Beach Walk Residence 4 by Imtiaz in Island A at Dubai Islands project rendering used for the August 2026 construction update showing the planned rooftop swimming pool, curved building balconies and surrounding landscaping in Dubai - Presented by Tohid Fetrat

Imtiaz Developments · Island A, Dubai Islands · Construction Update

Beach Walk Residence 4 by Imtiaz Construction Update - August 2026

August 2026 DLD Register Places Beach Walk Residence 4 at 42.87% Construction Progress on Island A

Substructure, superstructure, internal works and MEP were progressing at Beach Walk Residence 4 when RERA inspected on 13 August 2026, with foundations recorded as completed.

Direct advisor access. Every message answered personally, never by a call center.

42.87%DLD Register Progress
13 August 2026Inspection Date
Q2 2027Expected Completion
3707DLD Project Number

DLD Register and RERA Inspection Data

Beach Walk Residence 4 Construction Snapshot

An 8.73 point rise on the previous DLD reading, which the register shows without a date, places Beach Walk Residence 4 in the superstructure stage, where the record tracks the frame, internal works and building services advancing together, well before the finishing stage.

Project Name

Beach Walk Residence 4 by Imtiaz

Project Number

3707

Project Status

Active

Construction Progress

42.87%

Inspection Date

13 August 2026

Construction Start

20 April 2025

Total Units

70 residences

Total Built Area

7,874.82 sq m

Expected Completion

Q2 2027

Data source: DLD project register reading of 42.87% shown against the inspection dated 13 August 2026, with site notes from the RERA Independent Progress Monitoring Report of the same date. The image at the top of this page is a developer rendering of the planned building, not a view of the site. Construction tracking against RERA inspection data runs across the full tohidfetrat.com project portfolio and is reviewed after every published cycle. Last updated: August 2026.

Want each new reading the day it publishes? Message me on WhatsApp and I will send it to you directly: one message per inspection cycle, nothing else. Message me on WhatsApp

This Inspection Cycle

Beach Walk Residence 4 Construction Progress Summary

At the 13 August 2026 inspection, RERA recorded the ground works at Beach Walk Residence 4 as closed out: enabling, piling and foundations were completed, while the substructure, the superstructure, internal works and MEP were all progressing on the single G+2P+8+R building. The DLD register reading of 42.87%, following a previous 34.14% that carries no date, puts the building just short of halfway to 100% on the register, with handover expected in Q2 2027.

Completed
  • Enabling works across the plot
  • Piling works
  • Foundation works
In Progress at 42.87%
  • Substructure works
  • Superstructure of the G+2P+8+R residential building
  • Internal works
  • MEP works: mechanical, electrical and plumbing
Ahead of Handover
  • Internal and external finishes specified for the concrete and block structure
  • Further DLD register readings toward 100%
  • Handover of the 70 residences, expected in Q2 2027
Next inspectionPosted in the DLD project register after the next RERA site visit; no date is published in advance, so none is given here.
Completion targetHandover expected in Q2 2027; the DLD register carries a registered completion date of 20 April 2027, 250 days after the 13 August 2026 inspection.
Remaining distance57.13 percentage points separated the 13 August 2026 reading from 100%.

Dated Payments, Recorded Progress

What 42.87% Progress Means for Beach Walk Residence 4 Buyers

Beach Walk Residence 4 runs on a 60/40 plan fixed to calendar dates rather than site milestones, so a register reading does not trigger an instalment: it shows what the dated payments have bought so far. At the 13 August 2026 reading, booking plus four dated instalments, 45% of the price, had fallen due against 42.87% recorded in the DLD register. At this stage, four actions matter most.

Before Every Instalment

Verify the escrow account

Every instalment should go only to the DLD regulated escrow account registered for project 3707 with First Abu Dhabi Bank; the project is listed in the register as Beach Walk Residences 4 By Imtiaz. Beach Walk Residence 4 escrow account verification is the step before any transfer; the lookup itself takes about two minutes against the official DLD project record.

Before the Next Due Date

Reread your SPA payment schedule

Check how your sale and purchase agreement dates the instalments that followed this reading, 10% on 15 October 2026 and 5% on 15 March 2027, and how it defines the 40% due on completion, then map those clauses against the Q2 2027 handover. Not sure how your instalments map to this reading? Send me your SPA schedule and I will map it against the recorded milestones.

After Booking

Confirm your Oqood registration

Once booking is settled, an off plan unit at Beach Walk Residence 4 is recorded on the DLD interim register, known as Oqood, against project 3707. Confirm the entry carries your name and unit number before the next dated instalment, since it is the record your title deed is typically issued from at handover.

Every Cycle

Track the remaining cycles

With 57.13 points between the August 2026 reading and 100%, several more register readings will post before the Q2 2027 handover. The Beach Walk Residence 4 construction updates hub logs each one as it is published.

General framework, not legal advice: payment dates, notice periods, and fee obligations are set by your individual SPA and the DLD record, and both should be read directly.

Buying at 42.87%?

Entering a building mid-construction trades part of the launch runway for a record you can read: the ground works are closed out and the superstructure is on the register. Every instalment goes to the DLD-registered escrow account for project 3707, released against construction progress.

Entering Now at 42.87%
  • Enabling, piling and foundation works recorded as completed on 13 August 2026
  • Handover expected in Q2 2027
  • 40% of the 60/40 plan due on completion; instalments already dated are settled at signing, per the developer's current terms
Typical Launch Entry
  • Construction risk carried from excavation onward
  • A delivery horizon of two to four years is common
  • Longest instalment runway, priced at launch levels
AED 2.38M ≈ USD 647KStarting Price
60/40 Plan40% Due on Completion
Q2 2027Expected Handover
Ask What Is Available at Beach Walk Residence 4

06 Units Available listed on the project page as of this update; availability shifts between cycles.

About the Development

Beach Walk Residence 4 Project Details

Beach Walk Residence 4 by Imtiaz in Island A at Dubai Islands project rendering of a mid-rise residential building with curved balconies, rooftop greenery and landscaped podium in Dubai - Presented by Tohid Fetrat
Island A, Dubai Islands · Imtiaz Developments

With foundations recorded as completed and the superstructure progressing at the 13 August 2026 inspection, Beach Walk Residence 4 is a mid-construction G+2P+8+R building of 70 furnished apartments and 3 bedroom duplexes on Island A. Starting prices: AED 2.38M ≈ USD 647K.

For buyers entering at this stage, the trade off is a shorter wait than at launch against a larger share of the price already called by the dated schedule, with 40% held until completion and handover expected in Q2 2027.

Beach Walk Residence 4 by Imtiaz Project Guide

Site Context This Cycle

Explore Beach Walk Residence 4 Location on Dubai Map

The developer's brochure places Beach Walk Residence 4 about a five minute walk from the beach on Island A at Dubai Islands, and its Points of Interest map sets Mall by Nakheel beside the plot. On a compact building of ground, two podium levels, eight residential floors and a roof, the substructure, superstructure, internal and MEP works recorded on 13 August 2026 all run inside one footprint, so each register reading describes a single structure rather than an average across towers.

The same brochure describes Dubai Islands as a five island plan with 21 km of beachfront, nine marinas, six of them on Island A, and 1.98 million square metres of parks and open space, with Infinity Bridge and the Waterfront Market about five minutes away by car. For a buyer at 42.87%, the practical question is how much of that plan around the plot will be operating by the Q2 2027 handover; see the project's position on the interactive Dubai real estate map. See the project’s position on the interactive Dubai real estate map.

Interactive Dubai real estate map preview
Click to view Beach Walk Residence 4 on Dubai Map

Buyer Resources for This Project

Investing in Beach Walk Residence 4 at the Superstructure Stage

At 42.87%, with the price still being paid on fixed dates, the questions that matter are residency timing and where each instalment is held. Each resource below is matched to that point in the build.

Beach Walk Residence 4 by Imtiaz in Island A at Dubai Islands construction updates cover image featuring a project rendering of a residential building with rounded balconies and illuminated landscaped grounds at dusk in Dubai - Presented by Tohid Fetrat
You Are Here

Beach Walk Residence 4 Construction Updates

This page: the 13 August 2026 register reading and inspection notes for this Island A building.

Beach Walk Residence 4 by Imtiaz in Island A at Dubai Islands Golden Visa concept graphic featuring a gold card over a rendering of rounded residential balconies and landscaped gardens in Dubai - Presented by Tohid Fetrat

Beach Walk Residence 4 Golden Visa: Four Types Above the Line

Beach Walk Residence 4, 70 Imtiaz residences on Island A, sits above the threshold at all four unit types.

Read Beach Walk Residence 4 Golden Visa Guide
Beach Walk Residence 4 by Imtiaz in Island A at Dubai Islands escrow account concept graphic featuring a shield and padlock above a rendering of the landscaped residential entrance in Dubai - Presented by Tohid Fetrat

Beach Walk Residence 4: The Fourth Beach Walk Escrow on Island A

Beach Walk Residence 4 escrows 70 units at First Abu Dhabi Bank, DLD project 3707, certified 42.87% in August 2026.

Verify Beach Walk Residence 4 Escrow Account

Update Timeline

Other Beach Walk Residence 4 Construction Updates

August 2026 is the first monthly report on file for Beach Walk Residence 4, so the timeline starts here; each later register reading is added to the hub as it posts.

All Beach Walk Residence 4 Construction Updates

FAQs

Beach Walk Residence 4 Construction Progress in August 2026: Frequently Asked Questions

The DLD project register shows Beach Walk Residence 4, project 3707, at 42.87% against the inspection dated 13 August 2026, up from a previous reading of 34.14% that the register displays without a date. The RERA inspection report of the same date prints no percentage of its own, so 42.87% is the register figure for this cycle.

Yes, as of this update. Handover is expected in Q2 2027, and the DLD register carries a registered completion date of 20 April 2027, which falls inside that quarter and sat 250 days after the 13 August 2026 inspection. Registered dates can be revised between readings, and any revision would be logged on the Beach Walk Residence 4 construction updates hub when it appears in the record.

The DLD app lists 34.14% as the previous inspection beside the 13 August 2026 reading of 42.87%, but it shows no date for that earlier figure. Without a date the gap between the two readings cannot be converted into a monthly pace, so this report treats 34.14% as a reference point only, not as the start of a measured period.

The Independent Progress Monitoring Report dated 13 August 2026 recorded enabling, piling and foundation works as completed, with substructure, superstructure, internal works and MEP works progressing at the site. It describes the project as a G+2P+8+R residential building with a concrete structure, block work and internal and external finishes, and it carries inspection photographs that are not reproduced on this page.

The DLD register records construction as started on 20 April 2025 and the project as registered on 02 May 2025, 12 days later. Both dates are shown here exactly as the register carries them, and the 13 August 2026 reading came 480 days after the recorded start.

No. The image at the top of this page is a developer rendering of the planned building, supplied as the visual for the August 2026 update, and no construction progress can be read from it. The state of the site on 13 August 2026 is described only by the DLD register reading and the RERA inspection notes.

A Question the FAQ Can Not Answer?

Portrait of Tohid Fetrat, Dubai real estate advisor and portfolio manager with expertise in luxury developments

Your Advisor

Tohid Fetrat

Independent of the developer: I work for the buyer, and my only job on this page is helping you read the August 2026 inspection record for Beach Walk Residence 4 correctly before your next payment decision. Client identities and transactions are never published or referenced. Message me directly: you will always reach me personally, never a call center or sales team.

Ask your question, get your answer. No obligation and no follow-up unless you ask for it.

Get Progress Alerts