position at Beach Walk Grand
This page is one of four project resources that together cover a Beach Walk Grand purchase from payment protection to residency to handover. You are on the construction record; the siblings sit one click away:

Beach Walk Grand Construction Updates
This page: the DLD register record for Beach Walk Grand, from its December 2024 start onward.

Beach Walk Grand Golden Visa: Three Types on Dubai Islands
Imtiaz Developments' Beach Walk Grand, 112 fully furnished residences on Island A, lists all three unit types above the threshold.
Read the Beach Walk Grand Golden Visa Guide
Beach Walk Grand Escrow: Imtiaz Developments on Dubai Islands
Imtiaz Developments' Beach Walk Grand is DLD project 3367, 112 units escrowed at First Abu Dhabi Bank, 53.22% certified August 2026.
Verify the Beach Walk Grand Escrow AccountApproaching Handover
Between 53.22% and Handover: What Beach Walk Grand Buyers Should Do Now
Beach Walk Grand's 60/40 plan runs on dates rather than readings: its last dated instalment fell due on 15 July 2026, so the one payment still ahead for existing buyers is the 40% due on completion, tied to the handover expected in Q4 2026. Because that balance and the handover appointment arrive together, the three steps below are worth settling in the months before the notice, not in the days after it.
First, make sure every payment, the 40% completion balance included, is directed to the First Abu Dhabi Bank trust account for project 3367, using the Beach Walk Grand escrow account check before any transfer.
Second, if residency matters to you, read the Beach Walk Grand Golden Visa eligibility notes now, since the route open to you can differ before and after the title deed is issued.
Third, follow the record that produced the 53.22% figure: the Beach Walk Grand August 2026 inspection report holds the stage notes from 10 August 2026, and each later dated reading joins the timeline on this page.
Send me your unit number on WhatsApp and I will tell you what the latest inspection means for your handover and map the sequence for your specific unit.
The Wider Picture
Explore Island A Structure
Beach Walk Grand is one building in a district that is still filling in, so its record reads best beside the island and the developer around it. These three pages set its 112 residences in that Island A and Imtiaz context:

Island A: Four Imtiaz Projects, From Furnished Apartments to Marina-Front Penthouses
Island A is the urban waterfront core of Dubai Islands, with furnished apartments, duplexes and penthouses across four Imtiaz projects.
See Island A Properties for Sale
Island A Community Overview
Read the full Island A guide: the island's role in the Dubai Islands masterplan, property types, connectivity and pricing.
Explore the Island A Community
Imtiaz Developments: Fully Furnished Residences in Dubai Islands, JVC and Meydan
Imtiaz Developments, founded in 2011, has completed and under-construction design led residential projects in Meydan, JVC and Dubai Islands.
View the Imtiaz Developments Developer ProfileConstruction tracking for other Dubai projects is indexed on the Dubai Construction Updates hub.
FAQs
Beach Walk Grand Construction Updates Frequently Asked Questions
The Beach Walk Grand record for DLD project 3367 holds one dated reading, 53.22% on 10 August 2026, plus an earlier register reading of 44.65% that is shown without a date. Around it sit three register dates: construction start on 25 December 2024, registration on 30 December 2024, and a registered completion date of 25 December 2026. The inspection timeline lays these out in order.
Beach Walk Grand progress is tracked through the Dubai Land Department project register for project 3367, which gave 53.22% on 10 August 2026. Stage detail comes from the RERA Independent Progress Monitoring Report of the same date, which describes the work by stage and states no percentage, so every figure on this page is a register reading. Each dated reading has its own monthly page, starting with the Beach Walk Grand construction update for August 2026.
Yes, the two fall in the same quarter: the registered completion date for Beach Walk Grand in the DLD record is 25 December 2026, and handover is expected in Q4 2026. The registered date is the anchor set when project 3367 was registered, and it had not passed when the 53.22% reading of 10 August 2026 was taken. Handover itself is confirmed by Imtiaz Developments as final works complete, and this page's record is updated as later readings are added.
Beach Walk Grand has no measured pace yet, because only one of its two register readings is dated. As arithmetic, not a forecast: 53.22 points over the 593 days from the 25 December 2024 start to 10 August 2026 average about 2.69 points per month, and reaching 100% by the 25 December 2026 registered completion date would take about 10.24 points per month over the remaining 137 days. The pace analysis sets out both figures.
G+2P+12+R is how the RERA inspection report describes Beach Walk Grand: a ground floor, two podium parking levels, 12 residential floors and a roof level, all in one residential building. The developer's brochure gives the same stack, and its floor plans place the gym, club room and swimming pool on the 1st floor and private penthouse terraces with an infinity pool at roof level.
Beach Walk Grand is being built with 112 residences: 1 Bedroom Apartments, 2 Bedroom Apartments and 3 Bedroom Penthouses, every one sold fully furnished according to the developer, in a single G+2P+12+R building on Island A. At the 53.22% register reading of 10 August 2026, the building holding those 112 homes had its substructure complete and its superstructure in progress.

Your Advisor
Tohid Fetrat
Independent of the developer: I work for the buyer, and my only job on this page is keeping the Beach Walk Grand construction record accurate, inspection by inspection, until handover, walking the site personally each inspection period. Client identities and transactions are never published or referenced. Message or call me directly: you will always reach me personally, never a call center or sales team.
Ask your question, get your answer. No obligation and no follow-up unless you ask for it.